Chapter 4 and 5
Chapter 4 and 5
TADESSE AYALEW
October 2017
1
Session II
O4 Types of Construction Equipment
Construction Equipment Earthwork Equipments
and Plants
Hauling and Hoisting Equipments
Construction Equipments
Maintenance Management
2
Content
O4 Types of Construction
Construction Equipment Equipment
and Plants Earthwork Equipments
3
4.Construction Equipment
4.1 Introduction
every construction sites, which make the construction jobs easy, safe and
quicker.
Equipment are used for highway projects, irrigation, buildings, power
specific use often affects the required amount of time and effort and thus
the job-site productivity of a project.
It is therefore important for project managers and construction planners
Earth-compacting equipment
Hauling equipment
Hoisting equipment
Conveying equipment
10
4.3.1 EARTH-MOVING EQUIPMENTS
4.3.1.2 Back hoe
A backhoe, also called a rear actor or back
cubic meters.
The basic parts of clam shell bucket are the closing line,
14
hoist line, sheaves, brackets, tagline, shell and hinge.
Comparison between different types of equipment
15
4.3.1 EARTH-MOVING EQUIPMENTS
4.3.1.6 Bulldozer
A bulldozer is a crawler (continuous tracked
19
4.3.1 EARTH-MOVING EQUIPMENTS
4.3.1.10 Trenching Machine
Trenchers, or ditchers as they are
sometimes called, are similar to excavators
in the sense that they penetrate the earth,
breaking soil and rock, and remove it from
the ground. They differ from excavators in
that the soil is removed in one continuous
movement. Trenchers are specifically used
for digging trenches for pipes, but other
machines have been improvised in the past
to serve this purpose.
Trenchers can come in two types: ladder
22
4.3.1 EARTH-MOVING EQUIPMENTS
4.3.1.12 PRODUCTION OF EARTH-MOVING EQUIPMENTS (Cont…)
involved
Equipment Travel Time
Before discussing the productivity of Loader , Dozer and Hauling Equipment
lets see how we can determine the effective grade resistance which affects the
speed of the equipment that in turn has an impact on the Variable time
Continuously Operating
the actual volume per cycle and the cycle time. Thus, to
compute the actual productivity one should be able to make a
good estimate of the actual bucket capacity (which depends on
the soil characteristics) and the cycle time.
The actual productivity of these equipments can be estimated
Equation 4.3
A) Productivity of Shovel Family and Excavators (Cont…)
Table 4.1, bucket capacity rating methods for various types of excavating and
loading equipments
Heaped volume is the maximum
volume that can be placed in the bucket
Cont…
without spillage based on a specified
angle of repose for the material in the
bucket. (based on a 2:1 slope above hauler
Struck capacity is the bucket
bodies)
capacity when the load is struck
Table 2-2.
The most accurate estimate of bucket load is obtained by multiplying
the heaped bucket volume (loose measure) by the bucket fill factor.
A) Productivity of Shovel Family and Excavators (Cont…)
Equation 4.5
Example 4.2
A. Productivity of Dragline
Data are taken from “Liebher’s Technical Hand Book Earth moving
Product line”.
Drag Line Production = Dragline Capacity (m3) x C x f
Where, C = Theoretical Cycles/hr = 120 Cycles/hr
f = Correcting factor
= f1 x f 2 x f 3 x f 4 x f 5 x f 6 x f 7
f2 – Digging factor
Boom Length (m) 12 18 24 30
Digging factor,f2 0.86 0.79 0.72 0.65
f3 – Hoist factor
Boom Length (m) 12 18 24 30
44 Hoist factor,f3 0.95 0.92 0.90 0.87
A. Productivity of Dragline (Cont.…)
f1 - Fill factor
Class Fill factor
1 Sand or fine gravel
a) Dry 1.1 to 1.2
b) Damp 1.0 to 1.1
c) Wet 0.9 to 0.8
2 Clay
a) Sandy clay, dry 0.95 to 1.0
b) Cohesive, dry 0.9 to 0.95
c) Very cohesive, hard 0.88 to 0.9
f5 – Loading factor
Method of dumping Truck Hopper Stock pile
Loading factor, f5 0.96 0.95 1.0
f7 – Operator factor
Operator Experienced Average Beginner
Operator factor, f7 1.0 0.95 0.85
46
A. Productivity of Dragline
Example 3
Data are taken from “Liebher’s Technical Hand Book Earth moving
Product line”.
Clamshell Production (m3/hr)= Clamshell Capacity (m3) x C x f
Where, C = Theoretical Cycles/hr = 120 Cycles/hr
f = Correcting factor
= f1 x f 2 x f 3 x f 4 x f 5 x f 6 x f 7
Correction factors
f1 – Fill factor
Same as those for dragline.
48
B. Productivity of Clamshell
f2 – Digging factor
Clamshell capacity (m3) 1 2 3 4 5
Digging factor, f2 = 0.98 0.97 0.96 0.96 0.95
f4 – Swing factor
Swing Angle (deg) 60 90 120 180
Swing factor, f4= 1.2 1.0 0.98 0.90
f5 – Dump factor
Method of dumping Truck Hopper Stock pile
49Dump factor, f5 = 0.90 0.95 1.0
B. Productivity of Clamshell
f7 – Operator factor
Operator Experienced Average Beginner
Operator factor, f7 = 1.0 0.95 0.85
Example 4
An average operator has to excavate ‘damp sand’ with a clamshell of
2.0 m3. The digging depth is 10m and the swing angle will be 120
degrees. The sand is added into trucks and actual working time is 50
min/hr.
50
B. Productivity of Clamshell
Solution
Clamshell production = Clamshell capacity x C x f.
where C = theoretical cycles/hr
= 2.0 x 120 x f
where, f = f1 x f2 x f3 x f4 x f5 x f6 x f7
= 1.0 x 0.97 x 0.76 x 0.98 x 0.9 x 0.83 x 0.95
= 0.5127
Therefore, Clamshell Production = 2.0x120x0.5127
= 123.0 m3/hr
51
A.2 Productivity of Loaders
68
Example 4.8
69
4.3.3 HAULING EQUIPMENTS
4.3.3.0 General
The equipment used for transportation of
Public Highways
Off Highway Vehicle-Designed to be used
4.3.3.1 Truck
They have high mobility, good speed
71
4.3.3 HAULING EQUIPMENTS
4.3.3.2 Dump Truck
These are the trucks which are fitted with
75
Productivity of Haulers
travel time. It includes spot time (moving the unit position to begin
loading), load time and dump time.
Fixed time can usually be closely estimated for a particular type of
87
88
Example 4-10
Estimate the productivity of a 631 D single engine two – axle tractor
scraper, whose travel time curves are shown in Figure 2 – 12 & 2 ‐ 13
and fixed cycle time shown Table2 ‐ 8, based on the following
information:
Maximum Heaped Volume = 24 Lm3
Maximum Pay Load = 34,020 kg
Material Density = 1,898 kg/Bm3 or 1,571 kg/ Lm3 (Sandy Clay)
Rolling resistance = 50 kg/t
Job efficiency = 50 min/Hr
Operating Conditions = Average
Pusher Type = Single Pusher
Use g = 10 m/s2
Haul Route:
• Section 1 – Level loading area
• Section 2 – Down a 4% grade ( L = 610 m)
• Section 3 – Level Dumping Area
• Section 4 – Up a 4% grade ( L = 610 m)
• Section 5 – Level turn around ( L = 183 m)
91
92
Important tables and charts
96
97
Average Speed Factor Table
Exercise
101
4.3.4 HOISTING EQUIPMENTS
4.3.4.1 Forklifts
102
loads.
4.3.4 HOISTING EQUIPMENTS
4.3.4.2 Hoist
A hoist is a device used for lifting or
1. Building Design
Building Height
Project Duration
2. Capability
Power Supply
Operators Visibility
3. Safety
105 Initial Planning and Engineering
4.3.4 HOISTING EQUIPMENTS
4.3.4.2 Mobile Crane
These cranes are mounted on mobile units
which is either crawler type or wheel type
Truck cranes have high mobility while the
crawler mounted cranes move slowly.
Crawler mounted cranes are capable of moving
on rough terrain.
Adequate for all types of structures (up to 107
m)
Used for shorter projects duration (less than 4
months).
Not considered to be very safe due to lack of
safety devices or limited switches to prevent
overloading.
Can operate in muddy terrain but requires good
ground conditions.
Needs adequate operating clearance
106
4.3.4 HOISTING EQUIPMENTS
4.3.4.3 Overhead or Gantry Crane
large service area,
freedom from floor obstructions
and three-way mobility,
Widely used in erection, foundry, steel
plants, storage yards and different types of
industrial works.
These type of cranes consist of two main
parts i.e., the bridge and the crab.
The bridge consists of two main girders
fixed at their end to end and capable of
moving on gantry rails.
The crab consists of the hoisting gear
mounted on a frame.
The frame itself is mounted on another set
of wheels and capable of travelling across
the main girder.
107
4.3.4 HOISTING EQUIPMENTS
4.3.4.3 Tower Crane
Tower cranes are actually a derrick crane
mounted on a steel tower.
Tower cranes are usually used for industrial
and residential high-rise buildings.
These are commonly used for assembly of
industrial plants with steel structures.
The main parts of tower crane are under
carriage, slewing platform, tower with
operator’s cabin and jibs.
The tower has a truss structure welded from
steel bars and channels.
Preferable for high-rise (over 107 m).
Used for longer project duration.
Considered to be very safe due to the
presence of limit switches.
Can operate where ground conditions are
108 poor.
4.3.5 CONVEYING EQUIPMENTS
4.3.5.0 General
A conveyor system is a common piece of
Blasting
Loading
Transporting
Crushing
Screening
Secondary
Tertiary
A primary crusher receives the stone
Drum Dryer
Weight Hopper
Aggregate from the hot bins is dropped into a weight hopper
situated below the bins and above the pugmill. The weight
hopper is charged one hot bin at a time to control the gradation
of the blended aggregate. The aggregates are weighed
cumulatively in the hopper. After charging, the weight hopper
gates are opened to discharge the aggregate into the pugmill.
4.3.6 CONSTRUCTION PLANTS
4.3.6.2 Asphalt Production Plant
Asphalt‐Handling System
The asphalt cement is stored on site in a heated tank. The asphalt is
pumped to the weight tank, ready for discharge into the pugmill.
After the aggregates are added to the pugmill, the asphalt cement is
pumped through spray bars into the pugmill to coat the aggregates.
Pugmill Mixing
Most plants use a twin shaft pugmill for mixing the batch. To
Asphalt paver
This equipment that is used to pave the
mixed for a suitable period of time until all the ingredients are
adequately blended together
4.3.6 CONSTRUCTION PLANTS
4.3.6.3 Concrete Production Plant and Concreting Equipments
Mixing
Concrete pump
(through pipe)
Chute
Bucket
(Concrete (Large & massive
transported to lower construction. Handled by
level) crane) Wheelbarrow
Transporting concrete with concrete pumps
Transporting concrete with chutes
Transporting concrete with various means
Reading Assignment
142
Session II
O5 Construction Equipments
Maintenance Management
The Management of
Construction Equipment The Buy, Lease, or Rent Decision
143
5.1 CONSTRUCTION EQUIPMENT MAINTENANCE
routine maintenance,
that breaks down during the scheduled shift back to its working condition.
The aim of this type of maintenance is to minimize equipment downtime
after failure.
The alternative to constantly reacting to unpredictable equipment failure is to
149
5.1.3.2 AVAILABILITY AND RELIABILITY (Cont…)
Availability: The equipment manager can use some simple statistical tools to
calculate the availability of the different types of equipment in the fleet for
These tools can also serve as performance control measures for equipment
operated.
equipment time usage. Reliability on the other hand measures the interval of
Thus, a highly reliable piece of equipment could have a low availability due
151
5.1.4 MAINTENANCE PERFORMANCE CONTROL
equipment brokers, and rental companies provide a means for a user with
proper credentials and competence to acquire just about any heavy
construction machine available on a temporary or permanent basis.
There are numerous options to consider when deciding on heavy
154
CONVENTIONAL FINANCING PURCHASE
Over the past several years there has been an increasing trend
158
159
THE BUY, LEASE, OR RENT DECISION (Cont…)
Funding capabilities
162