Exhibitno Iso-6 Dmapresentation-Marketanalysis-Dayaheadcongestioncosts Curtailments Unsched Etctrans Capacity
Exhibitno Iso-6 Dmapresentation-Marketanalysis-Dayaheadcongestioncosts Curtailments Unsched Etctrans Capacity
Exhibitno Iso-6 Dmapresentation-Marketanalysis-Dayaheadcongestioncosts Curtailments Unsched Etctrans Capacity
System Operator
By
Keith Casey
ISO Department of Market Analysis
February 8, 2000
1. The difference between the constrained and unconstrained cost of energy for congestion zones “NP15” and “SP15” is calculated for each hour using the
following formula:
Congestion Costs = (PX Day-ahead Zonal (constrained) Price – PX Day-ahead Unconstrained)*PX DA scheduled zonal load
2. For each hour a Total Curtailment is calculated. This number is equal to the sum of the curtailments of each of the five paths listed in the above table. A
path is deemed curtailed if; 1) there is a positive congestion price and 2) its final NFU schedule is less than its initial NFU schedule. This is a subtle point
but there are cases where a path has a positive congestion price and the final NFU schedules are greater than the initial NFU schedules. This happens when
flows on a path are increased to relieve congestion on other paths in the system.
3. Using COI as an example, during hours when COI is congested, a Congestion Ratio is calculated where:
COI Curtailment
Congestion Ratio =
Total Curtailment
4. Continuing with the COI example, the portion of Congestion Costs for each zone (NP15, SP15) that is attributed to COI is calculated by multiplying the
Congestion Ratio by the Congestion Costs. If COI is the only path curtailed in a particular hour than 100% of the congestion costs are attributed to COI.
However, if several of the five paths were curtailed in a given hour and COI’s curtailment constituted only 20% of the total curtailments than only 20% of
the congestion costs would be attributed to COI.
Gen.
Export to
Gen. Cost Cost
NP15
QSP15 QNP15 QTOTAL
SP15 NP15
DemandSP15 SNP15
SSP15 DemandNP15 = Cost Savings to SP15 Load
PNP15
PU
PSP15
= Cost Increase to NP15 Load
Gen.
Gen. Cost Cost
QSP15 QNP15
80,000
60,000
40,000
20,000
0
300,000
200,000
100,000
4,500
4,000
Total actual day ahead curtailments
3,500
3,000
Total day ahead curtailments if
2,500
MWh
1,500
1,000
500
0
99
99
9
99
99
99
9
9
8
99
99
9
-9
-9
-9
-9
l- 9
v-
b-
r-
n-
p-
n-
g-
ay
ar
ct
c
Ju
No
Ap
Fe
Ja
De
Ju
Se
Au
O
M
25,000
20,000
15,000
10,000
5,000
0
20,000
15,000
10,000
5,000
0
40,000
MWh
30,000
20,000
10,000