Lecture Note 7
Lecture Note 7
Project Scheduling
3. Schedule Presentation
• Gantt Chart
• CPM
• PERT
Learning Objectives
systems
3
Overview
• Progress control.
• Estimated completion time (and sometime costs are associated with each
activity).
• The degree of activity details depends on the application and the level of
specificity of data.
5
6
Basics of Project Scheduling
• Milestone chart is the skeleton for the project schedule which senior managers
should know.
9
3. SCHEDULE PRESENTATION
10
A. Gantt chart
The most widely used management tool for project scheduling and control
reflects the start date, duration and end date of the activity.
Activity 1 2 3 4 5 6 7 8 9
A A A
B B B B
C
D
E
F F F F
Each activity is delayed as much as possible as long as the finish time of the
Early start
16
1. Early start
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A A A A A A
B B B B
C
D
E E E E E E E E
F
g
17
2. Early start
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A A A A A A
B B B B
C C C C C C C C C
D D D D D D D D
E E E E E E E E
F
g
18
3. Early start
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A A A A A A
B B B B
C C C C C C C C C
D D D D D D D
E E E E E E E E
F F F F F
g G G G G G
19
Late start
20
1. Late start
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A
B
C
D
E
F
g G G G G G
21
2. Late start
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A
B
C
D
E
F F F F F
g G G G G G
22
3. Late start
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A
B
C C C C C C C C C
D D D D D D D D
E E E E E E E E
F F F F F
g G G G G G
23
4. Late start
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A
B B B B
C C C C C C C C C
D D D D D D D D
E E E E E E E E
F F F F F
G G G G G G
24
5. Late start
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A A A A A A
B B B B
C C C C C C C C C
D D D D D D D D
E E E E E E E E
F F F F F
G G G G G G
B B B B
C C C C C C C C C
D D D D D D D
E E E E E E E E
F F F F F
G G G G G G
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A A A A A A
B B B B
C C C C C C C C C
D D D D D D D D
E E E E E E E E
F F F F F
G G G G G G
Difference between the two Gantt charts 26
Total slack (float) of activity is the difference between the start (or the end
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A A A A A A
B B B B
C C C C C C C C C
D D D D D D D D
E E E E E E E E
F F F F F
g G G G G G
27
• Help you identify the activities that must be completed on time in order to
complete the whole project on time.
• Show you which tasks can be delayed and for how long without impacting the
overall project schedule.
• Calculate the minimum amount of time it will take to complete the project.
• Tell you the earliest and latest dates each activity can start on in order to
maintain the schedule.
Terminologies
30
1. Early start (ES) is the earliest date a task can start
3. Latest start (LS) is the latest date a task can start without delaying the
project end date
4. Latest finish (LF) is the latest date a task can finish within delaying the
project end date
Critical Path Method has four key elements:
31
1. Critical Path Analysis
2. Float Determination
Below are some critical path examples to help you understand the key
elements
The duration of each activity is listed above each node in the diagram.
34
For each path, add the duration of each node to determine it's total duration.
The critical path is the one with the longest duration.
Critical path
Start – Activity 2- Activity 3- Activity 4- Finish = 5+7+2 =14
43