Commercial Presentation
Commercial Presentation
Commercial Presentation
by
Chitikena Abhijith
Manager (Commercial)
Transmission – An Enabler
2
Transmission : Concurrent Subject
Transmission
ISTS
Cross-border
Intra State
Links
4
Transmission planning rules
5
Transmission : Planning to Revenue
System
Planning
i2Ren0Cv1r5)–u6(s.
Revenue Project
Realization & implementation
Operation Phase & Capex
Operational risks. Regulatory Risk for 35 Project execution risks & Mismatch
years on Return on investment. Debt re- risk .No return on investment
servicing and operational expenses to be
ensured. Commissioning
& DOCO
declaration
6
Revenue
Transmission determination
: Mode of Development
Transmission
Return on equity set by CERC Annual transmission charge for a 35-year period
Establishes norms for capital and operating is set through the bidding process
costs, operating standards and performance Projects are bid on BOOT model with provision
indicators of deemed COD
7
Transmission tariff history
Transmission was part of generation and no separate provisions existed for transmission
tariff.
Unbundled transmission did not exist till the establishment of POWERGRID in 1989.
In fact POWERGRID treated as a generation company under the definition provided in
the Electricity (Supply) Act, 1948.
The assets of POWERGRID, the sole central government transmission company, were
transferred to it from central generators such as NTPC and NHPC etc.
Tariffs have been notified by the central government on
the basis of techno economic approvals of investment given by the CEA.
Notification dated December 17, 1997 by Ministry of Power was the first attempt to
formalize the methodology of tariff setting.
o A single part tariff comprising all costs on account of interest on outstanding loans and
working capital, return on equity, depreciation, O&M expenses as per norms and income
tax.
o The full cost is recoverable at an availability of 95%.
o An incentive is given in the form of increase in ROE at the rate of upto 1% point for every
1% point increase in availability.
o A debt equity ratio within the norm of 80% maximum and 20% minimum has been used
for POWERGRID. 8
Major Responsibilities
Commercial & RC
Regulations &
Petition & Tariff Billing Collection
MIS for
Orders Disbursement
Commercial
• Billing
Since Nov, 2020, Billing of transmission charges is being done as per CERC Sharing
Regulations, 2020.
CTUIL is the nodal agency for Billing, Collection and Disbursement (BCD) of ISTS
charges on behalf of all ISTS Licensees (Pvt. as well as Govt.)
MOP vide the Gazette notification dated 09th March 2021 has notified the CTUIL,
presently a subsidiary company of POWERGRID. At present, POWERGRID is
providing back end services for BCD function as an interim arrangement to CTU.
Commercial deptt is doing the BCD function.
Sharing
Sharing Regulations, 2020 - PoC Mechanism :
Preparation, filing & pleadings of Petitions on Policy issues, chronic issues such
as
Stranded Assets, Decapitalization issues
Filing petitions for various transmission system associated with URTDSM,
SCADA/EMS replacement etc. with CERC.
Approval for formation of POWERGRID subsidiary companies (Telecom),
praying for additional O&M & tariff for particular projects (Unified Network
Management System) etc. with CERC.
Regulatory Cell
Preparation of Management Information System (MIS) for Commercial Group with
following objectives;
Billing vs Realisation and outstanding dues status
Timely submission of Petitions /replies to CERC
Detailed scrutiny of Time over run & cost over run cases to avoid tariff deduction
by CERC
Obtain timely orders from CERC and avoiding cost restrictions/disallowance of
tariff by CERC
Filing of appeals in APTEL/ Supreme court pertaining to cases where disputes has
not been resolved in CERC forum;
Preparation of appeals, attending court hearings before respective courts.
Initiates action of filing caveats in critical matters viz; issues relating to encashment
of BG, regulation of power supply, payment of transmission charges etc.
Obtaining Legal Opinion from Senior Advocates and in providing Legal
Assistance to Petition Group.
Present Constitutional Provision
& Acts
Electricity- Concurrent Subject - Entry 38 List III of Seventh Schedule to the
Constitution. Both Parliament and State Legislatures have powers to legislate.
CERC is regulator at Central level and SERCs at State level
Domain
17
Evolution of Indian Power Sector
• The Appropriate Commission shall adopt the tariff if such tariff has been
determined through transparent process of bidding in accordance with the
guidelines issued by the Central Government.
Evolution of Indian Power Sector
Transmission tariff
Transmission
Regulated Tariff
ISTS Mechanism (Section TBCB (Section 63)
Intra State 62)
Structure of Indian Electricity Sector
Policy Mandate
Central Government:
Electricity Act 2003
National Electricity Policy
National Tariff Policy
CEA:
National Electricity Plan
NITI Ayog
National Energy Policy
National Tariff Policy
Notified by the Central Government in compliance to Section 3 of the
Act
Revised Tariff Policy on 28th January
Tariff Policy on 6 January, 2006
th
2016
Guiding documents for CERC and SERCs while framing the regulations.
•Structuring of debt,
•including its tenure,
Cost of Debt •Reducing the tariff should be encouraged.
•Savings on account of subsequent restructuring of debt should be
suitably incentivized by the Regulatory Commissions
28
Date of Commercial Operation
DOCO to be determined in accordance with the provisions of the
Grid Code.
Grid Code:
DOCO: Date declared by the transmission licensee from 0000 hour of which an
element of the transmission system is in regular service after successful trial
operation for transmitting electricity and communication signal from the
sending end to the receiving end
29
Date of Commercial Operation
In case the interconnected system is not ready,
Needs to file petition before the Commission for approval of the date
of commercial operation
Licensee shall give prior notice of at least one month, to other party
and the long term customers of its transmission system, as the case
may be, regarding the date of commercial operation:
Licensee shall be required to submit proof of readiness,
correspondences and relevant certificates along with the petition:
Documents required:
CEA Energization certificate, RLDC Trial operation certificate (with or
without electrical load), Implementation Agreement, Minutes of the
coordination meetings or related correspondences, Notice issued by the
transmission licensee, Certificate of the CEO or MD of the company
regarding the completion of the transmission system
30
Application for determination
of tariff
31
Truing up
Truing Up is done for:
Capital Cost
Rate of Return on equity (MAT rate)
Interest on working capital
For transmission system commissioned prior to 1.4.2019;
Petition for True up of 2014-19 period (in accordance with CERC Tariff
Regulations, 2014) and also for determination of tariff for the period
1.4.2019 to 31.3.2024 (in accordance with CERC Tariff Regulations, 2019)
Capital cost admitted as on 31.03.2019 shall form the basis of the opening
capital cost as on 1.4.2019.
Till issuance of tariff orders, transmission charges as approved by the
CERC earlier shall be billed.
For transmission system commissioned after 1.4.2019;
True up to be done only after completion of Tariff block (after
31.03.2024) and only POC petition needs to be filed.
32
Truing up
Scenario Provision
Original tariff >True up tariff Excess recovered tariff to be
refunded with simple interest
Projected Capital cost (original petition) falls recover the tariff recovered
short of the actual cost incurred (True up) on corresponding to the additional
year to year basis by more than 10% capital expenditure, along with
interest at the bank rate
‘Bank Rate’: MCLR of SBI issued from time to time plus 350 basis points
33
Capacity Charge
The Annual Fixed Cost (AFC) shall consist of the following
components:
Return
on
equity
Interest
on
Depreciation
working
capital
Tariff
Components
Interest
O&M
on loan
expenses
capital
34
Price Determination
(Cost of Service and Incentive based regulation)
Project Lifecycle
-2 0 12 25/35
Cost Heads
Sl.
No.
C Civil works
i) Infrastructure
ii) Non- Residential Buildings
Equity Return on Equity (15.5%)
iii) Colony 30%
D Equipment Cost
i) Transmission Lines
ii) Sub - Stations O&M Expenses (Normative)
iii) Special T&P
F
Incidental Expenditure During Construction (IEDC) Interest on Working capital (Normative)
incl. contingencies
Capital
Cost
36
Prudence Check of
Capital Cost
Provided that, while carrying out the prudence check, the Commission shall
also examine whether the generating company or transmission licensee, as
the case may be, has been careful in its judgments and decisions in
execution of the project.
37
IDC and IEDC
(1) Interest during construction (IDC) shall be computed corresponding to the loan
from the date of infusion of debt fund, and after taking into account the prudent
phasing of funds upto SCOD.
(2) Incidental expenditure during construction (IEDC) shall be computed from the
zero date, taking into account pre-operative expenses upto SCOD:
(3) In case of additional costs on account of IDC and IEDC due to delay in
achieving the COD,
to furnish detailed justifications with supporting documents for such delay
including prudent phasing of funds in case of IDC and details of IEDC during the
period of delay and
liquidated damages recovered or recoverable corresponding to the delay
38
IDC and IEDC
Delay in achieving the COD is not attributable to the transmission
licensee,
IDC and IEDC beyond SCOD may be allowed after prudence check and
The liquidated damages, if any, recovered shall be adjusted in the capital cost
IDC and IEDC beyond SCOD may be disallowed after prudence check
either in entirety or on pro-rata basis corresponding to the period of delay
not condoned and
39
Controllable and Uncontrollable factors
Controllable and uncontrollable factors for deciding time over-run, cost
escalation, IDC and IEDC of the project:
(1) The “controllable factors” shall include but shall not be limited to the
following:
(2) The “uncontrollable factors” shall include but shall not be limited to following:
40
Change in Law
‘Change in Law’ means occurrence of any of the following events:
41
Force Majeure
‘Force Majeure’
partly or fully prevents the generating company or transmission licensee to
complete the project within the time ….., and only if such events or circumstances
are not within the control of …..and could not have been avoided…….
Delay in obtaining statutory approval for the project except where the delay
is attributable to project developer
42
Initial Spare
Initial spares shall be capitalized as a percentage of the Plant and
Machinery cost, subject to following ceiling norms:
(i) Transmission line -
1.00%
(ii) Transmission Sub-station
- Green Field 4.00%
- Brown Field 6.00%
(iii) Series Compensation devices and HVDC Station - 4.00%
(iv) Gas Insulated Sub-station (GIS)
- Green Field 5.00%
- Brown Field 7.00%
(v) Communication system - 3.50%
(vi) Static Synchronous Compensator - 6.00%
Plant and Machinery cost shall be considered as the original project cost
excluding IDC, IEDC, Land Cost and Cost of Civil Works.
Transmission licensee for the purpose of estimating Plant and Machinery Cost,
shall submit the break-up of head wise IDC and IEDC in its tariff application;
43
Additional Capitalization upto
the cut-off date
Cut-off Date’ means the last day of the calendar month after thirty six months
from the date of commercial operation of the project;
44
Additional Capitalisation after
the cut-off date
The additional capital expenditure incurred after the cut-off date may be
admitted by the Commission, subject to prudence check:
(f) Liability for works admitted by the Commission after the cut-off date to the extent
of discharge of such liabilities by actual payments;
45
Availability
For AC system: For HVDC bi-pole links and HVDC back-to-
for tariff recovery: 98% back Stations:
for incentive: 98.5% for tariff recovery: 95%
for incentive: 97.5%
Availability shall be calculated on monthly
basis. New HVDCs
Normative Availability
• 1st 12 months : 85%
• for incentive: 97.5%
46
Sharing of saving/ other Income
47
Steps from Petition Filing To Tariff Order
Tariff petitions containing the detailed calculations of different elements of tariff alongwith all
relevant documentary evidence is to be filed before CERC for all assets that are to be capitalized .
Replies by Comml.
Petition Technical
to TVs with inputs
Validation/ queries
filing from concerned
by CERC
deptts
Reply Rejoinders to
RoPs Final Hearing
Respondents
48
Information in Petition
Approval of the scheme
Scheme approval
Investment approval (IA)
Initial spares
IDC/IEDC summary
Additional capitalisation
Sharing methodology
Tariff forms
49
Issues
Restriction due to Revised Cost Estimate/ FR
Cost restricted due to cost overrun.
50
Issues
O&M Add-Cap
For renovation of Buildings not allowed as same is not critical for System operations and
may be approved after RPC/SCM approval
Restricted in absence of OEM certificates and RPC/SCM approval for replacement of
equipment.
Decapitalisation before useful life
Remaining depreciation not allowed by CERC even if decapitalization is done after due
approval as per System requirement
In case of Re capitalization, carrying cost for intermediate period not allowed.
o Rs 6.86 Crs decapitalized from Indo Bangla project for removal of LILO of 400 kV S/C Farakka-
Jeerat Trans. Line at Baharampur.
o In case of Series Compensation on Panki- Muradnagar 400 KV S/C line of UPPCL in Northern
Region, Asset de-cap due to not in use w.e.f 31.10.2015. (De-cap around Rs.12.73 Cr).
o 315 MVA, 440/220 KV ICT-IV at Ballabgarh Substation with associated bay equipments in
Northern Region tariff allowed upto 12.06.2017 (Rs.5.85 Cr).
51
Projects under Cost Plus
Transmission Charges
Determined by the Central Electricity Regulatory Commission (CERC)
based on Terms and Conditions of Tariff Regulations which are notified
for a block period of five years.
Currently, Tariff Regulations for 2019 -24 are in vogue
Tariff Regulation contain the financial norms as well as operational norms.
Tariff is usually called the cost plus tariff as it is determined on the basis of
capital cost.
Tariff petitions containing the detailed calculations of tariff for different
elements as per the tariff forms along with all relevant documentary
evidence is to be filed before CERC for all assets that are to be capitalized.
Tariff is approved by CERC after the regulatory process through an order
in the petition.
Components of Tariff – Cost Plus
Depreciation
Debt Funding
Interest on Loan
Capital Cost & Capital
Capital Structure
Equity Funding
Return of Equity
Project
Interest on
Working Capital
Tariff Components
• Predefined rates for first 12/13 years and thereafter Straight line method (SLM) over useful
life of asset
• This component is for recovering principal portion of loan deployed in the project.
Asset Particulars Depreciation Rate
(Salvage Value=10%)
Land 0% (full ownership)
3.34% (under lease)
Building & Civil Engineering 3.34%
works
Transmission lines 5.28%
Substation equipments 5.28%
Communication equipments 6.33%
including Fibre Optic
IT equipments including 15.00%
software
56
Tariff Components
RoE Depreciation IOL O&M IOWC
Principal repayment considered equal to depreciation,
Actual rate of interest based on loan portfolio.
Debt - 70% of total capital cost or actual whichever is more
Sample Calculation:
IOL Calcualtion
Opening Loan (Rs Crs) 70.00
New Loan in year 0.00
Repayment as depreciation 5.28
Closing loan 64.72
Average Loan 67.36
Weighted average rate of
interest 8%
IOL (Rs Crs) 5.39
57
Tariff Components
RoE Depreciation IOL O&M IOWC
O&M : Predefined rates linked to configuration and voltage level of Tr. System
Particulars 2019-20 2020-21 2021-22 2022-23 2023-24
Norms for sub-station Bays (Rs Lakh per bay)
765 kV 45.01 46.60 48.23 49.93 51.68
400 kV 32.15 33.28 34.45 35.66 36.91
220 kV 22.51 23.30 24.12 24.96 25.84
132 kV and below 16.08 16.64 17.23 17.83 18.46
Norms for Transformers (Rs Lakh per MVA)
765 kV 0.491 0.508 0.526 0.545 0.564
400 kV 0.358 0.371 0.384 0.398 0.411
220 kV 0.245 0.254 0.263 0.272 0.282
132 kV and below 0.245 0.254 0.263 0.272 0.282
Norms for AC and HVDC lines (Rs Lakh per km)
Single Circuit (Bundled Conductor with six or more
sub-conductors)
0.881 0.912 0.944 0.977 1.011
Single Circuit (Bundled conductor with four sub-
conductors)
0.755 0.781 0.809 0.837 0.867
Single Circuit (Twin & Triple Conductor) 0.503 0.521 0.539 0.558 0.578
Single Circuit (Single Conductor) 0.252 0.260 0.270 0.279 0.289
Double Circuit (Bundled conductor with four or more
sub-conductors)
1.322 1.368 1.416 1.466 1.517
Double Circuit (Twin & Triple Conductor) 0.881 0.912 0.944 0.977 1.011
Double Circuit (Single Conductor) 0.377 0.391 0.404 0.419 0.433
Multi Circuit (Bundled Conductor with four or more
sub-conductor)
2.319 2.401 2.485 2.572 2.662
Multi Circuit (Twin & Triple Conductor) 1.544
रेगुलेटरी सेल 1.598 1.654 1.713 1.773
58
Tariff Components
RoE Depreciation IOL O&M IOWC
IOWC
Working capital considered
Working capital accounting for 45 days receivables
Maintenance Spares @15% of O&M and
1 month O&M
Rate of Interest considered
Bank rate linked to one year MCLR of SBI plus 350 bps
Sample Calculation
IOWC Calculation
O&M expenses a
Maint. Spares b
Receivables c
Total Working capital =(a+b+c)
Rate of Intt. 12.05%
IOWC =(a+b+c)*.1205
59
Tariff Structure (Cost Plus)
a) Return on Equity
b) Interest on Loan capital
c) Depreciation Annual Fixed Cost
d) Interest on Working capital
(As per CERC order)
e) O&M expenses
Minimum Availability
AC: 98% HVDC : 95%
If availability is less than the above norms, reduced recovery of transmission charges
Normative Availability for the purpose of Incentive
AC: 98.5% HVDC : 97.5% Ceiling : 99.75%
If availability is more than the above norms-
Monthly Availability
Annual Fixed Cost X = Tr. Charges
Normative Availability for incentive
Asset : 400kV D/C Quad Transmission Line (31.5 km) along with bays at
both end
61
Sample Calculation of Yearly Transmission Tariff
400kV D/C Quad Transmission Line (31.5 km) along with bays at both end
62
Sample tariff for 35 years for a 400kV D/c Quad line
Year ROE Depreciation IOL IOWC O&M Total
1 5.63 5.28 5.39 0.32 1.70 18.33
2 5.63 5.28 4.97 0.32 1.76 17.96
3 5.63 5.28 4.54 0.31 1.82 17.59
4 5.63 5.28 4.12 0.31 1.88 17.23
5 5.63 5.28 3.70 0.31 1.95 16.87
6 5.63 5.28 3.28 0.30 2.02 16.51
7 5.63 5.28 2.85 0.30 2.09 16.15
8 5.63 5.28 2.43 0.30 2.16 15.80
9 5.63 5.28 2.01 0.29 2.23 15.45
10 5.63 5.28 1.59 0.29 2.31 15.10
11 5.63 5.28 1.16 0.29 2.39 14.75
12 5.63 5.28 0.74 0.28 2.47 14.41
13 5.63 5.28 0.32 0.28 2.56 14.07
14 5.63 0.97 0.07 0.22 2.64 9.53
15 5.63 0.97 0.02 0.22 2.73 9.57
16 5.63 0.97 0.22 2.83 9.66
17 5.63 0.97 0.23 2.93 9.76
18 5.63 0.97 0.23 3.03 9.86
19 5.63 0.97 0.24 3.13 9.97
20 5.63 0.97 0.24 3.24 10.08
21 5.63 0.97 0.25 3.35 10.20
22 5.63 0.97 0.25 3.47 10.32
23 5.63 0.97 0.26 3.58 10.45
24 5.63 0.97 0.26 3.71 10.58
25 5.63 0.97 0.27 3.84 10.71
26 5.63 0.97 0.27 3.97 10.85
27 5.63 0.97 0.28 4.10 10.99
28 5.63 0.97 0.28 4.25 11.14
29 5.63 0.97 0.29 4.39 11.29
30 5.63 0.97 0.30 4.54 11.45
31 5.63 0.97 0.30 4.70 11.61
32 5.63 0.97 0.31 4.86 11.78
33 5.63 0.97 0.32 5.03 11.95
34 5.63 0.97 रेगुलेटरी सेल 0.33 5.20 12.13
35 5.63 0.97 0.33 5.38 12.32
63
Tariff Components
RoE IOL Depreciation O&M IOWC
All 5 components together form the total tariff of POWERGRID transmission asset as per the CERC
regulation.
20.00
18.3
3
18.00
16.00
14.00
12.323
12.00
Total
9.53
10.00
3
8.00
6.00
4.00
2.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
64
New Tariff Regulation Notification
65
New tariff Block
Parameters Existing in Tariff Regulations, Proposed in Draft Tariff Regulations,
2019-24 2024-29
Debt: Equity Ratio 70:30 Retained as TR 2019-24
Base Rate Existing Projects Pre-tax Return on equity at 15.50% Retained as TR 2019-24
of RoE for all Transmission
New Projects Transmission :- 15 %
Accelerated depreciation for 12 years and Same as TR 2019-24 expect following
after 12 years balance depreciation spread
o IT eqp incl. Software & SCADA System: 15%
Existing Projects over remaining useful life. o Communication equipment : 15 %
Rate of Depreciation: o Fibre Optic/OPGW :5.28 %
o S/S & TL- 5.28 % o Batteries : 9.5 %
o I. T Equipment including software: Accelerated depreciation for 15 years for S/S & TL
Depreciatio 15% and after 15 years, balance depreciation spread over
n o Communication equipment: 6.33 % remaining useful life.
New Projects o Batteries: 5.28 % Rate of Depreciation
o S/S & TL- 4.22 %
Depreciation same for other items as provided
for Existing Projects
Working capital consists of
• 45 days receivables,
• 1 month O&M expenses & Retained as TR 2019-24
IOWC • Maintenance spares @ 15% of
Projects O&M Exp
Rate of IoWC = 1 Yr SBI MCLR+350 Basis
Points
O&M Rates : Per MVAr rate introduced for Reactors irrespective of Voltage level
Per MVA rate for ICTs irrespective of Voltage level
68
CERC Sharing Regulations, 2020
Background
70
Tariff of ISTS Licensee
Responsibilities:
Billing
Invoicing to all DICs
Collection
Payment Collection in a
Common Pool Account
Disbursement
Proportionate
Disbursement to
ISTS Licensees
CTUs Role
CTU
Disbursement to ISTS
Licensees on a prorated
manner, in the ratio of MTC
given by NLDC
L1 L2 L3 Ln
Background
These regulations came into force with effect from 1st November, 2020 superseding
Central Electricity Regulatory Commission (Sharing of inter-state transmission
charges and losses) Regulations, 2010.
Transmission Sharing Methodology in Sharing Regulations,2020
3. Transformers Component
1. National Component 2. Regional Component 4. AC system component
(TC) : Trans. Charges for ICTs (ACC) : Balance Trans.
(NC) : To be shared among (RC) : To be shared by DICs
planned for drawl of power. To be Charges for AC system
all DICs in the ratio of their of beneficiary region in the
borne by State for whom it is excluding 1, 2 & 3
LTA+MTOA ratio of their LTA+MTOA
planned
(b) 100% of NER Agra, Back to back (b) STATCOM, SVC, Bus Reactor Spare
HVDC, Mudra Mohindargarh ICT & Reactor and any other element
(for1005 MW) & 30 % of all other critical for grid security as identified by (b) Balance component (AC-BC) : ( 4-
HVDC bi pole CTU * 4(a) ) to be shared among all DICs in
ratio of LTA+MTOA
* Where separate transmission charges are not available, the transmission charges shall be worked out and provided by CTU
Notification of Trans. Charges by Implementing Agency (NLDC)
Transmission Charges for Designated ISTS Customers (DICs) for the billing month of November,2023
4 Haryana NR 4412 405889903 767378974 119070492 100012546 209630238 203134563 2313176 1807429892
6 Rajasthan NR 4053 316398180 704810351 109362021 91857974 192537933 89257575 2064918 1506288952
Rebate and Late Payment surcharge: in line with tariff Regulations 2019
• Rebate: 1.50% for payment within 5 days and 1% after 5 days and within a period
of 30 days of presentation of bills.
→
• LPS: LPS shall be as per LPS rules 2022 and its amedments
Delay in issuance of RTA: CTU may raise provisional bills based on last available RTA
and subsequently raise adjustment bills when RTA is issued.
Payment Security Mechanism
DIC to open LC for amount equal to 2.10 times average amount of First Bill of a
Year( 1.05 times if TPA is signed) not later than 1 month prior to the date of
operationalization of LTA/MTOA
If DIC fails to pay any bill or part by the Due Date, CTU may encash the LC
The DICs shall renew LC 30 (thirty) days prior to the date of expiry.
In case of failure on the part of any DIC to maintain LC, CTU may regulate the power
Collection and Disbursement
First Bill: CTU shall raise the First Bill for billing period as per Regulations 5 to 8 of
Sharing Regulations 2020 in the first week of relevant billing month as per
procedure given below :-
First Bill shall be raised within one(1) working day after publishing of
Regional Transmission Account (RTA) by Regional Power Committees
(RPCs) of respective region as per the timeline given in the Sharing
Regulations, 2020.
In case RTA is not published by the 4th day of the billing month, CTU shall
raise provisional first bill on the next working day of the billing month as
per the last available RTA. Subsequently, CTU shall raise adjustment bill
within two working days after publishing of RTAs by all RPCs for the billing
month after considering provisional first bill.
Second Bill:
Second bill shall be raised on quarterly basis for April to June(Q1), July to
September(Q2), October to December (Q3) and January to March(Q4)
period. The bill shall be raised in the month of September, December,
March and June for Q1, Q2, Q3 and Q4 respectively.
One month prior to raising the second bill, ISTS licensee shall submit to
CTU, the final monthly transmission charges for the billing period which
is inclusive of approved MTC, incentive based on the certified
transmission system availability by RPCs and any other charges leviable
as per CERC Regulations/orders etc. in the prescribed format in the form
of excel sheets, PDF copy / hard copy duly signed by the designated
official of the ISTS Licensee.
ISTS licensee (RTM) shall include in second bill, any net savings in interest
resulting from re-financing or restructuring of loan to be shared with DICs
as per CERC (Terms & Conditions of Tariff) Regulations, 2019, as amended
from time to time, alongwith support documents.
Surcharge Bill:
CTU shall raise the Surcharge Bills as per following procedure:
Surcharge on outstanding dues of First Bill and Second Bill beyond due
date shall be calculated and billed on monthly basis.
ISTS Licensee, whose assets are covered under Clause (3), (6), (9) & (12)
of Regulations 13 shall submit their YTC data to Implementing Agency.
Generator, who has to receive YTC from ISTS Licensee as per Clause (8) of
Regulation 13, shall submit its claim it to the Implementing Agency.
After publishing the RTA, CTU, along with First Bill, shall also raise the
bilateral bill on behalf of the ISTS Licensee/Generator for specific cases to
entities from whom transmission charges are to be recovered.
After receipt of the payment against the bills raised for specific cases,
same shall be disbursed to concerned ISTS Licensee/ Generator.
If any dispute is raised by either entity in these special cases, same shall
be settled mutually between the parties without any prejudice to their
respective liabilities under the Central Electricity Regulatory Commission
(Sharing of Inter-State Transmission Charges and Losses) Regulations,
2020, without any liability to CTU.
Payment:
Mode of payment:
Due date of the payment shall be 45 days from presentation of bill as per
Regulation 16 of the Sharing Regulations 2020 or as amended from time
to time.
Except for the due date being a Bank Holiday, any delay in transfer of
money to the Designated Account of CTU due to any other reasons shall
be to the account of the concerned DIC. Date of payment shall be the
date of actual credit of payment into designated account of CTU.
Rebate :
Rebate deducted by a DIC from payment against First & Second Bill shall
be reviewed and any adjustment due to wrong deduction of rebate by
the DIC shall be made in the First Bill in the following month.
Rebate deducted by a DIC from the payment against Third Bill shall be
reviewed and any adjustment due to wrong deduction of rebate by DICs
shall be made in the subsequent Third Bill in the following month.
Payment Information:
DICs shall provide the information of payment for each and every transaction
made through electronic transfer to designated account of CTU, strictly adhering
to the format prescribed compulsorily within One(1) working days of making any
transaction to facilitate timely settlement of bills.
Adjustment of Payment
The payment received from a DIC shall be first adjusted towards late
payment surcharge on the outstanding dues and thereafter, towards
other outstanding bills, starting from the longest overdue bill (FIFO
method), as indicated in 20 (6) of Sharing Regulations 2020.
Any Tax deducted by DICs shall be apportioned and adjusted with the
ISTS Licensee in whose name TDS has been deducted and corresponding
TDS certificate issued by DIC.
Bill shall be considered correct, complete and conclusive between the DIC and
the CTU unless the DIC disputes the Bill within thirty (30) days of receiving it.
However, if any issue is brought out by the DIC at the later date, it shall be
reviewed by CTU for necessary action and same shall not be treated as bill
dispute.
If any error in raising the bill on account of CTU is intimated by DIC, same shall
be reviewed and CTU shall raise supplementary bill, if required, within Seven
(7) days of getting intimation from DIC.
If a DIC raises a dispute regarding any item or part of an item set out in a bill
raised by CTU as per regulation 5 to 8 of Sharing Regulations 2020, following
procedure is to be followed :-
a. Dispute must be raised by the DIC within 30 (Thirty) days of presentation
of the bill.
b. DIC shall serve a notice (a "Bill Dispute Notice") on the CTU setting out
(i) the item or part of an item which is in dispute, (ii) its estimate of
what such item or part of an item should be, (iii) and with all
documentary evidence in support of its claim.
c. If the bill has been raised by CTU as per RTA issued by RPCs and in case
DICs is not in agreement to amount of bill in the RTA, the DIC instead of
bill dispute notice, shall inform concerned RPCs/Implementing Agency
for correction in RTA with a copy to CTU. On revision of RTA, CTU shall
raise a supplementary bill.
d. If the CTU agrees to the claim raised in the Bill Dispute Notice issued
pursuant to Clause (b), CTU shall raise Supplementary Bill within fifteen
(15) days of receiving such notice from the disputing DIC and if the
disputing DIC has already made the excess payment against bill under
dispute, CTU shall adjust the excess amount (Supplementary Bill) against
the next month bill/refund the excess amount in case no next bill to be
raised.
e. If the CTU does not agree to the claim raised in the Bill Dispute Notice
issued pursuant to Clause (b), it shall, within fifteen (15) days of
receiving the Bill Dispute Notice, furnish a clarification to the disputing
DIC providing reasons thereof.
f. In case of disagreement to CTU clarification to the Bill Dispute Notice
under Clause ( e ) above, authorised representative(s) of the disputing
DIC and the CTU shall make best endeavours to amicably resolve such
Dispute within thirty (30) days thereafter.
g. If the disputing DIC and the CTU do not amicably resolve the dispute
pursuant to Clause ( f ), either party may approach the CERC for
adjudication of dispute.
h. If a Dispute regarding a Bill is settled pursuant to Clause ( f ) or by
Dispute resolution mechanism pursuant to Clause ( g ) in favour of the
disputing DIC that issued the Bill Dispute Notice, the CTU shall give
credit adjustment through a Supplementary Bill or through first bill in
the following month. Alternately, if the Dispute is settled in favour of
the CTU, then such amount as disputed shall be payable by the disputing
DIC along with the Late Payment Surcharge, as applicable.
i. For the avoidance of doubt, it is clarified that despite a Dispute
regarding the Bill which has been raised in accordance with RTA/RTDA as
per Regulations and these Procedures, the concerned DIC shall, without
prejudice to its right to the Dispute, be under an obligation to make
timely payment as per the bill raised. On resolution of the issue,
necessary adjustments shall be passed on by CTU to the DIC.
Billing & Collection Performance during FY 22-23
Status as on 01.04.2023 Rs. in Cr.
All ISTS Licensees POWERGRID Portion
Billing Collection Dues Billing Collection Dues
Dues as on
5231 4312
31.03.2022
Apr-22 3454 2436 6249 2973 2158 5127
May-22 3583 3170 6661 2834 2488 5473
Jun-22 3348 2869 7140 2644 2261 5856
Jul-22 7422 3395 11167 6606 2938 9524
Aug-22 3412 5037 9543 2704 4099 8130
Sep-22 3546 4958 8131 2804 4157 6777
Oct-22 8031 5261 10900 7255 4493 9539
Nov-22 3553 4128 10325 2835 3391 8983
Dec-22 5077 4776 10626 4269 4018 9234
Jan-23 3897 5483 9040 3150 4696 7688
Feb-23 3723 5074 7689 2950 4190 6448
Mar-23 3947 5955 5681 3172 4799 4821
Total 52992 52542 44196 43688
Trade receivables
39.81
(equivalent days)
An Empowered organization is the one in which
individuals have the knowledge, skill, desire and
opportunity to lead collective organisational
Success
64
CTU Graded Rebate Table
0-15 days 16-30 days 31-45 days ←
Days Rebate Days Rebate Days Rebate (%)
(%) (%)
T+0 1.65 T+16 1.30 T+31 0.50
T+1 1.65 T+17 1.28 T+32 0.45
T+2 1.65 T+18 1.26 T+33 0.40
T+3 (*) 1.65 T+19 1.24 T+34 0.35
T+4 1.50 T+20 1.22 T+35 0.30
T+5 1.50 T+21 1.20 T+36 0.25
T+6 1.50 T+22 1.18 T+37 0.20
T+7 1.48 T+23 1.16 T+38 0.15
T+8 1.46 T+24 1.14 T+39 0.10
T+9 1.44 T+25 1.12 T+40 0.05
T+10 1.42 T+26 1.10 T+41 0.05
T+11 1.40 T+27 1.08 T+42 0.05
T+12 1.38 T+28 1.06 T+43 0.05
T+13 1.36 T+29 1.02 T+44 0.0
T+14 1.34 T+30 1.00 T+45 0.0
T+15 1.32