1.3 QS & Terminology
1.3 QS & Terminology
1.3 QS & Terminology
UNIT-1: INTRODUCTION –
QUANTITY SURVEYING & TERMINOLOGY
Wikipedia.
In 1971, the Royal Institution of Chartered Surveyors (RICS) published a report titled The
Future Role of the Quantity Surveyor, which defined the work of the quantity surveyor
as:
‘…ensuring that the resources of the construction industry are utilised to the best advantage
of society by providing, inter alia, the financial management for projects and a cost
consultancy service to the client and designer during the whole construction process.’
QS developed its root in UK during 17th century
1785--Earliest recorded firm, Henry Cooper and Sons of Reading was established
1802-A number of Scottish quantity surveyors met to produce the first method of
measurement
1820--Emerged as a profession, one of the earliest QSs was Sir Henry Arthur Hunt in
Uk
1858--First recorded use of term “quantity surveyor”
1881-Royal Institution of Chartered Surveyors (RICS) was set up and is an
independent professional body which regulates property professionals and surveyors
in the UK and worldwide. The RICS provide education and training standards to all
members and protects consumers with strict codes of practice. The motto of the RICS
is “Est modus in rebus” (which translates into English as: “There is measure in all
things”).
Red Book
is a budget setting technique which considers the major elements of a building and
provides an order of cost estimate based on an elemental breakdown of a building
project.The elemental method can also be used to develop an initial cost model as a
prerequisite to developing an elemental cost plan. The method involves the use of
element unit quantities (EUQ) and element unit rates (EUR).
Elemental cost analysis (or cost analysis) –
is the usable area within a building measured to the internal face of the perimeter
walls at each floor level.The rules of measurement of net internal area are
defined in the latest edition of the RICS Code of Measuring Practice.
Nominated subcontractor/supplier
Available under some contracts where a subcontractor/supplier is selected by the
architect or engineer and not by the contractor.
Prequalification
The provision by a contractor of information as part of a preselection process.
Preselection
The establishment of a list of contractors with suitable experience, resources,
ability and desire to execute a project, bearing in mind the character, size,
location and timing of the project.
Prime cost (PC)
Under some contracts, prime cost sums are used in bills of quantities and
specifications for work to be carried out by nominated subcontractors or suppliers
of materials and goods. The contractor may also be invited to carry out work
covered by a PC sum in certain instances.
Project overheads
The cost of administering a project and providing general plant, site staff, facilities
and site-based services and other items not included in all-in rates.
Project strategy
Choice of implementation strategy and contract type.
Provisional sum
A sum included in bills of quantities for work anticipated but insufficiently
designed or detailed to permit descriptions and measurement in accordance with
the requirements of the Standard Method of Measurement (SMM).
are preliminaries that relate specifically to the work that is to be carried out by a
work package contractor.
Working Rule Agreement (WRA)
National Working Rules for the building industry produced by the National Joint
Council for the building industry.