Week#6. Project Scheduling
Week#6. Project Scheduling
Project Scheduling
deals with
If a project takes approximately 1 year, For example, a critical design review that Schedules with too many activities
then each activity should be between a last for 2 days in a 3-year project should become difficult to monitor and control
day and a week be included in the activities list because of
its pivotal importance
Approach to Estimate the Project Duration
Project Duration Estimation Approach
CPM PERT
Precedence Relations Among Activities
Availability Technologi-
of cal Precedence Relations
resources constraints
Lead-lag Relationships in Precedence
Diagramming
FSAB : activity B can not start until at least FS time units after
the completion of activity A.
Models
PERT
CPM
Gantt Chart (Program Evaluation and
(Critical Path Method)
Review Technique)
Gantt Chart
Activity at
the vertical
axis
duration at the
horizontal axis
Gantt Chart
E
Activity at
D
the vertical
axis C
duration at the
horizontal axis
Critical Path Analysis using Activity-On-
Arrow Network (AOA)
Rule Each activity is only represented by
1 one and only one arrow in the
network
direction of progress
i j
1,2,3,4,5,6 A,D1,D,F,G 21
EXAMPLE
Activity Precedence
A -
Construct the AOA diagram that comprises
activities A,B,C,…..,L that the following B -
relationships are satisfied : C -
1. A,B,and C, the first activities of the project, D A,B
can start simultaneously E B
2. A and B precede D F B
G F,C
3. B precedes E,F,and H
H B
4. F and C precede G I E,H
5. E and H precede I and J J E,H
6. C,D,F,and J precede K K C,D,F,J
7. K precedes L L K
8. I,G,and L are the terminal activities of the
project
D
2 7
A
D1 4 J 8
H
D2 L
B E I
1 3 5 9
D3
C G
6
Critical Path Analysis using Activity-On-
Node Network (AON)
An arrow specifies only precedence
Rule
All nodes, with exception of terminal relations; its length has no significance
Rule 5
node, must have at least one with respect to the time duration
1
successor accompanying either of the activities
that it connects.
Rule All nodes, except the first, must have
2 at least one predecessor
The early time of an event i is determined by the length of the longest sequence
from the start node (event 1) to event i. Denote as the early time of event i, and let
implying that activities without precedence constraints begin as early as possible.
To determine for each event i, a forward pass is made through the network. Let
be the duration or length of activity (i, j).The following formula is used for the
calculations:
Important Definition and Concept
The late time of each event is calculated next by making a backward pass through
the network. Let denote the late time of event i. If n is the finish event, then the
calculations are generally initiated by setting and working backward toward the
start event using the following formula:
Activity-On-Node Network (AON) :
Calculating Early Start and Early Finish Time
of Activities ES time for the initial activity is assumed to be
zero, as it is EF.
For all other activities, the EF time is equal to its
early start time plus its duration.
ES = Early Start
LS = Late Start
EF = Early Finish
Activity-On-Node Network (AON) :
Calculating Early Start and Early Finish Time
of Activities
ES = Early Start
LS = Late Start
EF = Early Finish
Activity-On-Node Network (AON) :
Calculating Late Start and Late Finish Time
of Activities
TS = Total Slack
FS = Free Slack
Activity-On-Node Network (AON) :
Calculating Late Start and Late Finish Time
of Activities
Activity B didelay 2 minggu
Activity E didelay 6 minggu
11/18/2022 12/23/2022 1/27/2023 3/3/2023
A B C D E F G
A Start Date 44866 44880 44901 44901 44908 44957 44985
Durations 35 21 56 49 49 28 35
G
Contoh : tentukan berapa lama non-critical
activity bisa didelay untuk project dibawah
Thank you