Week 6 Lecture Slides
Week 6 Lecture Slides
BUSINESS
SCHOOL
Slide 4
Traditional costing systems
Trace
Direct materials
Trace
Direct Labour
Individual
products or
Overhead costs services
Overhead Allocate
Indirect materials (cost objects)
Indirect labour cost pool
Production facility costs Plant-wide or (using
Etc. departmental volume
based cost
driver)
Slide 7
Has your costing system experienced any of the following symptoms?
Slide 8
Activity-based costing
• A method that can be used to measure both the cost of
cost objects and the performance of activities
• Activity:
– A unit of work performed within the organisation
Slide 9
Traditional approach (from week 5) …
Slide 10
ABC approach
Resource
Drivers
Activity
Drivers
Slide 11
Activity Based Costing (ABC)
Direct materials
Trace
Direct Labour
Trace or allocate Activity cost
Allocate using
using resource pools:
Overhead costs: Testing materials cost
activity cost
drivers pool drivers
Transport equipment Allocated using
costs number of materials Individual products
tested
or services or other
Supervisors’ salaries Inspection cost pool
cost objects
Allocated using
number of units
inspected
Inspectors’ salaries
Slide 12
Be careful…
• Do not confuse overhead costs with
activity cost pools (see previous slide)
Slide 13
Activity-based vs. traditional product costs
• Traditional product costing is based on the use of
volume-based cost drivers
– Not all aspects of manufacturing overhead vary with
production volume, for example fixed costs
– Activity-based costing recognises both volume-based
and non-volume-based cost drivers
• In ABC, the quantity of activity drivers consumed by a
product often depends on whether the activity is
performed for each unit, batch or product line.
Slide 14
Activity-based vs. traditional product costs
• Traditional costing treats all costs as unit level
– Ignores product level and facility level costs
– Also ignores batch size
• Units produced in large batches consume a
relatively low cost per unit of batch costs
– For example, imagine the setup cost per batch of units
is $200 and in August 100 units were produced in
each batch ….. Therefore, the setup costs per unit is
$2
– Scenario 1: In September, the units produced per
batch increased to 300 due to higher consumer
demand. However, despite the increase in batch size,
it still costs $200 to setup the batch leading to a setup
cost of $0.67 per unit
– Scenario 2: In September, the setup cost per batch of
units increased to $250 due to the introduction of more
sophisticated machinery. However, despite the
increased cost, 100 units per batch are still made
leading to a setup cost of $2.50 per unit.
Slide 15
Activity-based vs. traditional product costs
• Traditional costing systems tend to overcost high-
volume, relatively simple products and undercost low-
volume, complex products
– High-volume, simple products may use less
activities
– Low-volume, complex products may use more
activities
– Traditional costing does not recognise these
differences
Slide 16
Activity-based costing in
Cold Stone Creamery
1,500 shops across the U.S offering the “ultimate ice cream
experience”
Offers ice-cream with “mix-in” ingredients – 15 flavours, 30
ingredients and 3 sizes
Different ice cream orders had large variations in cost in terms of
ingredients and time
Slide 19
The ABC framework
Slide 20
Activity-based costing terminology
• Resource driver STEP ONE
– A cost driver used to estimate the cost of resources (i.e.
overhead costs) consumed by an activity
• Activity driver STEP TWO
– A cost driver used to estimate the cost of an activity
consumed by the cost object
• Bill of activities STEP THREE
– Identifies the activities, the activity cost per unit of activity
driver, the quantity of activity drivers consumed, and
therefore, the cost of the activities consumed by the product
Slide 21
The ABM framework
Slide 22
Activity-based management terminology
• Root-cause cost drivers
– The underlying factors that cause activities to
be performed and their costs to be incurred
– Used to monitor and control what is happening
in a business
– Provide information about root causes of
activities, their value to customers, and
appropriate performance measures to use.
– Can potentially be different to the activity
driver
Slide 23
Research Cost - $1.5 million –
Remember Week Pharmaceutical Company
1??
The research department sends out
blood samples for examination to
an external pathology lab.
What is the cost driver of this
activity?
Slide 25
Activity-based hierarchy of costs and activities
• Unit level activities
– Performed for each unit of product
Doesn’t matter if there
• Batch level activities are 100 or 150 units in
the batch – same cost!
Slide 26
The costing view: Bill of activities
Slide 27
Lecture illustration
• Yummy's Bakery makes a number of different cakes and pastries. Two of its
best-selling products are the Lamington and the Vanilla Slice.
• It has a budgeted overhead amount of $425,000 for the coming year. It
anticipates 2,000 direct labour hours.
• 400 Lamingtons can be produced an hour. 500 Vanilla Slice can be produced an
hour.
• The prime cost for a Lamington is $0.30 and $0.50 for a Vanilla Slice.
• On the next slide is a list of the main activities performed at Yummy and their
annual costs. These costs represent an allocation of all the bakery’s overhead
costs. They were allocated to activities using resource drivers.
• Five potential activity cost drivers and the annual quantity of each activity driver
are also listed.
Slide 28
Lecture illustration contd….
The data for the Lamington and the Vanilla Slice is as follows:
Slide 30
Lecture illustration contd…
Required:
1. Using traditional costing, with direct labour hours as a cost driver, calculate the
product cost for the Lamington and Vanilla Slice.
3. Calculate cost per unit of activity driver for the activities listed.
4. Use the information in parts 2 and 3 to determine a cost per unit for the
Lamington and Vanilla Slice.
After all this: Reflect on the difference of calculating product costs using
this method and what we did last week!
Slide 31
Lecture illustration solution
Question One
Budgeted overhead $425,000
Lamington Vanilla
Slice
400 produced/ hour = 0.0025 DLHrs 500 produced/ hour = 0.002 DLHrs
per unit
per unit
Applied overhead $0.53 Applied overhead $0.43
Slide 32
Lecture illustration solution
Question Two
Slide 33
Lecture illustration solution
Question Three
Activity Activity Cost Activity Driver
Quantity Cost/unit of
activity driver
Receivables $15,000 No. invoices
5000 $
Payables $25,000 No. purchase orders 2500
$
Program Production $28,000 No. batches
1000 $
Load Mixer $14,050 No. batches
1000 $
Operate Mixer $45,900 Kg processed
200000 $
Clean Mixer $6,900 No. batches
1000 $
Fill Trays $16,000 No. cakes produced Slide 34
Question Four
Activity Activity Driver Cost/unit of Lamington
quantity Annual Cost
activity driver
Compare costs
Lamington
Vanilla Slice Traditional $0.83
$0.93
Activity Based $0.82 $1.38
Slide 37
When to use ABC?
• When overhead costs are a significant proportion of total
cost, and a large part of overhead is not directly related to
production volume
Slide 38
When to use ABC?
Slide 39
When to use ABC – four key questions
Yes
3. Does the organisation have a high If most overhead costs are unit based,
then overhead drivers will probably be
proportion of non-unit level costs? No volume-based drivers – traditional costing
systems are usually able to capture these
reasonably effectively
Yes
Slide 40
Different forms of ABC
• Simple approach: allocates manufacturing overhead costs
to products
Slide 41
Slide 42
Which costs should be included in an ABC system?
• Depends on the purpose of the system, which depends on
the needs of management and on the problems that need
to be addressed.
Slide 43
Variations in forms of ABC
• Actual (past) or budgeted costs are analysed
Slide 44
Impediments to introducing ABC
• The benefits of ABC can be significant
but the take-up rate has been relatively
slow. Why?
– Lack of awareness of ABC
– Uncertainty about the potential benefits
of ABC
– Concerns about the extensive resources
required to implement ABC
– Resistance to change from managers
and employees
Slide 45
Impediments to introducing ABC
• Behavioural issues in implementing activity-based
costing
– ABC may require substantial changes to:
o The way businesses are managed
o The type of data that is collected
o Collection and analysis procedures
– Implementation requires the time and effort of many
people across the organisation (not just accountants!)
– These changes can be perceived as threatening and
therefore may be resisted
Slide 46
Overcoming impediments of ABC
• ABC must be accompanied by a change management plan that takes into
account the extent of change needed and the personalities involved
Slide 47
Limitations of activity-based costing
• Facility level costs
– When a high level of facility level costs is allocated to
products, an arbitrary element enters the product cost
• These costs bear no obvious relationship to products
• In lecture illustration: rent was split equally between products.
Could we do better? Allocate based on square footage used to
make products? Is that feasible/necessary?
• Use of average costs in decision making
– Batch, product level and facility level costs that have been
divided by the number of units produced (as in lecture
illustration) can lead to product costs that are of limited use for
decision making if there is any element of customisation
Slide 48
Limitations of activity-based costing
• Complexity
– The cost of updating an ABC system can be very high
although it may be needed to avoid producing outdated,
irrelevant information
– The level of complexity increases when the system is
used for both activity management and product costing
– Activity-based management requires extensive and
detailed analysis of costs and activities
Slide 49
Limitations of activity-based costing
• ABC can be difficult to implement in service firms
– High levels of facility costs, so potential for many
arbitrary allocations
– Individual activities are difficult to identify because they
are non-repetitive
– A non-repetitive production environment makes it difficult
to identify service outputs (so what is the cost object?)
Slide 50
Acknowledgement
Some of the slides contained in this presentation
were adapted from:
Slide 51