Types of Contracts (2)
Types of Contracts (2)
Types of Contracts (2)
Mode of execution
PPP
EPCC.
Item Rate Contracts
Nature of Agreement :
An item rate contract is one in which the contractor agrees to carry
out the work as per drawings, bills of quantities and specifications in
consideration of a payment to be made entirely on measurements
taken as the work proceeds, and at the unit – prices tendered by the
contractor in the bill of quantities.
A bill of quantities is prepared giving, as accurately as possible, the
quantities of each item of work to be executed and the contractor
enters the unit rate against each item of work.
The basis of agreement in thus the unit-rate of each item, certain
reasonable variation in the quantities being accepted by both parties.
The two parties are not bound by the total value of work. They are
bound by each individual rates
The bidders fill in the rate column for each of the item.
The rate or unit price includes the contractor’s overheads and profits.
For new items of work, not in original schedule, the rates need to be
separately negotiated.
Contract Documents :
All the documents as mentioned earlier are in variably included in the
agreement.
(g) What the owner pays to the contractor is the actual cost of the
work at the agreed rates. This arrangements is fair to both the
parties.
Disadvantage :
(a) The owner cannot be absolutely sure of the total cost to him , until
the work is completed. In case the quantities mentioned in the bill
are found to be inaccurate the cost of the work will vary considerably
from the estimated cost. If the actual cost increases the owner may
be put in the financial difficulty leading to even suspension of the
work.
(b) Both the owner and the contractor have to do considerable
computation and book-keeping during the progress of the work. Both
the parties are required to appoint staff to record the measurements
of the work done.
(c ) As the quantities are likely to vary there is a possibility of the
contractor submitting an unbalanced tender on the basis of shrewd
anticipation or perhaps outside information. If the contractor’s
anticipation proves to be correct the owner would stand to lose
heavily. A contract of this nature therefore requires very careful
scrutiny and consideration by a skillful and experienced engineer or
architect before it is entered into.
(d) The ‘extra items’ are often a source of trouble.
(e) Can lead to huge cost escalations
Front Loading
The contractor may put a higher rate for works to be completed
earlier, and a lower rate for ending items.
This ensures that contractor becomes cash rich upfront, and can
manage his working capital better.
However if the bid is heavily front loaded, contractor may run
away, after completing the profitable items.
Suitability of Item rate Contract :
The item rate contracts are widely used in the execution of large
works financed by the public bodies or the government. This form of
contract is suitable for the works which can be split into separate
items and the quantity under each item can be estimated with
reasonably accuracy.
With careful scrutiny to avoid acceptance of an unbalanced tender
this type of contract can be conveniently used for the works which
are unsuited to the lump sum contracts.
Percentage Rate Contract
Another type of measurement contract.
• Documents
• Same as item rate, only rate column of BOQ filled by owner and
not bidder
• Mode of payment
• Same as item rate
Lump Sum
Contracts
Nature of agreement :
In a lump sum contract the contractor agrees to carry out the entire
work as shown in drawings and described by specifications, supplying
labour and materials, all for a specified lump sum.
The value of the works is estimated by the contractor based on the
drawings and specifications provided.
The lump sum amount can be decided by negotiation or competitive
bidding.
Sometimes the agreement makes provision to adjust the ‘fixed sum’
allowing for the cost of extra work, variation , omission, etc.
The main features of the agreement is that the contractor agrees to
fulfill all his contract obligation for the stipulation payment no matter
what trouble and expenses he encounters in doing so.
Even though the fixed price is for the total completion of job, working
capital management becomes difficult if there is no interim payment.
(a)If no extras are contemplated the tenders tell him exactly what the
project will cost him. This is a sound footing on which he can take
the decision whether to start the project or abandon the same.
(b) He need not employ the staff to keep periodical accounts of the
contractor’s materials, labour and output. All that the engineer
has to do on his behalf is to see that the work is being executed
exactly according to the terms of the contract and issue interim
certificates to the contractor.
To make a contract, find out who can and will tackle the job and
make an agreement regarding the percentage to be paid to the
contractor.
This contract is also known as “time and lime” (i.e. labour and
material) contract.
Cost Plus Fixed Fee Contracts
In the cost plus fixed fee contract, the contractor is reimbursed the
actual cost incurred by him on materials and labour and is given a
fixed amount of money as his fee.
The contractor receives only the stipulated sum for his part in
overseeing and doing the job, no matter what the cost of the project
may be.
Under this form of contract, the employer can easily select a reliable
contractor to execute the work. The parties can work in harmony and
accomplish amazingly fine results.
The cost-plus –fixed –fee contract differs from the cost-plus
percentage type contract in respect of determination of the fee to be
paid to the contractor to cover overheads and profit.
The agreement specifies the fixed lump sum to be paid to the
contractor by the owner over and above the actual cost of the work.
The fee does not fluctuate with the actual cost of the work, This
factor overcomes the possible weakness of the cost-plus-percentage
type contract.
However, there is no incentive for the contractor to do the work
efficiently and effect economy in the cost of construction of the work.
If the fixed fee is to include the salaries of the contractor’s staff the
contractor will try to complete the work as speedily as possible so as
to make maximum profit.
In respect of all other points this form of contract is similar to the
cost-plus-percentage type contract.
Cost-Plus-Fluctuating Fee
Contract
By introducing an element of incentive for the contractor to carry out
the work in the most economic way an attempt is made in this form
of contract to overcome the main drawback of the previous two types
of cost-plus contracts.
This is achieved by suitably changing the nature of the agreement in
respect of the fee is determined by reference to some form of sliding
scale. Thus higher the actual cost, lower will be the value of the fee
that the contractor receives and vice versa.
From owner’s point of view this is one of the best of the ‘cost-plus’
type contract.
Contract Documents
6. Maintenance Shop
Contractor shall be permitted free use of these facilities for the entire
duration of the Work.
Payments
a) Staff Salaries.
b) Common Site expenses.
c) Plant and Equipment.
d) Tools and Tackles and Staging materials.
e) Direct labour
f) Material, if any
g) Mobilisation and Demobilisation charges
h) Supply of Material and Sub-contract work to be carried out through
specialised agencies.
i) Engineering and Design fees.
a) Staff Salaries :
Contractor shall in consultation and agreement with client, promptly
deploy
at site adequate number of experienced staff and augment same
from time to time.
Any demobilisation of Contractor’s staff also shall be done by
Contractor
in consultation and agreement with Client.
All of the above shall be payable from the date the Personnel reports
to Site and upto the date the Personnel is demobilised from Site upon
completion of his assignment.
These charges exclude cost of the following
1. Electricity/Water
2. Mess Expenses at site
3. Printing & Stationery
4. Books & Periodicals
5. Rates & Taxes
6. Local Conveyance
7. Car Hire Charges
8. Telephone, Postage, Telex & Telegram/Fax/Satellite link Charges
etc. Telephones at the residences of Contractors personnel shall be
as
per Company Policy of the Contractor.
9. Travel Expenses ( as per Company Policy of the Contractor )
10.Courier Expenses
11. Codes and Standards for Engineering and Construction.
12. Rent.
13.Repairs and Maintenance of office equipment
14.Repairs and Maintenance of temporary facilities and
accommodation.
15.Safety Helmets ,Safety belts & other approved safety items.
16.Security
17.Hotel and Guest House expenses
18.Statutory Charges.
19.Insurance Charges.
20.Unfurnished residential accommodation as per general policy of
the
Contractor
Client may, at its option, provide any of the facilities for Contractor 's
use and arrange for direct payment to third parties as applicable.
Client shall procure and supply to Contractor all the necessary Tools,
Tackles and Staging materials as described below as Free Issue.
1. Scaffolding Material.
2. Grinding Machines.
3. Hand tools such as Chisels, Hammers , Levels, Measuring tapes, etc.
4. Lifting Belts and Slings.
5. D Shackles , Chain Pulley Blocks , Tun Buckles etc.
6. Files
7. Dumpy levels, Theodolites, etc.
8. Welding Helmets and accessories such as Aprons, Gloves, welding
goggles, Dark
/white glass, etc.
9. Cutting sets, Heating Torches, etc.
10.Spanners , Torque wrenches, etc.
11.Vibrator Needles,
12.Shovels, Pickaxes, Crowbars, etc.
13.Buffing Machines.
14.Pipe Threading Machines , pipe bending machines etc.
15.Meggars, etc.
Contractor shall provide all necessary services related to determining
the
requirement, specification and timely procurement of same.
In rare cases where such Tools, Tackles and Staging materials are not
available in the market due to delivery constraints but are available
with the Contractor , then the same shall be mobilised by the
Contractor for the duration until such time the Tools, Tackles and
Staging materials ordered by Client are received.
In case of the use of the Contractor owned Tools, Tackles and Staging
materials at site then Client shall reimburse to the Contractor the
charges for the use of the same.
The charges for use shall be mutually agreed upon between Client
and the Contractor.
The Contractor shall engage Sub-Contract labour for specific jobs only
on explicit authorisation by Clients Construction Manager(s) and not
otherwise.
Client at its option may also direct the Contractor to procure such materials
from its designated suppliers. The Contractor shall do so and in this event
the Cost of materials shall be reimbursed by Client and this cost shall be
subject to Compensation as agreed in the Agreement.
It is understood and agreed that the Contractor shall not procure any
Materials or Consumables through their other offices on a Branch transfer
basis.
All Materials required for Site jobs will be procured and paid only from closest
available place from the site .
If there are any exceptions, the same shall be procured with prior
g) Mobilisation and Demobilisation charges:
Contractor shall, if required by Client, will arrange for specialised Sub-contract agencies
for supply of materials/services who shall be jointly selected by Contractor and Client.
1. Identify from time to time materials/services for which suppliers and sub- Contractors
are required.
2. Finalise Vendor(s)/Sub-contractor(s) list.
3. Evolve procedure/strategy for selection of Vendors/Sub-contractors for each of the
identified specialised materials and services.
4. Select Vendor(s)/Sub-contractor(s).
Contractor, shall be paid cost of such works/services or supplies (inclusive of all taxes,
duties whether payable by the Sub- contractor or by Contractor and freight charges).
i) Engineering and Design fees:
The Contractor shall submit overall construction organisation chart along with
resumes for Clients Construction Manager’s review and approval and
accordingly take steps to mobilise the personnel. The organisation chart shall
be reviewed from time to time and additional mobilisation or demobilisation of
persons as required shall be effected by the Contractor.
If in the opinion of Client , any of the Contractor’s staff is found unsuitable for
the assigned job, the Contractor shall take immediate steps to demobilise and /
or replace with alternate person.
DEFECT LIABILITY.
The cost of such rectification work, including cost of any free issue
materials supplied by Client for this purpose shall be recovered from
Contractor .
The recovery of cost of free issue material shall in the aggregate not
exceed 5% ( Five percent ) of the amount of Compensation received by the
Contractor for the relevant scope of work.
Reinforcement Non-recoverable
steel wastage allowance 0.5%
The amount of such recovery shall be withheld from the payment due under
compensation which shall be reconciled every six months.
COMPENSATION.
Till the submission of R.A.Bill and reconciliation of Free issue material, any payment
released on weekly fund replenishment basis or otherwise shall be treated as
advance to Contractor in clients Books of Accounts.
The Contractor will submit reconciliation of free issue Materials and Consumables
every quarter.
It is clarified that
· where it is stated that it shall form a part of Contractors cost and /or it is stated the
that the cost shall be reimbursed at actuals , it is agreed that this cost shall be
reimbursed by client and shall be subject to Compensation as per the percentage
specified in compensation of the Agreement and paid to the Contractor.
· On the completion of the total work, the compensation shall be adjusted on the
basis of material utilised in the work and no compensation will be paid on the value of
material unutilised and lying in the stock on which compensation has been paid.
EXCISE DUTY, ENTRY TAX AND OTHER STATUTORY
IMPLICATIONS.
a) Excise Duty, Entry Taxes, Sales Tax and Works Contract Tax, Purchase
Tax, Turnover Tax and any other Statutory levies wherever applicable,
presently and due to subsequent changes in laws, enactments, etc., on the
work performed by the Contractor shall be paid by client into Site
Account. In all such cases, no Compensation as per terms of payment will be
applicable.
Contractor shall not effect any such payments without prior approval from
client which approval shall not be unreasonably withheld.
a) To facilitate audit and verification of Cost and material utilisation and cost
at any and all times during the currency of the Project execution,
Contractor shall maintain at Project Site records of all relevant details of
purchase of materials and services, details of materials issued and
utilisation of materials in the aforesaid work, payments to the Suppliers
and/or Sub-contractors and any credits received or recoveries to be made
or made from the Vendors and/or Subcontractors and submit same to
Reliance once in a month.
The Contractor shall give a quarterly declaration along with Cost Statement
that
i) all recoveries & credits received/receivable from their Vendors &
Subcontractors or other Third parties are fully reckoned in the Cost
Statement.
ii) they have not included Service or Management Charge in Cost Statement
on account of any bills from or payment to 3rd parties.
- Material in stock
- Material forming part of work in progress and
- Un-accounted wastage/loss.
-Accounted wastage
d) All scrap, surplus material and salvaged material paid for by client will be
handed over to client by Contractor .
Over and above this, there will be a back charge by client of 50% of
the Amount involved if it is found to be an intentional overcharging by the
Contractor .
Incentive
Contracts
This is an improved version of the guaranteed maximum price
contract.
• These projects include design as well as construction (i.e. Combination of A/E contract &
Prime Contract).
• The owner only provides preliminary conceptual drawings (Front End Engineering) &
specifications during bidding. Detailed Design & Working Drawings (Detailed Engineering)
is done by the contractor as per specifications provided by owner.
•
• A Construction Management Service or a Project Management Consultant may be
employed by owner to check progress and quality of works.
Such a contract may be made on the basis of the cost plus a fixed fee or cost
plus a percentage of the cost or whatever arrangement is satisfactory to the
parties.
In some cases, they even assist in getting the plant into operation in order to
see that everything functions properly.
Under this type of contract, a manufacturer may also undertake to develop the
designs of any piece of equipment and then manufacture it.
The work can be greatly expedited under such contracts as extensive plans
and specifications need not be prepared by the employer. Further , there is no
division of responsibility.
In most cases specifications lay down the performance criteria only. Methods
decided by the contractor.
• An EPC project can be a complex one-of-a-kind product
development, made up of a large number of interconnected
subsystems and components, requiring considerable human
efforts and financial commitment. The EPC activities are time
phased according to specified precedence and resource
requirements and constraints.
Such combined contracts have been advantageously used in industrial projects when
there are specialists in the particular field of endeavor.
In some cases, they even assist in getting the plant into operation in order to see that
everything functions properly.
Under this type of contract, a manufacturer may also undertake to develop the designs
of any piece of equipment and then manufacture it.
The work can be greatly expedited under such contracts as extensive plans and
specifications need not be prepared by the employer. Further , there is no division of
responsibility.
In most cases specifications lay down the performance criteria only. Methods decided by
the contractor.
FIDIC RISK DIAGRAM
RED BOOK- YELLOW BOOK – SILVER BOOK
Increased Increased
Employer's Contractor's
Risk and Increase Risk and Increase
Design Control Project Price, Time
Design Certainty & Cost Certainty
Employer Contract between
Employer & Engineer
(possibly FIDIC White
Book)
Contract
between Engineer
Employer &
Contractor Engineer
administers FIDIC
Contractor Contract on
Behalf of
Employer
Note: Red and Yellow Books use the same
DAB arrangements
Employer
Contract
between
Employer’s
Employer &
Contractor Representative
Contractor
• Commercial Terms can be
• Lump sum
• Item rate
• A combination of both
• Cost plus
• Mode of payment can be
• Measurement Based
• Milestone Base
• Combination of Both
• In case of LSTK (Lump Sum Turn Key), deviation schedule is mandatory
since in absence of all drawings, it is impossible for bidder to estimate the
final cost correctly.
• Hence the bid documents include a BOQ, which contains rates of all items
and initial quantities (estimated by the bidder), used as a back up to arrive
at the Lump sum. The BOQ is revised after all drawings are completed, and
the lump sum fixed based on previous rate.
• In case of unit price EPC contract, the BOQ contains all items of work,
including design services, escalation, etc.
• The quantities and rates are estimated and submitted by the bidders. The
rates are fixed, but quantities may be changed depending on the drawing
(to any extent)
The justification for this system advanced by its advocates is, that it avoids
duplication and the expense of design staff, and enables the contractor, with
specialized knowledge of his own techniques, to design so as to produce
maximum economy, and therefore a leaner price, in a way that an architect
or engineer without knowledge of these techniques would not be able to
produce.
Pubic Private
Partnership
• The contractor undertakes to design, finance , construct ,
operate and maintain the works for a concession period.
•
• The contractor recuperates his cost from the collection of charges
levied on the beneficiaries who use the work and in some cases
annuity payment each year.
• The bidder then works out the cost of financing the project and its
recovery from the collection of toll or similar method till the cost of
construction together with the cost of finance and expected profit is
• The cost of maintenance of the project during the period in question
has also to be added to the basic cost.
• Each year’s income will recover the cumulative investment till the
net becomes zero or negative.
• The concession period worked out by each bidder will depend upon
the cost of construction worked out by each bidder and also the
rate of interest considered for financing the project and expected
profit.
• The bidder who submits the cash flow projections seeking the
minimum period of concession is generally awarded the contract.
• The authorities can provide some grants to bridge the gap known
as viability gap funding.
The bidder expecting the least grant is generally awarded the
contract.
In some cases, the bidders do not need grant, and the cumulative
income from the years of concession fixed by the authority, far
exceeds the total cost.
• Not suitable for works that are not likely to generate capital
for self financing eg. rural water supply projects, village roads
, city roads, etc.
Some of the more common and accepted framework for private
participation
Apart from the above there are also arrangements whereby existing
infrastructure facilities are turned over to private entities for being
modernized or refurbished, operated and maintained, permanently or
for a given period time. Depending on whether the private sector will
own such infrastructure facility, those arrangements are called either
"refurbish-operate-transfer" (ROT) or "modernize-operate-transfer"
(MOT), in the first case; or refurbish-own-operate" (ROO) or
"modernize-own-operate"(MOO) in the latter case.
• The main agreement contains several schedule
describing
• the project site
• project facilities
• site delivery schedule
• design requirements
• construction requirements
• operation and maintenance requirements
• cash flow projections
• annuity / grant payment schedule
• performance security
• state support agreement
• substitution agreement
• hand back requirements
ELEMENTS OF A BOT PROJECT
The various elements that are involved in the BOT projects are
identified as,
a. Project Identification
b. Ownership
c. Operation
d. Finance
Project Identification
The designer can then hire consultants as needed, who report directly
to the designer.
With plans in hand, the project owner gets bids from various
construction firms to construct the building. The project owner picks
the bid they like best and hires the contractor.
Further analysis of change order growth showed that DB projects also have
significantly lower total change order cost growth.
The DB projects took less time, had less cost growth, and were less expensive
to build in comparison to DBB projects.
A study by Penn State found that compared to DBB, DB projects had a six
percent reduction in change orders, delivered 33 percent faster overall, and
cost six percent less.
Reduced Risk: By involving the DB entity throughout design, the design and
construction disciplines are contractually obligated to work together to
complete a design that meets owner needs within constructability and budget
parameters.
The DB entity bears the risk for the design completeness thereby reducing the
need for change orders that can derail budgets and schedules alike.
When schedule is critical to project success and budget is still
unknown, the DB delivery method should be considered. DB relieves
the owner from warranting design documents and mediating
interpretations of those documents.
The main differences between PPC and other contract forms are:
- PPC integrates all project teams under one multi-party agreement
- PPC integrates the contractor as early as possible
Integrated team
The owner, the designer, the constructor and even some specialists
and subcontractors may be part of such agreement.
Placing all participants at the same level and binding them under the
same terms and conditions is very useful to unify their targets and
avoid any possible conflicts that might affect the project.
Early involvement
PPC integrates the owner, the designer, and the constructor in one
multi-party agreement.
These partners should also establish one team for jointly managing
the project. Subcontractors, consultants, and other service providers
may also be part of the agreement if the project requires.
The PPC provides a very good opportunity to use the knowledge and
experience of the constructor during the design development stage.
At the same time, the constructor benefit from their contribution in the
design development greatly.
They have the possibility to affect the project design and planning to
match their preferable method of working and their distribution of
resources during the construction stage.
Moreover, since PPC uses an open book policy, the owner and the
constructor will be able to build up their own price estimation and
integrate their profit for the project during that stage.
Joint controls
In such form all participants work under a contract that aligns their
commercial interests with the outcome of the project in which they
share all the pain and the gain.
All parties are requested to operate under full trust, good faith,
integrity and open book policy.
The key factor of alliance contracts is risk sharing. All project risks are
being collectively shared and managed by all the participants. In a
pure alliance all participants:
This means that although the risk is collectively shared but there is a
limit of the financial losses that the NOPs would undertake.
Variations are generally avoided except in specific cases and all the
time and effort spent on them is saved.
This approach avoid the misallocation of some risks into the weakest
party that might happen in the traditional contracting and in return
might have a bad impact of the project outcome.
Where all documentations and reports are available for all other
participants to review and audit if needed.
On the other hand, owner’s open-book record makes it easier for all
NOPs to understand why certain decisions must be taken for the best
interest of the project.
With partnering, aims and goals are agreed upon and dispute resolution
and escalation plans are established, but partners still retain
independence and may individually suffer or gain from the relationship.
With alliancing the alliance parties form a cohesive entity, which jointly
shares risks and rewards to an agreed formula.
Partnering only ties the commercial interests of the partners but it does
not state the way of achieving this interests or the relationships between
them.
Alliance all participants are expected to act in one integrated team and
good-faith is not a behaviour by choice but it is a contractually binding
In alliance trust, integrity and transparency are defining
aspects of the project and all participants commit to work
according to these qualities the moment they enter an alliance.