03 ApprovalRequest Training2012
03 ApprovalRequest Training2012
technical part
Technical Training
11 July 2012 – Cluj
Eng. Michele Lauritano
Contents
•PV Projects
•Tools:
•CRM
•Approval
•Approval process
•Technical Approval Sructure:
•Project location
•Array data
•Inverter details
•Grid connection
•Grid codes
•Environmental detals
•Buyouts
•Conclusions
PV projects
A PV project in Emerson CT is characterized by:
Several departments/people involved in different countries: Sales, Engineering (and
E&D), Purchase, Manufacturing.
Variable time from rise of interest to order
Variable project characteristics but standard product
High risk involved in projects
Documentation attached to the project:
Data of the project (technical, commercial, communications) need to be collected,
analyzed and sorted.
Pricing info or quotations have to be created
Technical analysis to be done: sizing, check of requirements, ad hoc analysis (PVSOl
PVSyst, temperature, etc…)
Others (contacts, datasheet, brochure, orders, contracts, etc..)
PV Projects - Order Winning Process
1. Find Sales = Red
Prospect Systems & Project
Management = Blue
Internal Sales = Yellow
2. Raise
Interest
PV Approval
9. Prepare
Request.xls, 4. Qualify
Quotation &
CRM Super Sizing Tool.xls Project
Contract
Office
5. Collect
Technical
Requirements
6. Develop
Technical
Proposal &
Approval
Ok
13. Receive
Order
Tool - CRM - Super Office
Collecting all relevant contact infos and relationship for:
Customers, Investors, Suppliers, Enduser, Partner
Collecting all project infos and the relationships to different contacts
Entering all sales opportunities to provide an actual pipeline for planning
processes like capacity and POR
Approved
Check Ok
Sizing if Possible To Quote
PV Approval Request
Quotation for :
Inverter
Approved
Sizing Tool Check Ok
To Quote
Quotation for :
Inverter-Station PV Approval Request
String Boxes
Scada System
Technical Check
Qualifying Docu Check Approved
Ok Check Ok
New Supplier Capacity Check To Quote
Frame Contract
PV Array data:
Inverter details:
MPP range
Obtained from VAC
Grid tolerances
Are derived from sizing: they determine the quality of the sizing or how much the sizing is
tolerant to variation of parameres (grid voltage, MPP range, utilization)
Grid codes – compliance
Europe:
Germany: BDEW2008 unit certificate (TUF Nord) and simulation model for plant certificate
Italy: CEI0-16 declaration + MV monitoring
France: Arrêté du 23 avril 2008 declaration + approval process
Spain: RD661 and RD1565/2010 requiring FRT for plant > 2MW
UK: G59/2 fulfill requirements for acceptance + G59/2 relay in MV + possible test at
commissioning
Connection can be done also: Czech Republic, Belgium, Greece, Poland - acceptance on project
base, possible negotiation with power utility.
Middle East
Israel: E&D engaged
Asia:
Thailand: PEA declaration and additional V/F protection relay
India: inverter offered with European certification (BDEW2008) and compliance to be proved case
by case (different rules for each state).
US:
UL1741 certification in progress
Environmental details
Check altitude:
– H <1000m ok
– 1000m < H <2000mm derating of 1% per 100m
– 2000m < H <3000mm derating + no chopper
– H>3000 not possible…
Pollution/dust/salinity:
– in extremely dusty conditions or close to the sea (<1.5km) cooling through
ventilation is not advised (air conditioning)
Ambient temperature:
– point of start for the temperature used in sizing
– Temperature checked from internet database/measures provided/PV Sol historical
min/max are used
Buyouts
Shelter:
– Concrete:
• Graeper - Germany
• Ferrari - Italy
• Ormazabal / Selma - Spain
– Metal: Elbag
Transformer:
– Siemens, EGB, or provided by shelter manufacturer
Switchgear:
– Ormazabal, Schneider, or provided by shelter manufacturer.
PCC and Power measurement: depending on country
Only approved components can be offered.
Array monitoring and SCB
Report in comments:
– All useful consideration done in sizing
– Calculation (PV Sol, PV Syst projects)
– Project-specific observation
– Open points/questions to ask to customer/sales engineer/technical engineer
Final approval:
– According to the stage of the project (Approval need to be updated in case of modifications
on project)
– Comments referring to the stage
– Dates
– Conditional approval in case some information still need to be confirmed/filled in
Conclusions
The technical approval is quick summary of the data of the project
with enough details to create the quotation and justify it technically.
How to fill in the approval
– Fill in the approval as well as you can (according to the stage:
preliminary, quotation, 2nd quotation etc..)
– Key-information need to be contained in approval and not only in
emails…
– Put a note if something is not clear/sure or if more cases apply.
– Put a note if something changes (possibly with a date of modification)
– Refer clearly to analysis/documents/email inside the approval; in case
add an object/attachment
– A well compiled approval saves a lot of time!
Questions ?
Thanks for your attention