CONTENTS
CONTENTS SLIDE NO.
Status of Highway Drawings 3
Status of Structure Designs & Drawings 4
Progress V/s Planned – August, 2024 7
Progress V/s Planned – September 1st week 8
Status of Progress 9
Progress of Pipe Culverts 10
Progress of Box Culverts 11
Progress of Bridges 12
Quality and Non compliance/Safety issues 13
Specific observation by IE/Authority – Non Compliance issues 14
RFI Status 15
Source Approvals 16
Material procurement 17
Utility Shifting 18
Borrow area details 19
Project Milestones and Payment Status 20
Site Photographs 21
Raichur-Sindhanur PMC - Weekly Review Meeting 2
Status of Highway Drawings
Submission by
Designs & Reviewed By Status of IE Approved
S No Samarth to SPV Submitted
Drawings PMC Approval /Commented
PMC
Plan and Profile – Submitted to compliance
1 Km 0+000 to Km 40 24-09-2024 25.09.2024 PMC approved Under Review
+ 000 RSHPL (12.11.2024) Lr no 269
Plan and Profile –
PMC Delivered
2 Km 40+000 to Km 04-11-2024 18-11-2024 the Comments
77+032
Lined and Flush Submitted to
3 Drain Status 0+000 20-10.2024 24.10.2024 PMC Approved Under Review
to 40+000 RHSPL (26.10.24) Lr No 239
Rigid Pavement
4 Design Report ( Toll 21-09-2024 23.09.2024 PMC approved Submitted Under Review
Plaza)
Flexible Pavement
Design Report for Approved
5 21-09-2024 23.09.2024 PMC approved Submitted
MCW& Traffic
Survey report
10+000 to 25+000
6 Junction Plan Submitted Under Review
Profile
Submission by Designer to
S. No Chainage (Km) Reviewed By PMC
PMC Remarks
Structural:
Because of high tension line crossing, designer proposed two options and
Structure
provided tentative GADs.
1 31+425 05-07-2024 Arrangement is yet
(1) RCC Voided Slab
to be finalized.
(2) PSC Precast Planks
40+892 , 48+336
19-11-2024
6 49+774 ,55+030 , Under review with PMC
26-11-2024
72+359
D Minor Bridges (Widening)
MNB 39+705 is under review by IE; upon receiving the approval designs
1 39+705 05-09-2024 shall be reviewed.. Concessionaire has submitted Condition survey of
existing bridge to IE on 12-11-2024
E Minor Bridges (Reconstruction)
Submitted
1 25+035 05-09-2024 11.09.2024 Approved Approved
on 18.11.24
Earthwork up to top of Embankment Km 77.032 10.400 4.48 6.52 5.92 3.88 Nill
1 Inprogress
2 Completed
4 Reconstruction of Existing Slab/ Pipe Culverts Into Box 14+530 1 Nos 1 Under Progress 50% RHS Slab Casted
5 Construction of New Box Culverts 17+760 3 Nos 3 Under Progress 56% RHS Slab Casted
Sr No Instruction No Instr Issued date Instruction Isuued Action Taken Instr Closed Date Remarks
on
RFI Summary
2500
2010
2000
1575
1500
1167
1000 887
1.SAIL 1.SAIL
2.TATA 2.TATA
3.RINL 3.RINL
2 Steel 4.Suguna 4.Suguna
5.JSW 5.JSW
6.JSPL (Panther) 6.JSPL (Panther)
1. Fosroc 1. Fosroc
3 Admixture 2.Berger 2.Berger
3.CICO 3.CICO
1.SAPCO BPCL
4 Bitumen 2.Bitcol Bitcol
3.BPCL
DBM Required Quantity from 11+300 to 18+000 & 18+300 to BC Required Quantity from 11+300 to 18+000 & 18+300 to
22+000 22+000
Material Requirement Details Material Requirement Details
DBM BC
Name IN MT Remarks
Name IN MT Remaks
20mm 7617.84382
12mm 9135.36
10mm 2240.5423
6mm 4032.97614 6mm 3425.76
Stone Dust 8065.95228 Stone Dust 9820.512
Lime 448.10846 Lime 456.768
Bitumen 1064.258 Bitumen 1313.208
If SPV fails to cut and transfer the trees within 60 days of getting permission, they'll face penalties. To transport the cut
trees, SPV will need to obtain another permit from the Forest Department.
Thank you
M/s RUKY Projects Private Limited
Flat No 1403A, 14th Floor,
Manjeera Trinity Corporate,
JNTU-HiTech City Road, Kukatpally,
Hyderabad- 500072, Telangana, India
RWANDA
M/s RUKY Projects Private Limited
Remera, Gasabo, Umujyi wa Kigali,
RWANDA