3rd Unit Slides
3rd Unit Slides
Risk Concepts
Risk in a project depends on the uniqueness of the project and the experience of the project team.
When activities are routine or have been performed many times before, managers can anticipate the
range of potential outcomes and manipulate the system design and project plan to achieve the desired
outcomes. However, when the work is unique or the team is inexperienced, making it difficult to
anticipate the problems, the potential outcomes are less certain. Even routine projects have risks,
because outcomes may be influenced by the factors that are new and emerging, or beyond anyone’s
control.
The notion of risk involves two concepts:
1. The likelihood that some problematic event will occur.
2. The impact of the event if it does occur.
Hence, risk is a joint function of the two:
Risk = f (likelihood, impact)
A project may be considered risky whenever at least one – either the likelihood or the impact – is large.
For example, a project will be considered risky when the potential impact is human fatality or massive
financial loss even when the likelihood is small.
Although the risk cannot be eliminated altogether, it can be reduced and plans readied in case
things go wrong; this is the purpose of risk management. The process and elements of risk
management are shown in the following figure.
Risk Identification
You can only manage things you are aware of. Thus, risk management begins with identifying the risks and
predicting their consequences. Risks in projects is generally referred to as the risk of failure, which implies
that a project might fall short of schedule, budget, or technical performance goals by a significant margin.
The Sources or Causes of high risk must be studied and well understood before the project can be approved
and funds committed.
Different types of Risks and their Causes
Any factor that can influence the outcome of a project is a risk cause or risk hazard. Risk in projects can be
classified as internal risks and external risks.
Internal risks
Internal risks originate inside the project, and project managers and stake holders usually have some
measure of control over them. Three main categories of the internal risks are as follows:
Market risk is the risk of not fulfilling the market needs or the requirements of particular customers. Sources
of market risk include:
• Failure to adequately define market or customer needs and requirements.
• Failure to identify changing needs and requirements.
• Failure to identify newly introduced products by competitors.
Market risk stems from the developer misreading the market environment, it can be reduced by
working closely with the customer; thoroughly defining needs and requirements early in the
project; closely monitoring trends and developments among markets, and competitors; and
updating requirements as needed throughout the project.
Assumption risk is risk associated with the numerous implicit or explicit assumptions made in
feasibility studies and project plans during project conception and definition. The risk of meeting
cost, time, and performance requirements depends on the accuracy of many assumptions.
Technical risk is the risk of encountering technical problems with the end-item or project activities
(sometimes these risks are listed in special categories – schedule risks being those that would cause
delays, cost risks those that would lead to overruns, and so on). Technical risk is high in projects that
involve new and untried technical applications, but is low in projects that involve familiar activities
done in customary ways.
One approach to expressing technical risk is to rate the project end-item or primary
process as being high, medium, or low according to the following features.
• Maturity: how experienced or knowledgeable the project team is in the project technology. An
end-item or process that takes advantage of existing experience and knowledge is less risky than
one that is innovative, somewhat untried, or cutting edge.
• Complexity: how many steps, elements, or components are in the product or process, and how
tightly interrelated they are. An end item or process with numerous, interrelated steps or
components is riskier than one with few steps and simple interrelationships.
• Quality: how producible, reliable, and testable the end-item or process is. In general, an end-item
or process that has been produced and is reliable and/ or testable is less risky than one that has
yet to be produced or has unknown reliability or testability.
• Concurrency or Dependency: the extent to which multiple activities in the project overlap or are
dependent. Sequential activities with no overlap are less risky than activities with much overlap.
External Risks
These originate from outside the project, and project managers often have limited or no control
over them. External risk causes include:
• Market conditions
• Customer needs and behaviour
• Competitor’s actions
• Supplier relations and business failures
• Government regulations
• Physical environment, i.e. whether conditions
• Interest rates and exchange rates
• Labour availability (strikes and walkouts)
• Decisions by senior management or the customer regarding project priorities, staffing, or budgets
• Material or labour resources (shortages)
• Subcontractor failure
Any of these can affect the success of a project.
Identification Techniques
The Project risks and their sources are identified in many ways. The principle methods are explained
as follows.
Project Analogy
The project analogy method involves scrutinizing records, post-completion summary reports, and
project team member’s recollection from earlier analogous projects to identify risks in new,
upcoming projects. The better the documentation (the more complete, accurate, and well-
catalogued) of past projects and the better people’s memories, the more useful these are as means
for identifying risks.
Checklist
Documentation from prior projects is also used to create checklists – lists of risks and their causes in
projects. A checklist is originally created from the experiences from past projects, and is updated as
new experience is gained from recent projects. Risk checklists can pertain to the project as a whole,
or to specific phases, work packages, or tasks within the project.
The more experience a company or managers gain with projects, the more they learn about
the risks, and the more comprehensive they can make the checklists. As experience grows with
completed projects, the checklist are expanded and updated. When a checklist cannot guarantee
that all significant risk sources or causes in a project will be identified, it does help ensure that the
important known one’s won’t be overlooked.
A disadvantage of risk checklist is that people might only consider the risks listed and not
consider any not in the list.
Work Breakdown Structure (WBS)
Risks can be identified through analysis of the WBS. Every package is scrutinized for potential
technical hurdles or problems with management, customers, suppliers, equipment, or resource
availability. Processes or end-items within each work package are assessed for internal risks in
terms of, for example, complexity, maturity, quality, and concurrency. The work package is also
assessed for external risks – for example, relying on a subcontractor to manage the work package.
Process Flowchart
Project risks can also be identified from process flowcharts. A flow chart illustrates the steps,
procedures and flows between tasks and activities in a process. Examination of a flowchart can
pinpoint potential trouble spots and areas of risks.
Project Networks and Convergence Points
The risks can also be identified through scrutiny of the precedence relationships and concurrent or
sequential scheduling of activities in project networks. For example, risk sometimes increases at
merge points in the project network. At these points, work performed by different teams comes
together and must be integrated; sometimes only do then errors become evident, such as
subsystems produced by two teams not matching up or functioning correctly. The result is that the
project may get delayed.
Cause-and-Effect Diagram and Brainstorming
Risks can be identified from the collective experiences of project team members who participate in
a brainstorming session to share opinions about possible risk sources in the project, and record
them on a cause-and-effect diagram. This can be worked out in two ways: 1. Given an identified,
potential outcome (effect), to identify the potential causes (sources); 2. Given a risk source (cause),
to identify the outcomes that might ensue (effects).
Delphi Technique
The term “Delphi” refers to a group survey technique for combining the opinions of several people
to develop a single judgement. This technique comprises a series of structured questions and
feedback reports. Each respondent is given series of questions (e.g., what are the five most
significant risks in this project?). For which he writes his opinions and reasons. The responses of
everyone surveyed are summarized in one report that is given to everyone. Seeing others opinions,
respondents have the opportunity to modify their own opinions. Because the written responses
are anonymous, no one feels pressurized to conform to their opinions. If people change their
opinions, they must explain the reason why; if they don’t, they must also explain why. The process
continues until the group reaches a collective opinion. Studies have proven this technique to be an
effective way of reaching consensus.
Risk Symptoms and Triggers
As the sources and outcomes of each risk are identified, so are its symptoms, which are visible
indicators or warning signs that the risk is materializing; these serve as a trigger to initiate
counteractions or contingencies to mitigate or combat the risk. For example, for the risk “failure to
meet technical requirements”, a symptom might be “failure of component X during test”; should
that symptom be observed, it would trigger the action “move to design plan B”.
Risk Assessment
Risks are ubiquitous, but it is only the notable or significant ones that require attention. If a risk and
its consequences are significant, ways must be found to avoid or reduce the risk to an acceptable
level. What is considered “acceptable” depends on the risk tolerance of project stakeholders.
Similarly, what is considered significant depends on the risk likelihood, the risk impact, and the risk
consequence.
Risk Likelihood
Risk likelihood is the probability that a risk factor will actually materialize. It can be expressed as a
numerical value between 1.0 (certain to happen) and 0 (impossible), or as a qualitative rating such
as high, medium, or low. The following table shows an example of qualitative ratings and the
equivalent percent values for each. When, for example, someone says the likelihood of this or that
risk is low, the probability of its happening, according to the table, is 20 percent or less.
The association between qualitative ratings and particular numerical values is subjective, and
depends on the experience of the project team and the risk tolerance of stakeholders. For
example, the above table might be for a project with high economic stakes, and therefore a
numerical likelihood greater than 50 percent equates to “high risk”.
When the project has multiple, independent risk sources (as is common), they can be combined
into a single composite likelihood factor, or CLF, which can be computed as a weighted (W) average.
CLF = W1*Likelihood of risk source 1 + W2*Likelihood of risk source 2 + W3*Likelihood of risk
source 3 + -------
Where W1, W2, W3, and so on each have values 0 through 1.0 and together total 1.0.
For example, if there are five risk sources with their likelihood of happening as 0.1, 0.3, 0.5, 0.3, and
0.5 and all of them are rated equally at 0.2, then
CLF = (0.2)0.1 + (0.2)0.3 + (0.2)0.5 + (0.2)0.3+ (0.2)0.5 = 0.34
However, when the risk sources are not independent, then the individual likelihoods cannot be
summed up. In such a situation the sources would be subjectively combined into one source and a
single likelihood value based on judgement is assigned.
Risk Impact
What would happen if a risk source or hazard materialized? The result would be a risk impact. A
poorly marked highway intersection is a risk hazard; it poses the risk impact of a collision and injury
or death. Risk impacts in projects can be specified in terms of time, cost, performance, publicity,
and so on. For example, the impact of insufficient resources might be failure to meet schedule or
user requirements.
Similar to risk likelihood, risk impact can be expressed as a qualitative rating (such as high, medium,
or low) or as a numerical measure between 0 and 1.0 (where 0 is not serious and 1.0 is
catastrophic), based upon a manager’s or expert’s judgement about the impact.
Just as the likelihoods for multiple risks in a project can be combined, so can the impacts from
multiple risk sources. Accordingly, the composite impact factor (CIF) can be computed using
weighted average. However, if the risk impacts are not independent, they should be treated jointly.
Risk Consequence
Earlier, the notion of risk was defined as being a function of risk likelihood and risk impact; the
combined consideration of both is referred to as the risk consequence or risk exposure, which can
be expressed as follows
Risk consequence = Impact × Likelihood
Example: Suppose the likelihood associated with a risk is 0.40. Also, should this risk materialize, it
would set the project back 4 months and increase the cost by an estimated 3,00,000/-. The
expected risk consequences for time and cost are thus:
Risk consequence time (RT) = 4 months × 0.40 = 1.6 months = 6.4 weeks
Risk consequence cost (RC) = 3,00,000 × 0.40 = 1,20,000/-