Capital Budgeting
Capital Budgeting
Capital Budgeting
Edited by
Amit Kumar De
M.COM., M.A., M.B.A.,
M.Phil., A.I.C.W.A., L.L.B.,PGDFA,CFM
Long Term Investment Decisions
• Reliance Industries diversifies into the
Telecommunications Section’, ‘Reddy’s Labs set
up a new plant in Andhra Pradesh’ and so on.
What do all these mean? These news headlines
are typical examples of capital expenditure
decisions.
• Capital mean Capital expenditure and Budgeting
means planning – therefore capital budgeting
means planning for such expenditure whose
benefit is received beyond one year
Planning for Capital Expenditure
INVESTMENT
CRITERIA
DISCOUNTING NON-DISCOUNTING
CRITERIA CRITERIA
n Ct
NPV = – Initial investment
t=1 (1 + rt )t
NET PRESENT VALUE
The net present value of a project is the sum of the present values of all the cash
flows associated with it. The cash flows are discounted at an appropriate
discount rate (cost of capital)
Naveen Enterprise’s Capital Project
Year Cash flow Discount factor Present
value
0 -100.00 1.000 -100.00
1 34.00 0.870 29.58
2 32.50 0.756 24.57
3 31.37 0.658 20.64
4 30.53 0.572 17.46
5 79.90 0.497 39.71
Sum = 31.96
Pros Cons
• Reflects the time value of money • Is an absolute measure and not a relative
If - Decision Rule
Discount rate
The internal rate of return (IRR) of a project is the discount rate that
makes its NPV equal to zero. It is represented by the point of
intersection in the above diagram
Net Present Value Internal Rate of Return
• Assumes that the discount • Assumes that the net
rate (cost of capital) is known present value is zero
• Calculates the net present • Figures out the discount rate
value, given the discount that makes net present
rate value zero
Calculation of IRR with NPV
You have to calculate NPV at 20% discount rate and also calculate IRR. Try a
few discount rates till you find the one that makes the NPV zero
Year Cash Discounting Discounting Discounting
flow rate : 20% rate : 24% rate : 28%
Discount Present Discount Present Discount Present
factor Value factor Value factor Value
1.See whether the NPV determined +ve/ -ve. If +ve ,then try
successively higher discount rate from the given rate , if
- ve ,then try successively lower discount rates until we get
the rate at which NPV marginally below zero and the rate
at which NPV is marginally above zero.
5.13
24% + 28% - 24% = 26.24%
5.13 + 4.02
Calculation of IRR without NPV
Step–1: Find the average annual cash inflow after taxes
Step–2: Find the Fake pay back period = Initial outlay/Step
1 figure.
Step–3: From the table, find the interest rate at which the
PV of annuity of Re. 1 will be nearly equal to the figure
got in step 2 for the relevant life of project.
Step–4: Use the interest rate got in step 3 as the
initial value for starting the trial and error process and
keep trying at successively higher or lower rates of interest
until we get the rate at which NPV marginally below zero
and the rate at which NPV is marginally above zero.
Step–5: Use the interpolation to determine the approximate
value of IRR between the two interest rates.
© Centre for Financial Management, Bangalore
© Centre for Financial Management, Bangalore
FINANCIAL APPRAISAL OF A PROJECT
INVESTMENT
CRITERIA
DISCOUNTING NON-DISCOUNTING
CRITERIA CRITERIA
So , A = FV of an annuity * r / [(1+r)n-1]
= FVA * Sinking Fund Factor
S.F.F. = r / [(1+r)n-1]
= 1 / [(1+r)n-1]/ r
= Reciprocal of FVIFA
Capital Recovery Factor
PV of an annuity = A [(1+r)n-1]/ r (1+r)n
0 1 2 n–1 n
C0 A= C1 = C2 … = C3 … = Cn =A
© Centre for Financial Management, Bangalore
© Centre for Financial Management, Bangalore
© Centre for Financial Management, Bangalore
© Centre for Financial Management, Bangalore