Reliability Analysis
FMEA
Development program for Preventive Maintenance Engineers
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015
Objectives
• Understand the importance and concept of Reliability Analysis and how
to apply it in preventive maintenance
• To be able to replicate the FMEA process in the specific plant conditions
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 2
Have you heard this expression?
“Why is there always enough time to do it over, but
never enough time to do it right the first time?”
Restated in a maintenance context,
“Why is there always enough time (and money) to
fix a broken machine but never enough time (or
money) to prevent it from failing?”
Jim Fitch (Noria Corporation).
WS06 Preventive Maintenance Strategy, CM, 2015-05-21
Driver: Preventive Maintenance Strategy
Coupling failure of the bucket elevator
322BE1
Lack of lubrication in
hydraulic coupling
Geared
couplings
damaged
Proactive action: Complete hydraulic
Condition
Preventive maintenance coupling damaged
routine to re-grease. Shaft of
Aprox. Cost of proactive gearbox
task 500 USD damaged
Motor
Time damaged
++
+ Total cost: Functional
- failure
-- 45 kUSD
Cost to repair
INTERNAL USE ONLY © 2015 LafargeHolcim 4
Bearing failure in a bucket elevator
Possible Bearing
contamination clearance above Excessive Approx. total cost of the failures:
wear
of bearing normal 50 kUSD
Unusual noise
PROACTIVE Bearing inspection:
TASK internal clearance and
lubricant condition New bearing inspection Excessive heat
(Approx. cost of
(Notification: 81246630 564-BE1
the PROACTIVE
Mech Insp 6 Month
TASK to avoid
03.30.2011
the problem:
Condition
(There has been a notification in
1 kUSD)
the system for several months to
replace these bearings.)
81345529 564-BE1 INSP D.E. head shaft bearing. 09/27/2011
(During inspection I found the drive end head shaft brg. hot and
making an unusual noise. Temp. was at 110deg. C and brg.
making a grinding noise on 9/27/11.)
Time
+ WO 10640994 – 09/30/2011 564-BE1
- INSP D.E. head shaft bearing
(Replaced both bearings and drive
WO 10656060 04/03/2012
564-BE1 OEE Replace
-- Cost to repair shaft complete- $24,883.46) gearbox output shaft
(Installed new gear box. Job
complete- $23,425.98)
INTERNAL USE ONLY © 2015 LafargeHolcim 5
Agenda
Reliability Process - FMEA
FMEA and measures
Decision process
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 6
Failure Mode Effect Analysis (FMEA)
• … is a review technique that focuses on defining possible failure modes
and their effects on the system
• … provides basis to determine the preventive maintenance actions,
contingency plans to be implemented and spare parts requirements
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 7
Reliability analysis process
1. Risk Analysis 2. FMEA 3. Measures
• Definition of risk matrix • Perform FMEA for all / most • Measures to reduce
for each process area “A” critical equipment probability / severity
• Definition of operation loss • Allocate failure causes in risk ✓ Preventive Maintenance
and impact on revenue matrix Routines
cost related to probability • Measures required if ✓ Contingency plan
of occurrence located outside predefined ✓ Hold Critical spare parts
protection level
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 8
Template
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 9
Equipment and equipment function
The equipment name
must include the
proper ACS code
Equipment: _______________________
Equipment Function: _______________________
_______________________
Include all the functions of the
equipment such as e.g.
- Primary
- Secondary
- Protection Devices
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 10
Sub-systems
Start
#‘s
Divide equipment into
sub-systems to
increase focus of
analysis
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 11
Failure modes
Do not list all
Sequential #‘s possibilities
reset for each regardless of it
sub-system likelihood
• When brainstorming failure modes try to stick to...
• Failure modes which have occurred before
• Failure modes which are already the subject of proactive maintenance routines
• Failure modes which have not yet occurred, but which are considered to be real
possibilities
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 12
Causes
List possible
Letter in alphabetical causes for each
order, reset it for failure mode
each failure mode
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 13
Effects
• Failure effects describe what happens for occurance of each
single failure mode
• The effect of the failure should be considered in the worst case
scenario and that there are no current efforts being performed to
prevent it
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 14
Severity and probability
Probability
Severity
• According to the failure mode and the effect, severity and
probability are determined
• Assess each failure mode and its effect according to the risk
profile for the area the equipment is located
• Correlation to aspect impacted (e.g. production loss, safety, etc.)
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 15
Assumptions and explanations
• Finally, document any and all assumptions or explanations for the
evaluation
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 16
Completed sheet
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 17
Feed back to risk profile
• Example: Failure modes of belt 332-FB6
• Drive pulley:
• 1: Bearing failure
• 2: Broken shaft
• Drive:
• 3: Gear box bearing failure
• 4: Gear box gear wheel failure
• 5: Gear box shaft failure
• 6: Electrical motor bearing failure
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 18
Example: Belt 332-FB6, NO Actions considered
6
1
2 3 4 5
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 19
Agenda
Reliability Process - FMEA
FMEA and measures
Decision process
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 20
FMEA - Measures to be taken
• As part of an FMEA the following type measures can be defined
• Preventive maintenance
• Contingency plan
• Hold critical spare part
Probability
A
B
C
D
E
F
IV III II I Severity
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 21
Impact of decisions taken
• Holding spare parts can reduce severity by eliminating lead time of
spare parts
• Having a contingency plan can reduce severity – being prepared
Probability
A
B
C
D
E
F
IV III II I Severity
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 22
Impact of decisions taken
• Proper alignment, clean working environment, proper lubrication etc.
can reduce probability by guaranteeing optimal working conditions
Probability
A
B
C
D
E
F
IV III II I Severity
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 23
Impact of decisions taken
Condition monitoring reduces both,
probability and severity
Probability
C
D
E
F
IV III II I Severity
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 24
Agenda
Reliability Process - FMEA
FMEA and measures
Decision process
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 25
Decision process
QUESTION
Is the detection of the potential failure
during operation both technically TASK
feasible and economically justified? CONDITION MONITORING
1
• Vibration Analysis A
NO • Temperature measurement
YES
Is the detection of the potential failure • Human sense
during stand -still both technically
feasible and economically justified ?
2 INSPECTION Would a spare part on
• Specific measurement stock be economically
NO • NDT (Non destructive Tests) justified ?
YES
Is an age -related overhaul or exchange
task both technically feasible and
economically justified ?
3 Decision if corrective
NO SCHEDULED OVERHAUL OR EXCHANGE maintenance task is of
YES high or low cost.
Is a task to detect a hidden failure both
technically feasible and economically
justified ?
4 FAILURE FINDING TASK
• Actuate Safety Circuit
NO Check in the risk
YES • Functional Test
Are the failure consequences still in profile for
5 acceptance
an unacceptable zone? RE-DESIGN COMPULSORY
YES
6 NO PREVENTATIVE MAINTENANCE
Re-design if both technically feasible
NO and economically justified.
A Is a servicing task (lubrication, cleaning,
tightening) economically justified ?
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 26
Capture action and decisions in the worksheet
Corresponds to
New New
coding system in
severity probability
FMEA Sheet.
(e.g. 1.1.A)
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 27
Step 8: Feed back to risk profile
Example: Failure Modes of Belt 332-FB6
• Drive pulley:
• 1: Bearing failure
• 2: Broken shaft
• Drive:
• 3: Gear box bearing failure
• 4: Gear box gear wheel failure
• 5: Gear box shaft failure
• 6: Electrical motor bearing failure
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 28
Example: Belt 332-FB6, NO Actions considered
6
1
2 3 4 5
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 29
Example: Failure modes of Belt 332-FB6 - Actions
• Drive pulley:
• 1: Bearing failure ➔
Action: buy bearing
• 2: Broken shaft ➔
Action: weld temporary
• Drive:
• 3: Gear box bearing failure ➔ Action: buy bearing
• 4: Gear box gear wheel failure ➔ Action: vibration analysis
• 5: Gear box shaft failure ➔ Action: weld temporary
• 6: Electrical motor bearing failure ➔ Action: hold bearing
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 30
Example: Belt 332-FB6, actions considered
6 6
1 1
2 3 5 2 3 4 4 5
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 31
Risk matrix
Reduce severity
Probability Eliminate repetition and/or probability
D Look for the
root cause
E
F
Severity
No action
IV III II I
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 32
Where to start?
This can entail a massive
amount of work if every asset
in the plant is examined,
therefore we need to examine
only
Critical assets
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 33
Questions / Comments …
P05 Reliability Analysis FOR INTERNAL USE ONLY © LafargeHolcim 2015 34