07 Projectcostmanagement 101018055200 Phpapp02
07 Projectcostmanagement 101018055200 Phpapp02
07 Projectcostmanagement 101018055200 Phpapp02
7 - Project Cost
Management
Project Management Training
Project Cost Management
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Process
Knowledge
Area Initiating Planning Executing Monitoring & Closing
Control
Cost Estimating
Cost Cost Budgeting Cost Control
Project Cost Management
• The process involved in estimating, budgeting, and controlling cost
so that the project can be completed within approved budget
• Life cycle costing
– Looking at the cost of whole life of the product (include maintenance)
• Value analysis (value engineering)
– Looking at less costly way to do the same work within the same scope
• Law of Diminishing Returns
– E.g. adding twice resource to task may not get the task done in half cost/time
Tools &
Inputs Techniques Outputs
1. Scope baseline 1. Expert judgment 1. Activity cost estimates
2. Project schedule 2. Analogous estimating 2. Basis of estimates
3. Human resource plan 3. Parametric estimating 3. Project document
4. Risk register 4. Bottom-up estimating updates
5. Enterprise 5. Three-point estimates
environmental factors 6. Reserve analysis
6. Organizational process 7. Cost of quality
assets 8. Project management
estimating software
9. Vendor bid analysis
Types of Cost
• Variable Costs
– Change with the amount of production/work
– e.g. material, supplies, wages
• Fixed Costs
– Do not change as production change
– e.g. set-up, rental
• Direct Costs
– Directly attributable to the work of project
– e.g. team travel, recognition, team wages
• Indirect Costs
– overhead or cost incurred for benefit of more than one project
– e.g. taxes, fringe benefit, janitorial services
Quality/Accuracy of Cost Estimation
Estimate Accuracy
Rough Order
of Magnitude • Most difficult to estimate as very little project info
+/- 50%
(ROM) is available, made during initiating process
Definitive -5%
Estimate • During the project and refined
10%
7.2 Determine Budget
• Process of aggregating the estimated cost of individual activities or work
packages to establish an authorized cost baseline.
Tools &
Inputs Techniques Outputs
1. Activity cost estimates 1. Cost aggregation 1. Cost performance
2. Basis of estimates 2. Reserve analysis baseline
3. Scope baselines 3. Expert judgment 2. Project funding
4. Project schedule 4. Historical relationship requirements
5. Resource calendars 5. Funding limit 3. Project document
reconciliation updates
6. Contracts
7. Organizational process
assets
Cost Aggregation
• Reserves & risk management are important Cost Budget
while estimating!
Management reserves
– Contingency reserves: 🡪 Cost Baseline
the cost impacts of the remaining risk Cost baseline
Activity estimates
Determines Budget: Other considerations
• High level parametric estimate as a rule of thumb
– E.g. testing cost 50% of development cost
Tools &
Inputs Outputs
Techniques
1. Project management 1. Earned value 1. Work performance
plan management measurement
2. Project funding 2. Forecasting 2. Budget forecast
requirement 3. To-complete 3. Organizational process
3. Work performance performance index updates
information 4. Performance reviews 4. Change requests
4. Organizational process 5. Variance analysis 5. Project management
assets 6. Project management plan updates
software 6. Project document
updates
How to control cost?
• Follow the cost management plan
• Manage change
– Recording all appropriate change
– Preventing incorrect change
– Ensuring requested changes are agreed upon
– Managing the actual changes when and as they occur
• Percent complete:
– 50/50 Rule
– 20/80 Rule
– 0/100 Rule
Activity is considered X percent complete when it begins and get credit for
the last Y percent only when it is complete
Earned Value Management
• Method to measure project performance against scope, schedule
and cost baseline (performance measurement baseline)
Image captured from Practice Standard for Earned Value Management, PMI © 2005
Earned Value Technique Example:
Project Budget: $400K
Project Schedule: 4 months
Actual Cost (AC) As of today, what is the actual cost incurred for
the work accomplished? $200K
Cost Performance Index We are getting $__ worth of work out of every $100K/$200K
(CPI) = EV/AC $1 spent. Are funds being used efficiently? = 0.5 i.e. 50%
4/0.33
Revised Total Duration Baseline Duration/Schedule Performance Index
= 12 months
Slide adapted from the original which taken from www.alphaPM.com
Earned Value Technique
Terms and Formulas Definition
Budget at completion (BAC) How much did we BUDGET for the TOTAL project effort?
Estimate at Completion (EAC) What do we currently expect the TOTAL project cost (a
= BAC / CPI forecast)?
Estimate to Complete (ETC) From this point on, how much MORE do we expect it to cost to
= EAC - AC finish the project (a forecast)?
Variance at Completion (VAC) As of today, how much over or under budget do we expect to
= BAC – EAC be at the end of the project?
Cost
Variance
(CV)
PV
Schedul
e
Variance
ACTUA (SV)
EV L
PLAN
EARN
VALUE
TIME
Project is over budget & behind schedule
Earned Value Management
EV can be calculated by
(%progress) x (planned man-
days)
Image captured from Practice Standard for Earned Value Management, PMI © 2005
Exercise
• You have a project to build a box. The box is six sided. Each side is to take one
day to build and is budgeted for $1000 per side. The sides are planned to be
completed one after the other. Today is the end of day three.
• Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV,
SPI, EAC, ETC, VAC.
• Describe your interpretation based on the calculation!
Side 5 0% $0
Side 6 0% $0
Exercise Solution
Parameter Calculation Result
PV
EV
AC
BAC
CV
CPI
SV
SPI
EAC
ETC
VAC
• AC+(BAC-EV)
– Used when current variances are thought to be atypical of the future
• TCPI
BACKUP SLIDES
Forecasting EAC
• Common alternative way to calculate EAC
Table captured from Practice Standard for Earned Value Management, PMI © 2005
Earned Schedule - An emerging EVM practice
• SPI($)
– At project start SPI is reliable
– At some point SPI accuracy diminishes
– Toward the project end it is useless (SPI = 1 at project end)
– Doest not show weeks/months of schedule variance
• SPI(t)
– Time based schedule measures
– Create a SPI that is accurate to the of the project
SV(t) = ES – AT
SPI(t) = ES / AT
Thank You