Transformer Presentation
Transformer Presentation
Transformer Presentation
Introduction
Our objective is to provide training on the Power transformer and Earthing Transformer
operation &
maintenance. Power transformer rating is of 132kV, 35/50 MVA, manufactured as per the IEC
standard
60076.Make Japan AE power System Corporation, Japan and 500 kVA Earthing Transformers
are from
AREVA Turkey.
A 66/11 kV, 31.5 MVA Star-Delta (Vector Group of Dyn11) Transformer with On Load
tap changer 17 Tap positions. Highest voltage at maximum tap position is 72.6 kV and
Low Voltage at minimum Tap is 59.4 kV. (Please refer to name plate).
Rated Primary current at 275A ,31.5 MVA LV Amps is 1581 with impedance Voltage HV/LV at
75 °C (at ONAF) >
11.56 %. Short Circuit rating of HV side is 40 kA for 1 Sec and LV side 25kA for 3 Sec.
12 Nos radiators are provided on each Transformer and 08 cooling Fans in two Groups (04
Fans in one
Group) fully automatic control through Oil Temperature Indicators and Winding Temperature
Indicators.
Each radiator is fixed with Tank through Butterfly Valve and individual radiator can be
replaced in case of
any rectification during maintenance.
01 Conservator Tank is fixed on IDT having enough capacity to accommodate the expansion
PRESENTATION TO ADANI - MUNDRA Slide - 2
and
TRAINING MANUAL–TRANSFORMER
MV Cable Boxes are designed such free standing and self supported that incase of any
problem Transformer can be removed without disturbing cables.
Transformer Tap change control is also affected from the substation control room with
facilities for remote
control from supervisory control center.
Mechanical Protection:
A.1 Buchholz Relay
A.2 Oil Temperature Trip
A.3 Winding Temperature Trip
Electrical Protection:
B.1 Differential Protection
B.2 REF Protection
B.3 O/C and E/F Protection
Earthing Transformer:
500 kVA (11/0.4kV) earthing Transformer with ONAN cooling system is installed to provide
the earthing
of Power transformer (11kV winding is delta connected).
Layer type windings and Primary is in Zigzag and LV side is Star connected and having
ZNyn11 vector
Group. Short circuit rating on 11kV is 12.7 MVA for 30 Sec.
Voltages are regulated through Off Load tap changer and LV winding is used for substation
load. All
utility of the substation is fed by ETs through LVAC switchgear.
1. Buchholz relay
2. OIL and Winding Temperature Trip
3. LV REF and LVAC REF
4. O/C & E/F Protection for both MV and LV windings
Buchholz Relay
Most of the faults in the transformer are accompanied by the generation of gases due to
decomposition of oil and insulating material. However if such a fault is limited within a small
scale, gases are generated slowly and collected at the ceiling of the tank cover while rising
in the oil in the form of bubbles. If a serious faults happens gases are generated abruptly to
PRESENTATION TO ADANI - MUNDRA Slide - 6
TRAINING MANUAL–TRANSFORMER
It operates the alarm contact against slowly generating gas or the trip contact against
abruptly generating gas.
Dehydrating Breather
The breather is installed on the ventilating pipe on the upper part of such units as
transformer, oil filled equipment and insulation oil storage tanks.
The breather completely removes parts of moisture and fine floating substances out of the
flowing air by means of the absorbent and filter. Humidity is almost completely removed by
silica gel, a desiccating agent.
Noise
In order to find out faults at their early stage pay attention to any abnormal noises having
generally high frequency during the daily inspection. These noises are likely to be produced
as a result of faults in the transformer.
Oil Leakage
Any oil leakage may lead to the deterioration of oil and will spoil the outside appearance of
transformer very much. Check carefully the parts where gaskets are applied.
PRESENTATION TO ADANI - MUNDRA Slide - 9
TRAINING MANUAL–TRANSFORMER
Dehumidifying Breather
The breathing action of the breather can be observed exactly at its oil cup, even while running
whether
either the ambient temperature or oil temperature changes. Check whether the breathing
action is going on
normally or not.
Silica gel is adopted as the standard dehumidifying agent, that looks blue in dry condition by
mixing cobalt
chloride and it will become light pink when it has absorbed moisture. Special attention should
be paid to the
changes of color. It is desirable to replace it with new one at suitable opportunity.
Dial Thermometer
Check whether the alarm contact is good.
Buchholz Relay
Check whether its float moves smoothly or not using of float checking device and further
whether its contact
function is good or bad.
Bushings
Check whether the following damages or trouble is observed on the bushing:
Dirty spot, crack and trace of discharge on porcelain insulator.
Loosened bolt, nut and irregular tightness on fixing terminals or studs.
Earthing Transformer
General Data
- Make : Areva
- Rating : 0.5 MVA
- Insulation Level : L11 75AC 281L1 –AC3
- Rated Voltage : 11000/400 V
- Cooling Method : ONAN
- Impedance Voltage at Tap 3 : 3.87%
- No of Radiators :2
- Total Weight : 5700 KG
- Oil Weight : 1770 KG
- Type of Oil : Nynas nytro 10 XN
- Vector Group : ZNyn11
- Designed Ambient Temperature : 55 deg °C
If the test preparations are found satisfactory, the separately processed oil with good test
values shall be
filled in the cable box. Following are the required specification of oil.
Ensure the insulation resistance of the supporting insulators provided on the bus bar at the LV
side. Ensure
the tightness of LV cable and connection at bus bar. Ensure the tightness of LV bushing
terminal end.
Ensure that the connections are per the drawing/documents and all are connection are locked
with the
torque tightening.
To check and ensure the operation and performance of AVR as per the specification and
documents
/ requirements.
Automatic voltage control shall be initiated by voltage regulating relay. The relay shall be
operated from the
normal reference voltage stated in the requirements from the circuit mounted on the LV
voltage transformer.
The relay shall be insensitive to the frequency variation from 47 to 51 Hz the relay shall also
be incorporate
the under voltage blocking facility if reference voltage falls below the 80% of the nominal
value and
automatic restoration of control when the reference value varies 85% of the nominal value.
The relay
bandwidth shall be adjustable of to any value between 1.5 and 2.5 times transformer tap step
% the
nominal setting being twice the transformer tap step %.
▪ Operation
PRESENTATION TO ADANI - MUNDRA Slide - 17
a. Put AVR in auto mode and MDU in remote and check the following:
TRAINING MANUAL–TRANSFORMER
f. Put AVR in supervisory and MDU in remote and check the following:
1. Operation possible from MDU and AVR.
2. Operation not possible from DCS and SCADA.
AVR Display
1. Ensure that AVR display has parameters like Voltage, Current, Frequency, Tap no.,
Master/Follower/Independent mode, Paragramer functions (Breaker status).
- Switch on AVR & MDU control supply, DC supply and MDU motor supply. Identify and
verify the
terminal where CB status inputs are connected.
- All the CB status inputs be temporarily short circuited.
- Select paragrammer screen of all AVRs and ensure that all CB status are closed in all
AVRs.
- Switch of control supply of AVR 1 and observe whether there is any status disturbance in
the
paragrammer of other AVRs.
- Keep MDU in Local and ensure that the tap positions are same in MDU, OLTC, AVR
Display and Bus
Bar diagram.
- Keep AVR in “Hand” (manual) and Independent mode and ensure the following
Indications/operations
- Check that Tap Changer in Local indication lamp glows.
- REMOTE / SUPRY try color LED off and MDU local LED glows.
- LED in the Hand push button glows and Raise/Lower operation not possible. Also
Independent LED
glows.
- AVR VT supply absent message in the status line.
- Keeping MDU in remote ensure that tap operation is not possible from MDU.
- Keeping AVR in “REMOTE” ensure that “REMOTE / SUPRY” tri-color LED glows in green
and MDU
local LED off. Also LED in the “Hand” push button glows.
- Raise/Lower operation possible from AVR and Independent LED glows.
- AVR VT supply absent message in the status line.
- Give Raise/Lower commands from AVR and ensure simultaneous tap raising/lowering of
the tap
positions at MDU, OLTC, AVR display & Paragrammer.
PRESENTATION TO ADANI - MUNDRA Slide - 19
TRAINING MANUAL–TRANSFORMER
▪ During tap operation ensure that “Tap 0” display is not coming at any point.
▪ Bring the OLTC in extreme tap positions and observe the message “Tap changer in extreme
position”
in the status line is displayed and tap operations are blocked at extreme positions.
▪ Check “T.C. Incomplete” alarm in the status line when tap operation is stopped midway.
This can be
simulated by switching off the MDU control supply during tap operation In- progress. Reset
TC
Incomplete alarm by doing further tap operations after switching on the MDU control supply.
▪ Ensure “T.C. Motor Supply Faulty” alarm in the status line by switching off the MCB of TC
motor
supply at LVAC panel. Ensure T.C. Control Supply Faulty alarm in the status line by switching
off the
MCB of TC control supply at AVR panel.
▪ Put the AVR in “SUPRY’ and ensure the following:
- Put the AVR in SUPRY and ensure that Red color LED of REMOTE /SUPRY push button
glows.
- Raise/Lower operation not possible from AVR panel.
- Tap changer in “LOCAL’ indication lamp off.
- MDU Local LED off.
- Independent LED glows.
- AVR VT supply absent message in the status line.
▪ Gradually raise the voltage output of the variac and observe the voltage deviation in the
home screen
display. Also observe the deviation pointer moves upwards.
▪ Increase the voltage by 4% of the (band width) the reference level (110V) and ensure the
following:
- Time bar in the home screen display starts filling and at the end of the filling, LED in the
“Lower”
command push button starts glowing.
- Tap change in progress message in the status line as long as the operation is in
progress.
- After green LED of lower Command goes off, tap position is seen reduced by one tap.
- Tap position in MDU, OLTC, AVR display and programmer are same.
- As soon as the lower tap operation starts, bring the variac output back to 110 V.
- Repeat the above automatic tap lowering for two or three tap operations.
▪ Decrease the voltage by 4% of the (band width) reference level (110V) and ensure the
following:
- Time bar in the home screen display starts filling and at the PRESENTATION
end of the filling,
TO ADANI LED in
- MUNDRA the
Slide - 21
TRAINING MANUAL–TRANSFORMER
▪ As soon as the Raise tap operation starts, bring the variac output back to 110 V.
▪ Repeat the above automatic tap raising for two or three tap operations.
▪ Keep the variac output at 110V and ensure the alarms.
▪ Reduce the voltage by 20% of the reference value and ensure the following:
- Red LED glows against “< U”.
- Under Voltage message in the status line.
- Automatic tap raising operation is seen blocked from AVR.
- Ensure that in Manual mode both Raise and Lower operations are blocked when AVR is in
Under
Voltage condition.
- Put AVR in AUTO mode.
▪ Bring back the variac to 110V and increase the output by 20% of the reference value and
observe the
following:
- Red LED glows against “> U”.
- Over Voltage message in the status line.
- High speed automatic tap lowering command issued by the relay.
- Bring the variac output less than 30% of the reference value and observe that all alarm
indication
vanished except “AVR VT Supply absent” message in the status line.
- Put AVR in SUPRY mode and in AUTO.
- Ensure that automatic tap operation and signaling take place in SUPRY mode also as
described
above.
▪ Identify and verify the Terminals where CB status inputs are connected.
▪ All the inputs to be temporarily short circuited. PRESENTATION TO ADANI - MUNDRA Slide - 22
▪ Select all AVRs in HAND mode.
TRAINING MANUAL–TRANSFORMER
▪ Ensure the tap position at MDU, OLTC, AVR display and Programmer is same.
▪ Select parallel control of all AVRs in Manual.
▪ Select AVRs in REMOTE.
▪ Select AVR 1 in Master and others in Followers (i.e. M F F)
▪ Ensure the following:
- Master LED of AVR 1 glows.
- Follower LED of AVR 2 & 3 glows.
- LED against “Parallel” symbol glows in all AVRs.
- Master message in the status line display of AVR 1.
- Follower message in the status line display of AVR 2 & 3.
- No alarm display and alarm indications in any AVRs.
- All circuit breaker are in closed status in programmers of all AVRs.
- Programmer shows the correct indication of the parallel selection.
- Raise/Lower the tap from the master AVR and ensure proper parallel tap operation in all
IDTs.
Check tap positions at MDU, OLTC, AVR display and Programmer of all IDTs.
- Ensure that tap operations are not possible from the AVRs selected as Followers.
- Select AVR2 as Master and Others as Followers and do the tap operations as done in
AVR1 and
ensure satisfactory operations and indications (F M F).
- Then select AVR3 as Master and others as Followers and repeat the procedure as
mentioned
above (F F M).
- Do tap operations and indication checks on all possible combinations as suggested in
the test
format for OLTC Operation Checks – Parallel Manual mode.
- Ensure that operation shall not be possible from Follower AVRs.
- Parallel operation shall not be possible from any of the AVRs if more than one master is
selected.
- Parallel operation shall not be possible from any of the AVRs if Followers are selected
without
any Master. PRESENTATION TO ADANI - MUNDRA Slide - 23
- Switch off AVRs one by one and observe “Failure Par. Control” message in the status
TRAINING MANUAL–TRANSFORMER
- Again operate the same AVR in Independent mode and create one step tap difference
and switch
off the MDU control supply.
- Then put this AVR again in parallel mode and then observe that Raise/Lower command
initiated
from the AVR but tap operation is not taking place at MDU and OLTC.
- Meantime ensure an “Out of step” alarm message an the status line of each AVR after
time delay.
- Repeat this check in other AVRs also
- Create two-step tap difference and put the AVR in parallel mode and observe an “out of
step”
alarm message immediately.
- Select AVR in SUPRY mode and ensure that operations are not possible from AVR panel.
- AVR faulty.
- AVR faulty alarm can be checked by switching off the AVRs one by one.
- Then ensure proper resetting of alarms.
- Now select AVRs in AUTO mode from DCS and ensure correct indications.
- Check Raise/Lower operation by varying the variac output by ± 4% of the reference
voltage.
- Ensure correct feedback in DCS for satisfactory tap operation and indication.
- Select AVR 1 in Master and others in Followers (M F F).
- Select AVRs in MANUAL mode.
▪ Ensure the following in the event list, SLD and TC control box of DCS:
- Tap changer IDT1, 2 & 3 parallel.
- Tap changer IDT1 - Master.
- Tap changer IDT2 & 3 - Followers.
- Tap position indication.
- Give a Raise command from DCS to the IDT selected as master and ensure that
satisfactory parallel
tap operation takes place in other IDTs.
- Ensure correctness of feedback and indication in DCS of all IDTs
- Give a lower command and check the operations and feedback as before.
- Then ensure that Raise/Lower tap operation is not possible from the IDTs selected as
Followers in
DCS.
- Select other AVRs one by one as Master and repeat the tap operations as described
earlier. (i.e. F M F,
F F M).
- Then create “out of step” alarm condition and ensure that parallel operations are blocked
from DCS.
- Parallel Auto selection is not possible from DCS.
PRESENTATION TO ADANI - MUNDRA Slide - 27
- Parallel Auto to Parallel Manual selection is not possible from DCS.
TRAINING MANUAL–TRANSFORMER
To ensure the operation of tap changer indication and alarms, at DCS/SCADA when initiated
at device.
Alarm
5. AVR Faulty:
AVR faulty means, the single-phase supply input of AVR is not available. This can be
simulated by
switching off the MCB of AVR input supply at AVR panel. AVR faulty alarm will appear in
DCS and
SCADA. The alarm can be accepted by switching on the same MCB.
6. VT Supply Faulty:
VT Supply Fail means, the reference voltage from the secondary side of the LV Voltage
transformer is
not available. This can be simulated by giving an AC 110V supply to the VT secondary
terminals after
disconnecting the wires actually coming from the VT secondary side to AVR and VT supply
fail will be
vanished. Bt switching off the above VT supply, VT supply fail alarm will appear at DCS and
SCADA.
To ensure the performance of OLTC parallel operation through AVR at parallel manual mode
with master,
follower, and Independent selection independently. Parallel auto mode with master, follower
and
independent selection automatically with breaker status and same operation with auto to the
reference
voltage of VT secondary voltage.
Procedure
- MFF: MFF means AVR1 is the master of IDT1, AVR2 and AVR3 are the followers of IDT2,
IDT3
for the master.
- MF1: MF1 means AVR1 is the master of IDT1, AVR2 is the follower of IDT2 for the
master and
AVR3 is the independent for IDT3.
- Master: (M) Master means the OLTC operation is possible from the master only.
- Follower: (F) Follower means the OLTC operation not possible from the follower but
operation
followed by the master.
- Independent: (I) Independent means the operation of OLTC can be done individually.
▪ If all the breakers are closed as shown in figure, the scheme will be configured in such a
way that the
IDT1 as master and IDT2 & IDT3 are followers.
Pressure gauges shall be connected at the bottom and top of the main tank to monitor the
pressure level
during testing
- Ensure the rubber bag and rubber bag rupture relay are normalized.
- Ensure the main tank and the OLTC tanks are normalized.
- All the nuts and bolts are fully tightened and torque checked.
- Ensure new gaskets are used during erection.
- Ensure no oil trace at anywhere the Transformer.
- Ensure proper cleaning of the Transformer and its surroundings.
- Ensure the availability of nitrogen cylinder with regulator and pressure gauge.
- Ensure all gauges have proper valid calibration status.
- Ensure the availability of thermometer for ambient temperature.
- Ensure valves between main Buchholz relay and conservator and between HV cable
box/boxes and
conservator are open.
- Ensure all radiator valves are open.
- Ensure the valves between OLTC and conservator is open.
- Ensure the PRD operating pressure.
- Note down the pressure due to normal oil head at bottom and top of the tank.
- Note down the ambient and oil temperature.
- Slightly open the N2 cylinder valve and regulated N2 shall be allowed to pass and
pressured the
normal oil head. When the pressure reaches at as stated above by simultaneously
monitoring the
pressure gauges P1, P2 and P3 and maintaining continuouslyPRESENTATION
for 48 hours.
TO ADANI - MUNDRA Slide - 36
- During the pressurizing, ensure the pressure at tank top (P2) is less than the operating
TRAINING MANUAL–TRANSFORMER
To ensure the properties and characteristics of oil processed oil filling into the transformer.
Is used to identify the presence and quantity of gasses dissolved in the transformer oil.
Chemical names and symbols of gases
- Nitrogen : N2
- Oxygen : O2
- Hydrogen : H 2
- Carbon Monoxide : CO
- Carbon Dioxide : CO 2
- Methane : CH 4
- Ethane : C2 H6
- Ethylene : C2 H4
- Acetylene : C2 H2
To ensure the items provided are confirming to the specification and drawings:
Frequency Response Analysis (FRA) is a valuable tool to verify the geometric and mechanical
integrity of
electrical apparatus; especially transformers, providing accurate and repeatable
measurements. This is a
proven field diagnostic technique capable of detecting damage arising due to
dislocation/movement of core
and winding during transportation or after occurrence any fault.
FRA is based on the principle of measurement of steady electrical response against a steady
sinusoidal
input given to the test object.
The basis of the FRA technique is that the impedance of the transformer is a function of the
resistance,
inductance, capacitance and applied signal frequency. The resistance is related to the
physical construction
of the winding. Capacitance and inductance is related to the construction and geometry of the
windings.
Deformations and movements have an effect on both inductance and capacitance that may
be reflected in
the resulting frequency response.
There are two basic methods for conducting FRA test; Low Voltage Impulse method and
Sweep Frequency
Response Analysis (SFRA).
Low Voltage Impulse method relies on indirect measurement of the frequency response. An
PRESENTATION TO ADANI - MUNDRA Slide - 40
impulse or set
TRAINING MANUAL–TRANSFORMER
SFRA measurement is done with the frequencies being swept in a wide range; usually from 20
Hz to 2
MHz. this is the simple direct measurement in frequency domain. Also a direct relationship
exists between
geometric configurations and RLC network constituted by winding and core assembly
identified by its
frequency dependent transfer function. Measuring the frequency response may be performed
by applying a
simple varying frequency signal to the transformer that covers the frequency range of
interest. Sweep
frequency method has far higher repeatability and consistency over impulse methods which
are prone to
variation due to lead arrangement and impulse shape.
Normally a factory FRA measurement is taken as reference (signature) and later on site
measurement
(after erection or any failure) is compared with the reference measurement. In practice
measurement after
erection at site is taken as reference for the future measurements done at site during the
operational period
of the transformer.
Possible damages in the winding are indicated in a relevant range of frequencies by shifting of
reference
points or by the introduction of new resonance, not being present in the reference
measurement.
The comparison of the traces belonging to different phases or different Transformer of same
PRESENTATION TO ADANI - MUNDRA Slide - 41
design (sister
TRAINING MANUAL–TRANSFORMER
Possible damages in the winding are indicated in a relevant range of frequencies by shifting of
resonance
points or by the introduction of new resonance, not being present in the reference
measurement.
The comparison of the traces belonging to different phases or different Transformer of same
design (sister
unit) may be useful, but with limitations.
A shifting of the resonant point (if any) of the open circuited admittance is noted. The
difference (i.e. the
shifts of resonant points or the introduction of new resonance not present in the reference
measurement) is
evaluated as an indication of normal vibration or faults in the winding.
The plots of the admittance (reverse of impedance) verses frequency indicate a series of
resonance with
small value and anti resonance with high value. The resonance with low admittance
represents a parallel
resonance circuit. The resonance with high admittance represents a series resonance circuit.
Test Preparation
Measuring the frequency response of a winding within a transformer transfer function from
winding to
winding, gives a fingerprint for that winding or transformer. The process requires
measurement of both input
and output signals, which are then ratioed to give the response. This reduces the effect of the
measurement
of a three lead system involving input, measured input and measured response.
PRESENTATION TO ADANI - MUNDRA Slide - 42
TRAINING MANUAL–TRANSFORMER
The test can also include voltage transfers between windings i.e. applying a signal to one
winding of a
transformer and measuring the response at another winding to determine the amplitude
change and phase
shift of the signal having been transferred along a winding, or from one winding to the other.
Transformer under test should be completely de-energized and isolated from the power
system. This shall
be solidly earthed which is common to FRA test equipment. FRA is performed as response to
electrical
measurement at the terminals connected to the starting and end of any winding. The test
leads must be first
connected to the FRA instrument and then to the Transformer Bushings.
The main cable clamps red and black are connected to bushing terminals accordingly. Also
connect the
ground clips for each cable, red and black to the corresponding Bushing flanges. The test set
up and actual
test shall be done as per the manufacturer’s manual.
PRESENTATION TO ADANI - MUNDRA Slide - 43
TRAINING MANUAL–TRANSFORMER
Precautions / Safety
FRA measurement is sensitive to DC magnetization of the core and hence it has to be carried
out before
application of any DC voltage. If any DC measurement was carried out before FRA
measurement, it should
be properly demagnetized.
The resultant plot may distort from the actual one in case of a loose connection.
Interpretation
The exact comparison of the FRA measurement plots at site with the factory measurement
can be made
only if measuring equipments, measuring connection, setup, measuring lead etc are the
same. However
identical test equipments with the same connection and setup may give almost the same
results.
Frequency response plot provides a fingerprint for a transformer. Fingerprints from similar
transformers
have common features.
The core condition, in principle, cannot be checked by the FRA method. However
magnetization of core,
affects low frequency results.
PRESENTATION TO ADANI - MUNDRA Slide - 44
TRAINING MANUAL–TRANSFORMER
Thank You