0% found this document useful (0 votes)
46 views

Section 1c - Pipeline Installation Methods

Offshore installation methods for hydrocarbon pipelines.

Uploaded by

Luis M. Luis
Copyright
© © All Rights Reserved
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views

Section 1c - Pipeline Installation Methods

Offshore installation methods for hydrocarbon pipelines.

Uploaded by

Luis M. Luis
Copyright
© © All Rights Reserved
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 65

Subsea Pipeline

Engineering

Section 1c

Marine Pipeline Construction

Section 1c Haward Technology Middle East 1


Subsea Pipeline
Engineering

Pipeline Construction

 Laybarge methods construct the pipeline at sea,


from short lengths welded together, and lowered
into place.
 Tow and reel methods construct the pipeline on
shore, and then move the whole pipeline to its
final position.

Section 1c Haward Technology Middle East 2


Subsea Pipeline
Engineering
Pipeline Construction (cont’d.)

Section 1c Haward Technology Middle East 3


Subsea Pipeline
Engineering
Pipeline Construction – S-Lay Installation
 When using the S-lay installation method, onboard welded pipe
joints leave the vessel horizontally and are guided off a "stinger" - a
structure on the back of the ship that supports the seagoing pipe
string to control its bend radius.
 Due to its high production rate
and the possibility to install
concrete coated pipe, S-lay is
extremely suitable for pipe
installation in shallow and
intermediate waters. Larger
water depths are equally possible
but require a very long stinger,
turning S-lay into a less practical
and efficient solution.

Section 1c Haward Technology Middle East 4


Subsea Pipeline
Engineering
Pipeline Construction – J-Lay Installation
J-lay
Pipe stalks with a
length up to 6 joints
are upended and
welded to the
seagoing pipe in a
The ramp angle is chosen near vertical
in such a way ramp.
that it
is in line with the pipe catenary to the seabed.
The J-lay method is very suitable for deepwater
as the pipe leaves the lay system in an almost
vertical position. The pipeline is only bent once
during installation (at the seabed) which is
advantageous for installing pipelines that are
sensitive to fatigue.
Compared to other lay methods, J-lay has a relatively low
production rate due to the limited number of work stations.
The J-lay method is less suitable for shallow waters as this
requires a steep departure angle.
Section 1c Haward Technology Middle East 5
Subsea Pipeline
Engineering
Pipeline
Construction
(cont’d.)
S- Lay

Section 1c Haward Technology Middle East 6


Subsea Pipeline
Engineering

Pipeline Construction - S-Lay (cont’d.)

Section 1c Haward Technology Middle East 7


Subsea Pipeline
Engineering

Pipeline Construction - S-Lay (cont’d.)

Section 1c Haward Technology Middle East 8


Subsea Pipeline
Engineering

Pipeline Construction - S-Lay (cont’d.)

Section 1c Haward Technology Middle East 9


Subsea Pipeline
Engineering
Pipeline Construction - S-Lay (cont’d.)

Section 1c Haward Technology Middle East 10


Subsea Pipeline
Engineering
Pipeline Construction - S-Lay (cont’d.)

Section 1c Haward Technology Middle East 11


Subsea Pipeline
Engineering
Pipeline Construction - S-Lay (cont’d.)
Example 1:
Calculate the Lay Rate based on the design considerations
for installing a pipeline using the S-lay method.
The main characteristics of the pipeline are given below:
Water depth: 1500 m
Length : 100 km
Pipe outer diameter (OD): 14 inch (365 mm)
Wall thickness (WT): 25 mm
Design pressure : 400*105 Pa
Specified Minimum Yield Stress : 482 N/mm2
Expected undisturbed production rate : 3.6 km / day using
single joint welding
Expected repair rate : 5 % of all welds
Average repair time : 20 minutes
Pipe joint length : 12 m
Coating : Corrosion protection
Section 1c Haward Technology Middle East 12
Subsea Pipeline
Engineering

Pipeline Construction - S-Lay (cont’d.)

Answer:

Calculate the lay rate.

The number of welds in one day is: 3600/12 =


300
The number of repairs in one day is:
0.05*300=15
The total time spent for repairs in one day is:
20 min x 15 = 300 min = 5 hours
Total: 3600/(24+5)= 124 m/h = 2980 m/day

Section 1c Haward Technology Middle East 13


Subsea Pipeline
Engineering

Pipeline Construction - S-Lay (cont’d.)

Section 1c Haward Technology Middle East 14


Subsea Pipeline
Engineering
Pipeline Construction - S-Lay (cont’d.)

Section 1c Haward Technology Middle East 15


Subsea Pipeline
Engineering
Pipeline Construction - S-Lay (cont’d.)
 Overall safety record was very good for the activity set
involved (one high potential lifting incident during Solitaire
mobilisation, one medical treatment case on the survey
vessel)
 105 km of 22" concrete coated pipe laid in under 18 days
including pull-in and lay down.
 Average lay rate of ~6.9 km/day (or over 4 meters/minute)
 Peak lay rate ~7.8 km over a 24 hour period
 No weather downtime & very minimal mechanical
downtime
 Program completed 11 days ahead of the 30 day plan
(lump sum contract)
 28 kilometres were laid between the live Magnus gas lines
(100 meters apart)
Section 1c Haward Technology Middle East 16
Subsea Pipeline
Engineering
Pipeline
Construction -
S-Lay (cont’d.)

Pipe Tensioner

Section 1c Haward Technology Middle East 17


Subsea Pipeline
Engineering
Pipeline
Construction
- S-Lay
(cont’d.)

Section 1c Haward Technology Middle East 18


Subsea Pipeline
Engineering

S-Lay

Advantages of S-lay
 Whole length of barge can be used for operations
at multiple stations (line-up, welding,
radiography, field joint infill, tension)

Disadvantages of S-lay
 In deep water, tension has to be high in deep
water, stinger has to be long

Section 1c Haward Technology Middle East 19


Subsea Pipeline
Engineering

Lay Barge, S-Lay Method

Section 1c Haward Technology Middle East 20


Subsea Pipeline
Engineering

Lay Barge J-Lay


Method

Section 1c Haward Technology Middle East 21


Subsea Pipeline
Engineering

J-Lay Method

 To date, the deepest operating pipelines have


been laid using the J-lay method, where the
pipeline departs the lay vessel in a near-vertical
orientation, and the only bending condition
resulting from installation is near the touchdown
point in the sagbend.

Section 1c Haward Technology Middle East 22


Subsea Pipeline
J-Lay Engineering

Advantages of J-lay
 Tension can be much lower, particularly in deep
water.
 Touchdown point is closer to barge, and spans are
shorter.
 No stinger pipe.
 Less exposed to wave action - barge can lower pipe
and then weather-vane around.

Disadvantages of J-lay
 Welding all carried out at one or two stations.
 inflexible if breakdown occurs.
 not suitable for very shallow water unless ramp can
be rotated into horizontal position.
Section 1c Haward Technology Middle East 23
Subsea Pipeline
Engineering
J-Lay
Method

Section 1c Haward Technology Middle East 24


Subsea Pipeline
Engineering

J-Lay Method (cont’d.)

Section 1c Haward Technology Middle East 25


Subsea Pipeline
Engineering
Reel - Lay

Section 1c Haward Technology Middle East 26


Subsea Pipeline
Engineering
Reel - Lay
 Long pipe segments are welded, tested and
coated onshore and then spooled onto a large
vertical pipe reel in one continuous length.
 Once the Reel-lay vessel is in position, the pipe is
unspooled, straightened and overboarded as the
vessel moves forward.
 The advantages gained by the high production
rate as well as the controlled welding and
inspection conditions onshore, make Reel-lay an
extremely efficient method for the installation of
pipelines up to 20 inch in all waters. A Reel-lay
vessel requires a spoolbase nearby to reduce
transit time to and from the installation site.
Reel-lay is therefore often combined with other
Section 1c pipelay methods onboard. Haward Technology Middle East 27
Subsea Pipeline
Engineering

Reeling (cont’d.)

 PLUTO (Pipe Line Under The Ocean) England to


France, 1944
 100 km+, two kinds of 3-inch pipe, one steel ERW,
no coating, the other a hollow submarine cable

Section 1c Haward Technology Middle East 28


Subsea Pipeline
Engineering
Reeling (cont’d.)
 Historically, the technique of laying undersea fluid-carrying
pipelines had its rudimentary beginnings in England in the
1940's in a War-time project known as "Operation Pluto".
 In the summer of 1944, 3-inch nominal bore steel tubes,
electrically flash-welded together, were coiled around
floating drums. One end of the pipe was fixed to a terminal
point; as the floating drums were towed across the English
Channel, the pipe was pulled off the drum. In this manner,
pipeline connections were made between the fuel supply
depots in England and distribution points on the European
continent to support the Allied invasion of Europe.
 PLUTO (Pipe Line Under The Ocean) England to France,
1944
 100 km+, two kinds of 3-inch pipe, one steel ERW, no
coating, the other a hollow submarine cable

Section 1c Haward Technology Middle East 29


Subsea Pipeline
Engineering
Two Types of Reelships
 Horizontal axis (e.g. Technip Apache, Deep
Blue, DSND Fennica)

 Vertical Axis Reel (e.g. Global Chickasaw,


Hercules)

Section 1c Haward Technology Middle East 30


Subsea Pipeline
Engineering

Reeling (cont’d.)

Section 1c Haward Technology Middle East 31


Subsea Pipeline
Engineering

Reeling (cont’d.)

Section 1c Haward Technology Middle East 32


Subsea Pipeline
Engineering

Pull and Tow Methods


 Pull is from a fixed point, on an opposite shore or
an anchored barge.
 Tow is from a free-floating tug.

Section 1c Haward Technology Middle East 33


Subsea Pipeline
Engineering

Pull

Section 1c Haward Technology Middle East 34


Subsea Pipeline
Engineering

Pull

Section 1c Haward Technology Middle East 35


Subsea Pipeline
Engineering

Pull (cont’d.)

Section 1c Haward Technology Middle East 36


Subsea Pipeline
Engineering

Tow

Section 1c Haward Technology Middle East 37


Subsea Pipeline
Engineering

Tow (cont’d.)

Section 1c Haward Technology Middle East 38


Subsea Pipeline
Engineering

Surface Tow

Section 1c Haward Technology Middle East 39


Subsea Pipeline
Engineering

Bottom Tow

Section 1c Haward Technology Middle East 40


Subsea Pipeline
Engineering

Mid-depth Tow

Section 1c Haward Technology Middle East 41


Subsea Pipeline
Engineering

Mechanics of Suspended Pipeline

Section 1c Haward Technology Middle East 42


Subsea Pipeline
Engineering

Element of Suspended Pipeline


 Geometry described by relationship between
distance along pipe S and inclination y

Section 1c Haward Technology Middle East 43


Subsea Pipeline
Engineering

Element of Suspended Pipeline


 Mechanics described by end forces and moments
on the element, the weight of the element, and
the resultant hydrostatic force on the element

Section 1c Haward Technology Middle East 44


Subsea Pipeline
Engineering
Element of Suspended Pipeline
 Element has three
components:
 One component is a force that
acts along the local axis, and is
equal to the local hydrostatic
pressure multiplied by the
cross-section.
 The other component is
horizontal U and
 The third component is vertical
V.
 These forces and moments -
system I, are in equilibrium.

Section 1c Haward Technology Middle East 45


Subsea Pipeline
Engineering

Element of Water Filling Same Space as


the Pipe Element
These forces and moments - system II, are in
equilibrium

Section 1c Haward Technology Middle East 46


Subsea Pipeline
Engineering
Element of Suspended Pipe – Force
Equilibrium

 System I is in
equilibrium system II is
in equilibrium
 Therefore the
difference between I
and II must also be in
equilibrium
 Now write down the
equilibrium equations

Section 1c Haward Technology Middle East 47


Subsea Pipeline
Element of Suspended Pipe – Force
Engineering

Equilibrium

Section 1c Haward Technology Middle East 48


Subsea Pipeline
Engineering
Element of Suspended Pipe – Force
Equilibrium (cont’d.)

 The F term is only significant close to the lift-off


point and close to the touchdown point.
 Over almost all the suspended span the pipe
behaves as a catenary.
 The horizontal component U of the tension
controls the curvature, which is w/U.
 The vertical component V supports the weight.

Section 1c Haward Technology Middle East 49


Subsea Pipeline
Engineering

Tow Method
 For all pull and tow methods, the pipe has to
have a uniform low weight during the pull.
 For bottom pull and bottom tow, the route has to
be surveyed carefully, and the pipe must have an
abrasion-resistant coating that can stand up to
being dragged across the seabed

Section 1c Haward Technology Middle East 50


Subsea Pipeline
Engineering

Pipe Installation Stress-Strain Relationship

Section 1c Haward Technology Middle East 51


Subsea Pipeline
Engineering
Pipe Installation Stress-Strain Relationship
(cont’d.)

Section 1c Haward Technology Middle East 52


Subsea Pipeline
Engineering
Pipe Installation Stress-Strain Relationship
(cont’d.)

Section 1c Haward Technology Middle East 53


Subsea Pipeline
Engineering
Pipe Installation Stress-Strain Relationship
(cont’d.)

Section 1c Haward Technology Middle East 54


Subsea Pipeline
Engineering
Pipe Installation Stress-Strain Relationship
(cont’d.)

Section 1c Haward Technology Middle East 55


Subsea Pipeline
Engineering
Pipe Installation Stress-Strain Relationship
(cont’d.)

Section 1c Haward Technology Middle East 56


Subsea Pipeline
Engineering

Quantify Buckle Prevention

 How much wall thickness is needed to prevent


buckling during reeling ?
 Sometimes said: D/t < 20 or 22 not so!
 Larger diameters require a smaller D/t

Section 1c Haward Technology Middle East 57


Subsea Pipeline
Engineering

Quantify (cont’d.)
 Pipe diameter D, wall thickness t
 Reel diameter b
 Maximum bending strain = D/b
 DnV buckling strain = (t/D) – 0.01
 (taking girth weld factor as 1, and yield/tensile<0.85);
so if geometric factor of safety = f

Section 1c Haward Technology Middle East 58


Subsea Pipeline
Engineering

Quantify Buckle Prevention (cont’d.)

Section 1c Haward Technology Middle East 59


Subsea Pipeline
Engineering
Quantify Buckle Prevention (cont’d.)

Section 1c Haward Technology Middle East 60


Subsea Pipeline
Engineering

Reeling Method (cont’d.)

 Pipe with concrete weight coating cannot be reeled.


 Links choice of construction method to design of
pipeline.
 If stability is a governing factor, requires the steel
thickness to be increased to give the pipeline enough
weight.
 Expensive (particularly for CRA pipe).
 Leads to other difficulties (such as upheaval
buckling).
 Means that anti-corrosion coating has to resist
potential mechanical damage.

Section 1c Haward Technology Middle East 61


Subsea Pipeline
Engineering

Alternative Flexible Concrete Weight


Coating
 Polymer-modified rubber-like concrete
 More expensive than conventional concrete, but
much cheaper than steel (per kg of submerged
weight)
 Can be applied
 Gives mechanical protection to anti-corrosion
coating

Section 1c Haward Technology Middle East 62


Subsea Pipeline
Engineering

Reeled Bundles
 Simple pipe-in-pipe systems can be reeled (e.g.
Seahorse and Tarwhine projects).
 Studies have shown that more complex bundles
can also be reeled.
 Possibility of helical bundles (Husham patent
1895).
 Carrier diameter and wall thickness limited by
reeling capacity.

Section 1c Haward Technology Middle East 63


Subsea Pipeline
Engineering
Reeled Bundles Compared With Towed
Bundles
Reeled
 carrier diameter limited
 submerged weight can be large
 route can be curved.

Towed
 carrier diameter not limited
 submerged weight during tow needs to be small
 final route must be straight.

Section 1c Haward Technology Middle East 64


Subsea Pipeline
Engineering

End of this
Section

Section 1c Haward Technology Middle East 65

You might also like