Project Budget
Project Budget
Construction Project
Costs Management
What is Cost and Project Cost Management?
Cost Baseline
The cost baseline is a time-phased
budget that is used as a basis against
which to measure, monitor, and control
overall cost performance on the project.
Project Funding Requirements
Funding requirements, total and
periodic (e.g., annual or quarterly), are
derived from the cost baseline and can
be established to exceed, usually by a
margin, to allow for either early
progress or cost overruns.
Funding usually occurs in incremental
amounts that are not continuous, and,
therefore, appears as a step function.
Why Project Budgeting?
Why needs for preparing a project budget :
To identify the monetary requirement in time both in
the forms of how much and when so as to be able to
implement according to plans or contract
agreements constraints
To indicate organizations whether their projects are
in a position to look for diversified sources of
finances in order to carry them out successfully
To enable organization to rethink and overhaul their
operational systems so that they can meet their
contractual performance targets
Building the Planned Project
Budget the WBS is the first step in
Establishing
defining the project and in establishing the
baseline.
All of the efforts used in producing the
deliverable of each task can be defined in
terms of cost (Labor, materials, facilities,
services and overhead).
Building the Planned Project Budget
• The sum of all tasks within the WBS constitutes the
total budget of the project.
Developing a Baseline Budget
for a Project
• Once a detailed budget is developed and
approved, the project manager should publish
this baseline and set it as a point of
comparison for actual performance progress.
• The baseline budget is the tool for measuring
how project changes affect our schedule and
budget.
Cost Budget Baseline
This process aggregates the estimated costs of
individual activities or work packages to establish
and authorized cost baseline.
Establish the Schedule
Based Baseline
on the Project Scope and available resources, the work
activities in the WBS are scheduled to establish the Schedule
Baseline.
Schedule Baseline
Preliminary Design 1.1.1 Jan Feb Mar Apr May
•• Developing
Developingthe
theProject
ProjectBudget
Budget
1.1. Develop
DevelopCost
CostComponents
Components––Financial
FinancialVs
VsEngineering
Engineering
2.2. Use
UseProject
ProjectBudgeting
BudgetingFormats
FormatsCWP
CWPFormats.xls
Formats.xls
3.3. Assign
Assignand
andFill
Fillininthe
thedifferent
differentCosts
Costsinto
intothe
the project
projectbudgeting
budgeting
structure
structure
4.4. Prepare
Prepare the the Project
Project Budget
Budget against
against schedule
schedule
Project
ProjectBudgeting
Budgetingnew-12.xls
new-12.xls
10/19/24
•• Formats
Formats for
for Project
Project Budgeting
Budgeting
CWP
CWPFormats.xls
Formats.xls
––Master
MasterSchedule
ScheduleFormat
Format
––Resources
Resources (Material,
(Material, Labor,
Labor, Equipment)
Equipment)
Schedule
ScheduleFormats
Formats
––Cost
CostBreakdown
BreakdownFormat
Format
––Project
Project Budgeting
Budgeting (Construction)
(Construction) Format
Format
––Cash
CashFlow
FlowFormat
Format
––Project
ProjectBudgeting
Budgeting(Financial)
(Financial)Formats
Formats
Cash
Cash Flows
Flows Programming
Programming
Financial / Budgetary / Cost Breakdown Structure
• Use Cost Breakdown Structure (CWP Formats)
• Use Financial / Budgetary Breakdown Structure
(CWP Formats)
• Determine Corresponding monthly expenses from
Resources Programming
• Cash flow Programming includes Cash inflows, Cash
outflows and Cash flow balance (Liquidity)
Project Control Costs
It is the process of monitoring the status of the project to
update the project costs and managing changes to the cost
baseline.
The key benefit of cost control is to provides the means to
recognize variance from the plan in order to take corrective
action and minimize risk.
This method assumes what the project has experienced to date can be
expected to continue in the future. The ETC work is assumed to be
performed at the same cumulative cost performance index (CPI) as that
incurred by the project to date. Equation: EAC = BAC / CPI
B. Forecasting
Three of the more common methods to compute EACs are described
as follows:
EAC forecast for ETC work considering both SPI and CPI factors.
In this forecast, the ETC work will be performed at an efficiency
rate that considers both the cost and schedule performance indices.
This method is most useful when the project schedule is a factor
impacting the ETC effort.
Variations of this method weight the CPI and SPI at different values
(e.g., 80/20, 50/50, or some other ratio) according to the project
manager’s judgment.
Equation: EAC = AC + [(BAC–EV) / (CPI × SPI)]
Each of these approaches is applicable for any given project and
will provide the project management team with an “early warning”
signal if the EAC forecasts are not within acceptable tolerances.
Estimate At Completion EAC:
EAC = AC+ETC
Estimate to Complete ETC:
ETC equals the revised estimate for the work
remaining.
The earned value technique in its various forms is a commonly
used method of performance measurement. It integrates project
scope, cost (or resource) and schedule measures to help the
project management team assess project performance.
Cost and Schedule Forecasting
Exercises:
Exercise #1:Schedule Variance Example.
PV = $ 42000
EV = $ 38000
AC = $ 48000
Budget at Completion BAC = $80000
SV = EV – PV = $38000 – 42000 = - $4000
SV % = SV/PV = -4000/42000 = -9.5 % Hence there is schedule
overrun of 9.5%
Exercise #2: Cost Variance Example.
CV = EV- AC = 38000 – 48000 = - 10000
CV% = CV/EV = -10000/38000 = -26 % Schedule overrun by 26%
# 3 Cost Performance Index ( CPI)
CPI = EV/AC = 38000/48000 = 0.79
Hence $0.79 worth of work was done for every $ 1 spent.
#4 Schedule Performance Index: SPI
SPI = EV/PV = 38000/42000 = 0.90
$ 0.90 worth of work has been for each done for each $1.00
worth of work that was planned to be done.
#5. Estimate at Completion and Variance at
Completion
EAC = BAC/CPI = 80000/0.79 = $101265
VAC = BAC – EAC = 80000-101265 = - $ 21265. The
project will exceed the planned budget by $21265
Problems:
#1:
BAC = 40 K
EV = 20 K
PV = 28 K
AC = 26 K
Determine:
% of work scheduled
% of budget spent
Cost Variance CV
Scheduled Variance SV
Case 1:
PV = 1600
EV = 1600
AC = 1600
Ideal Case where every thing goes as per plan.
Case2:
PV= 1900
EV= 1500
ACP= 1700
400 worth of work is behind schedule
SV = EV- PV = 1500-1900= -400
SV%= ( SV/PV)x100 = -21%
CV = EV – AC = 1500 – 1700= -200 Cost overrun by 200
CV% = (CV/EV)x100 = -13%
SPI = EV/PV = $0.79
CPI= EV/AC = $0.88
C. To-Complete Performance Index (TCPI)
It is a measure of the cost performance that is required to be
achieved with the remaining resources in order to meet a
specified management goal, expressed as the ratio of the cost
to finish the outstanding work to the remaining budget.
TCPI is the calculated cost performance index that is achieved
on the remaining work to meet a specified management goal,
such as the BAC or the EAC. The equation for the TCPI
based on the BAC: (BAC–EV)/(BAC–AC).
The efficiency that must be maintained in order to
complete on plan. TCPI = (BAC– EV)/(BAC– AC)
Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete
The efficiency that must be maintained in order to
complete the current EAC. TCPI = (BAC – EV)/(EAC – AC)
Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete
Exercise 1
You are managing a highway construction project. Your
total budget is $650,000 and there are a total of 7,500
hours of work scheduled on the project. You check with
your accounting department, and they tell you that you’ve
spent a total of $400,000. According to the schedule, your
crew should have worked 4,500 hours, but your foremen
says that the crew was allowed to work some overtime,
and they’ve actually put in 5,100 hours of work. Based on
this calculate the following earned value numbers:
PV, EV = ?
CV, SV = ?
BAC = ?
AC = ?
SPI, CPI = ?
BAC = $650,000
AC = $400,000
It’s nine months into your project. The total budget for your
project is $4,200,000. You have spent $1,650,000 so far
and you’ve got a CPI of 0.85. Use EVM from forecasting to
figure out where things stand. Find the following:
EAC = ?
ETC = ?
VAC = ?