Lecture Note Transportation Projects Evaluation and Economics Part
Lecture Note Transportation Projects Evaluation and Economics Part
PLANNING
TOPIC:
TRANSPORTATION
PROJECTS EVALUATION AND
ECONOMICS
PART 1
LECTURER: ING. DR. ALBERT FORDE
Contents
Introduction
BasicIssues in Transportation Projects
Evaluation
Elements of Cost
Economic Evaluation Methods
Example
Assignments
INTRODUCTION
The basic concept of transportation evaluation is simple and
straightforward, but the actual process itself can be complex and
involved.
A transportation project is usually proposed because of a
perceived problem or need.
For example, the Integrated and Resilient Urban Mobility Project
was based on the need to mitigate congestion and to improve
mobility along critical corridors in Freetown.
In most instances, there are many ways to solve the problem, and
each solution or alternative will result in a unique outcome in
terms of project cost and results. For instance, two alternatives
could be proposed to address the congestion issue along the
Lumley corridor.
INTRODUCTION
The first proposal could be to install traffic signals at the three
major intersections, and construction pedestrian/foot bridges to
separate vehicular and pedestrian traffic.
These two solutions are quite different in terms of their costs and
effectiveness.
The first solution will be less costly then the second, but it also
will be less effective in reducing delay.
Basic Issues In Transportation Project Evaluation
A transportation improvement can be viewed as a mechanism for
producing a result desired by society at a price.
The question is, will the benefits of the project be worth the cost?
In some instances, the results may be confined to the users of the
system, whereas in other instances, those affected may include
persons in the community who do not use the system.
Prior to beginning an analysis to evaluate a transportation
alternative, the engineer or planner should consider a number of
basic questions and issues.
These will assist in determining the proper approach to be taken,
what data are needed, and what analytical techniques should be
used. These issues are as follows:
Basic Issues In Transportation Project Evaluation
Objectives of Evaluation
Measures of Effectiveness
Who will use the information, and what are their view points?
A transportation project can affect a variety of groups in different
ways.
In some instances, only one or a few groups are involved; in other
cases, many factions have interest.
Examples of groups that could be affected by a transportation
project include the system users, transportation management,
labor, citizens in the community, business, etc.
Each of these groups may have special concerns, since these
viewpoints may differ from group to group, the elements of the
evaluation process itself will be reflective of the viewpoint
expressed.
Selecting and Measuring Evaluation Criteria
What are the relevant criteria, and how should these be measured?
A transportation project is intended to accomplish one or more
goals and objectives, which are made operational as criteria.
How are measures of effectiveness used in the evaluation process itself? One
approach is to convert each measure of effectiveness to a common unit, and
then, for each alternative, compute the summation for all measures.
For example, if the cost of an accident is known and the value of travel time can
be determined, then for a railroad grade crossing problem, it would be possible to
compute a single number that would represent the total cost involved for each
alternative, since construction, maintenance, and operating costs are already
known in dollar terms, and accident and time costs can be computed using
conversion rates.
Measures of Effectiveness
The decision maker also may wish to know if all the alternatives
have been considered and how they compare with the one being
recommended.
The decision maker may want to know the cost to highway users as
the result of travel delays during construction.
ELEMENTS OF COST
Since an evaluation is concerned with costs differences, those costs that are
common to both projects can be excluded.
The first cost for a highway or transit project may include engineering design,
right of way, and construction.
Each transportation project is unique, and the specifics of the design will dictate
what items will be required and at what cost.
Other excluded costs are those that already have been incurred.
These are known as sunk Costs and as such are not relevant to the
decision of what to do in the future since these expenditures have
already been made.
ELEMENTS OF COST
For example, if a highway project that will carry average daily traffic
(ADT) OF 50,000 autos saves only 2 minutes per traveler, and the
value of time for the average motorist is estimated conservatively at
$ 5/hr., the total minimum annual saving is
Present Worth(PW)
Equivalent Uniform Annual Cost(EUAC)
Benefit-Cost Ratio (BCR)
Each method, when correctly used will produce the same results.
The reason for selecting one over the other is preference for how
the results will be presented.
Where
facility and user costs incurred in year n
N = service life of the facility(in years)
i = rate of interest
Net Present Worth
The present worth of a given cash flow that has both receipts and
disbursements is referred to as the Net present worth (NPW).
Therefore, a minimal value of interest rate is the rate that would have
been earned if the money were invested elsewhere.
Net Present Worth
Using the Equation below, the NPW of the project is given as:
Where,
initial construction cost
n = a specific year
maintenance cost in year n
maintenance cost in year n
user cost in year n
salvage value
revenues in year n
service life, years
Net Present Worth
where P is the present value given the future amount F, and N is the
years of service life.
Equivalent Uniform Annual Worth
Where
EUAW = equivalent uniform annual worth
NPW = net present worth
i = interest rate, expressed as a decimal
N= number of years
P = present lump sum
F = future lump sum
A= annual lump sum
The terms in the brackets in Equ 3 is referred to as the capital
recovery factor and represents the amount necessary to repay $1 if
N equal payments are made at interest rate i .
For example, if a loan is made for $ 5000 to be repaid in equal
monthly payments over a five-year period at 1 percent /month, then
Equivalent Uniform Annual Worth
The inverse of the capital recovery factor is the present worth factor
for a uniform series, as stated in Equ 4. Thus, the present value of 60
payments of $111.25 at 1 percent per month, is
NPW = = 111.25(44.96) = 5000
Equivalent Uniform Annual Worth
The ratio of the present worth of net project benefits and net project
costs is called benefit-cost ratio (BCR).
This method is used in situations where it is desired to show the
extent to which an investment in a transportation project will result in
a benefit to the investor.
To do this, it is necessary to make project comparisons to determine
how the added investment compares with the added benefits. The
formula for BCR is
Where
reduction in user and operation costs between higher-cost
Alternative 2 and lower-cost Alternative 1, expressed as PW or EUAW
increase in facility costs, expressed as PW or EUAW
BENEFIT– COST RATIO
The alternative selected is the one with the highest initial cost
and a BCR of 1 or more with respect to lower cost alternatives
and a BCR less than 1 when compared with all higher cost
projects.
EXAMPLE
Since BCR is less than 1, we would not select Alternative III. We reach the
same conclusion as previously, which is to select Alternative II.
Assignment 1(Due 18th June,2024)
Question 3
Three transportation projects have been proposed to increase the
safety in and around a residential neighborhood. Each project consists
of upgrading existing street signing to highly retro reflective sheeting
to increase visibility. The following table shows the initial construction
costs, annual operating costs, useful life of the sheeting, and the
salvage values for each alternative. Assume that the discount rate is
8%. Calculate the present worth for each alternative and determine the
preferred project based on the economic data.
Assignment
Question 4
Two designs have been proposed for a short span bridge in a rural area,
as shown in the following table. The first proposal is to construct the
bridge in two phases (Phase I now and Phase II in 25 years). The
second alternative is to construct it in one phase. Assuming that the
annual interest rate is 6%, determine which alternative is preferred
using present worth analysis.
Annual
Construction Service
Alternative Maintenance
Costs($) Period(Years)
Cost($)
I(Phase I) 14,200,000 75,000 1 — 50
I(Phase II) 12,600,000 25,000 26 — 50
II 22,400,000 100,000 1 — 50