API Spec Q1 - Section 5 Product Realization
API Spec Q1 - Section 5 Product Realization
Where contract requirements are changed, ensure that relevant documents are
amended and that relevant personnel are made aware of the changed requirements.
Records of the results of the review, including resulting actions, shall be
maintained.
Work Environment
• lighting
• humidity
• temperature
Preventive Maintenance for
equipment needed to
• produce,
• move, and
• store product/raw materials
The procedure shall identify the techniques, tools and their application for risk
identification, assessment, and mitigation.
Risk assessment associated with product delivery shall include:
a) facility/equipment availability and maintenance; and
b) supplier performance and material availability/supply.
Risk assessment associated with product quality shall include, as applicable:
a) delivery of nonconforming product;
b) availability of competent personnel.
Maintain records of risk assessment and management including actions taken.
07/07/2024 API Spec Q1 - Section 5 Product Realization 7
5.4 Design and Development
Maintain a documented procedure to plan and control the design and dev. of the product.
a) Design and dev. plan and control procedures must include the D&D plans and updates.
b) Identify the D&D stages in the plan and control procedure.
c) Identify the resources, responsibilities, authorities, and their interfaces to ensure effective
communication;
d) Identify the review, verification, and validation activities necessary to complete each D&D
stage; &
e) Identify the requirements for a final review of the design.
07/07/2024 API Spec Q1 - Section 5 Product Realization 8
5.4.1 Design and Development Planning (Continuation)
• When design and development activities are performed at different locations
within the same organization, the procedure shall identify the controls required to
ensure that the designs meet the requirements of 5.4.
• When design and development are outsourced, the organization shall ensure the
supplier meets the requirements of 5.6.1.6.
5.4.2 Design and Development Inputs
Inputs shall be identified and reviewed for adequacy, completeness, and lack of conflict.
Inputs shall include functional and technical requirements, and the following: