Control & Measuring Instruments
Control & Measuring Instruments
a. Resistance thermometer
b. Thermocouple
c. Thermistor.
Resistance thermometer
• It is a precision resistor with a known
temperature coefficient of resistance.
The majority are PT -100 with 100 ohm at
0’C increasing by 0.385 ohm/’C up to 100.C.
•
A torque of value T is applied to a shaft of fixed length L and radius
r. An angle of twist θ is generated and is dependent of the modulus
of torsional rigidity G and given by
• T/r = Gθ/L
• The modulus of rigidity, the radius and the length of the shaft are all
fixed thus the torque on the shaft is proportional to the angle of
twist
Typical system
Two AC generators are mounted so that
they are driven by the main shaft and
area at set distance apart L. A sinusoidal
waveform is produced. One of the
generators is adjusted so that at
minimum torque the generated
waveforms are 180' out of phase. The
outputs from the two generators are then
added and the resultant voltage is used
as the measurement of torque
As the torque is applied to the shaft so
the twist causes the waveforms to shift in
phase. When the two waveforms are now
added an output ac current is produced
which may be amplified and rectified to
give an output voltage proportional to the
torque applied to the shaft.
Torductor torque transducer
Torque
• Differential measurement
• Indirect via current
Force
• Strain gauge + spring
principle
When a force is
applied, the
conductors become
longer and more tiny,
the resistance
increases, R -> R+ΔR
Bridge
Strain gauges in the different resistor positions
R+ΔR R-ΔR
V V
R-ΔR R+ΔR
Speed : Tacho
• Tachometer
generators
– A DC machine
– No load – long lifetime
(> 20000 h)
– Linearity error < 0.5%
– Ripple < 5%
Speed; Magnetic pick up
• speed pick-up
Magnetic pickups / proximity switches
CONTROL ACTIONS
• Two step control action
This can be defined as 'the action of a controller whose output
changes from one state to another due to a variation in its
input' One example of this control is that of a float operated
filling v/v say for a cistern. In normal condition the output of the
float is nil and no water passes through the valve, should the
water level drop the float detects this and operates the valve to
change to its second state which is open and water flows.
When the level re-establishes then the float controls the valve
to return to its primary state which is closed. In this way the
float is controlling the water level by changing the valve
between two different states. A more realistic system is shown
below.
The actions of controllers having
variable output
Proportional control action
• This; where the change in output signal from a controller is proportional to the change in input
signal
• The control can be summed up in the following;
• Output = Constant x Deviation
• Output - this is the output from the controller and goes to the control element i.e. the piece of
equipment that actually alters the process.
Constant- This is the 'Gain' of the controller, as the output varies with the deviation, the amount
it varies can be altered.
• Say if the deviation changes by one unit the output changes by one unit, hence the gain is one.
If the output varied by two for the same one change in deviation then the gain would be two.
Similarly if the change in output was one half a unit for a one unit change in input then the gain
would be half. Another way used to describe Gain is 'Proportional band', here a gain of one is
described as a proportional band (Pb)of 100%. For a gain of two the Pb is 50%, and for a gain of
a half the Pb is 200%, hence it can be seen that the magnitude of the Pb is opposite to the gain.
Deviation- This is the difference between the set point of the controller and the measured value.
If the set point was one unit and the measured value was two units the deviation would be one
unit.
• Deviation = Set point - Measured value
• The important think to remember is that the narrower the Proportional band the higher the gain
and hence the higher the output varies for a change in deviation, this has the effect of making
the controller control the process quicker by operating the controlling element more for smaller
variations measured value. This has the negative effect as will be seen of making the system
unstable
OFFSET
• For a proportional controller to work there must be a deviation, if the deviation is
zero then the controller output to the controlling element is zero. For the example
of the tank and filling v/v obviously this is not possible, with the water constantly
flowing out of the manual outlet v/v then the filling valve ( or controlling element )
must always be some degree open. If the level is at the level of the set point
then the output is nil, the filling v/v is shut and the level drops, deviation occurs
and the filling v/v opens. with this it can be seen that the system is not stable;
what would happen in reality is the level would change (say the level was low
and was now rising) until it reached a point close to the set point where the
deviation multiplied by the gain would give an output signal to the filling v/v such
that the flow of water in to the tank equaled the flow of water out of the tank.
• This deviation is called 'offset'
• Therefore a proportional only controller when in equilibrium must have offset
The amount of offset will be determined by the Gain, for the tank system if the
gain is high the deviation can be small for a larger output
• The offset will increase for increased loads on the system i.e. if the outlet v/v on
the example where to be opened further obviously the filling v/v would have to
be opened further, and hence the deviation ( offset ) to give the required output
would have to be greater.
• For the system above all the control would be positive as the filling v/v would
only be open if the level was low and hence the offset would always be positive,
when the level rose above the set point, say caused by Lags leading to
Overshoots or the filling v/v leaking slightly the deviation would be negative and
the output zero.
Proportional action and instability
(Hunting)
• As the gain increases so the output increases for smaller
and smaller changes in deviation, eventually the response
starts to look similar to that of a two step controller with
the control valve flying from full open to full shut with the
slightest deviation from the set point. This would be o.k. if
the system was devoid of all Lags, with lags however,
particularly between the controller and controlling
element, there is a tendency for 'over shoot'.
• This can occur with reduced gain when the process lags
are increased, for systems with a very large lags even
small changes in gain can seriously effect the stability of a
system and especially its ability to resist step ( or rapid )
load changes.
• For smaller values of gain the system can be set up to
have minimum of hunt and be self stabilizing .
Split range control
(negative and positive offset)
• A system could be designed to control both the outlet valves and inlet valves
(this is what is seen on the feed water system level control with the spill and
filling being controlled from the one controller) ; here the controller would be
set up so that when the level is at the set point its output is mid range ( say
for a controller operating in the 3 to 15 psi range this would be 9 psi)
• The control valves would be set up so that one, say the filling v/v would go
from close at 9.5 psi to open at 15 psi, and the spill v/v would go from close
at 8.5 psi to open at 3 psi. The 1 psi in the middle is called the 'Deadband'
and is there to ensure both v/vs are not open at the same time.( The v/v
acting to open with increasing input signal is called 'Direct Acting' and the
v/v closing with increasing pressure is called 'Reverse Acting')
Integral action (and the removal of offset )
• Integral action is defined as the action of a controller
whose output signal changes at a rate proportional to the
input (deviation from the set point) signal.
• What this means is that if a controller has a constant
deviation then the integral action controller will increase
its output continuously until it reaches maximum (often
referred to as 'Saturation')
If the deviation is zero the integral action controller is
zero
If the deviation is small the rate the controller output
increases by is small
If the deviation is great then the integral action controller
will rapidly increase its output.
• Integral action is included in proportional controllers
to remove the inherent offset of the proportional
action, the offset is the deviation the integral action
requires to alter the output
Integral action time
• The amount of integral action, or how fast the integral action increases or
decreases the output for one unit of deviation is expressed as the time
taken to repeat the proportional action after a stepped change in input.
• Rate of increase of output = Deviation x Integral action time
• What this means is say the load changes in the simple filling system
example by the manual v/v being opened and the level suddenly
dropping by a foot, the proportional action will see this load change and
give a stepped change in output i.e. if the foot drop in water level equals
a change in input signal to the controller of one unit away from the set
point, the controller will give a stepped change in output equating to the
gain (which is say two ) times the deviation ( one unit) which equals a
change in output of two units.
• Whilst all this has been going on the integral part of the controller has
seen the deviation and has decided to increase the rate of output by an
amount equal to the deviation multiplied by the integral action time. The
time taken for the output to increase by a further two units ( remembering
that this was how much the proportional action changed the output) is
the integral action time and is measured in seconds.
• The shorter the integral action time ( less seconds ) the more rapidly the
integral part of the controller will increase the output; The longer the
integral action time the slower the integral action will increase the output.
Integral action
• Output = Derivative
action x rate of change of
input
• Derivative action
[coefficient]- This is
described as the time the
proportional action takes
to repeat the derivative
action after a ramped ( or
constant rate of change)
input. The units are
seconds
Boiler Water level Control
A regulated supply of water must exist for a boiler
generating steam. With the system in balance without
leaks the flow of water to the boiler will be equal to the
flow of steam. When there is a change in steam demand
then the flow of water will have to be changed.
One Element
Integral (Time)
Integral action is defined as the action of a controller whose
output signal changes at a rate proportional to the input
(deviation from the set point) signal.
Derivative (Rate of change)
The definition of this is the action of a controller whose
output is proportional to the rate of change of input
Valve Positioners
Valve positioners are used on controlling valves where accurate and rapid
control is required without error or hysterises.
•Precise positioning,
•can cope with large variations in forces acting on plug
•Rapid positioning
•Removes friction effects of gland
•Removes effects of large distances between vale and postioner
•Eliminates hysterises
A valve positioner consists of a very high
gain amplifier- this may be pneumatic,
electro pneumatic etc, and a feed back
link which detects the actual position of
the valve. movement is for the valve to
close. The input pressure from the
controller to the bellows falls. The flapper
moves away from the nozzle and the
pressure after the orifice falls. The
pressure to the diaphragm falls and the
valve begins to close. The feed back arm
moves up rotating the cam clockwise.
This raises the beam increasing back
pressure in the nozzle until equilibrium is
again achieved. The change over cock
allows the signal from the controller to be
placed directly on the diaphragm