CONSULTANCY
PROJECT
OWNER /
CLIENT
OWNER’S ENGR. EPC CONTRACTOR
EPC ENGR.
NEXT
DESIGN
INPUT
INSTRUMENTATION
DESIGN ACTIVITIES
MILESTONE ACTIVITIES
REFERENCE DOCUMENTS
PLANNING & SCHEDULING
BASIC ENGINEERING
CONTRACT COMMENTS/
REVIEW REPORT CLARIFICATION ON
DESIGN INPUT
NEXT
ENGINEERING SCHEDULE.
MILESTONE
HOME
ACTIVITIES
BASIC DESIGN
BASIC ENGINERING
INSTRUMENT
INSTRUMENT COMMENTS ON INDEX(PREL)
DESIGN BASIS P&ID / UFD
DESIGN
OUTPUT
HOME
DETAILED DESIGN & PROCUREMENT
PREPARE PREPARE MR
INSTRUMENT FOR CONTROL
INDEX SYSTEM TBA/PORN FOR VENDOR DWG.
INSTRUMENTS REVIEW
COMMENTS ON PIPING
DRAWING
FINAL MTO
INSTRUMENT
LOCATION
LAYOUT
PREV NEXT
MILESTONE
INSTRUMENT INDEX(FINAL)
LOGIC DIAGRAM
CONTROL ROOM LAYOUT
OVERALL MTO
HOME
ACTIVITIES
Instrumentation Engineering Work Process
Reference Documents
PREV
HOME
P&I DIAGRAMS
AND
INSTRUMENTATION DELIVERABLES
12-08-04 10
P & I DIAGRAM
Expanded as Piping and Instrumentation Diagram or
Process and Instrumentation
Diagram
Is a schematic illustration of functional relation ship of
Process, Piping & Instrumentation of any plant
Shows all piping including the physical sequence of branches,
reducers, valves
Shows all Instruments- whether Local/ Remote
Different symbols are used for identifying the location of
Instruments
12-08-04 11
P & I DIAGRAM
Shows all the Instruments with Tag numbers
Shows Process piping, Sizing & Identification
Shows miscellaneous items like:
Vents
Drains
Special fittings
Sampling lines
Shows Flow directions
Shows
12-08-04 Control Inputs/ outputs / Interlocks 12
P & I DIA GRAM
12-08-04 13
INSTRUMENTATION DELIVERABLES
Instrumentation Design Basis
Instrument Index
Instrument Specification
Instrument Datasheet
Distributed Control System (DCS) Specification
Programmable Logic Controller (PLC) Specification
Instrument Junction Box Wiring diagram
Instrument Cable Schedule
Instrument Installation Diagrams
12-08-04 14
INSTRUMENTATION DELIVERABLES
12-08-04 15
INSTRUMENTATION DESIGN BASIS
Units of Measurement
Air supply at Battery limit
Power supply for various systems like:
DCS / PLC
Emergency Shut Down
Analyzers / Chromatographs
Control panels
Field Instruments
Package Instrumentation
12-08-04 16
INSTRUMENTATION DESIGN BASIS
Flow Measurement
12-08-04 17
INSTRUMENTATION DESIGN BASIS
Level Measurement
12-08-04 18
INSTRUMENTATION DESIGN BASIS
Temperature Measurement
Local Gauges: Bimetallic or Mercury in steel type
For remote measurement: Thermocouple / RTD
Generally up to 300 deg C RTD is
used for temperature > 300 deg C Thermocouple is used.
Temperature Transmitter: Required /Not i.e
Thermocouple or RTD signal is going to be converted to mA signal
or not.
Mounting of Temperature Transmitter: Integral/Remote
i.e. if Temperature transmitter is there then whether it is head
mounted or mounted away from the head.
12-08-04 19
INSTRUMENTATION DESIGN BASIS
Control Valve
Type: Globe/ Ball/ Butterfly
Trim char.:Equal % / Linear/ On-Off
End Connection: Flanged / Welded
Accessories: Position Transmitter
Air filter Regulator
Solenoid Valve
I/P Converter or E/P Positioner
Limit Switches etc.
12-08-04 20
INSTRUMENTATION DESIGN BASIS
Safety Valve
Type: Conventional/ Pilot operated/ Balanced bellows
Generally Conventional type is used.
For clean service where Operating
pressure >90% of Set point- Pilot operated valve
is used.
For corrosive service When built up Back
pressure > 10% of Set point- Balanced bellows
is used.
12-08-04 21
INSTRUMENTATION DESIGN BASIS
Process Switch
Flow: Independent receiver switch (through transmitter)
Level:Directly actuated or through transmitter
Pressure: Directly actuated or through transmitter
Temperature: Independent receiver switch
Special Instruments: Independent receiver switch
12-08-04 22
INSTRUMENTATION DESIGN BASIS
12-08-04 23
INSTRUMENTATION DESIGN BASIS
Control Philosophy
Mode of plant operation: Centralised / Local – Generally
the main plant operation is centralized and package plant operations
can be local, for example, Instrument Air compressor.
No. of Control room: will be decided based on the size of
the plant
Plant Controls: whether through DCS or standalone PLC
Final Control Element: Pneumatic or Electric or Hydraulic
Field Transmitter: Field bus compatible / Smart /
12-08-04 24
INSTRUMENT INDEX
12-08-04 25
INSTRUMENT INDEX
Make
Model Number
Requisition Number
Revision number
Etc.
12-08-04 26
INSTRUMENT SPECIFICATION/ DATA SHEET
Level Gauge
Level Transmitter
Level switches
Analyzers
Control Valves
Safety valves
For preparation of Instrument Datasheets, Process Data sheet for
each instrument tag will be furnished by the Process.
12-08-04 28
INSTRUMENT SIZING CALCULATIONS
Control Valve
Flow Elements
Safety valves
Rupture Disc
Thermo-well Depth
Restriction Orifice
12-08-04 29
DCS SPECIFICATION / PLC SPECIFICATION
Control System Architecture shows where all redundancy is
required
Generally Processor/ Power supply / Communication
redundancy is specified
I /O redundancy is provided only for critical I/O’s
Requirement of number of operator consoles is specified
Third party integration – Integrating the PLC’s given by the
Package vendors
MIS connectivity – to the Top Management
12-08-04 etc. to be specified. 30
INSTRUMENT JUNCTION BOX SCHEDULE
12-08-04 31
INSTRUMENT CABLE SCHEDULE
12-08-04 32
INSTRUMENT INSTALLATION DRAWING
12-08-04 34
OTHER DESIGN DOCUMENTS
Reference Drawings required: P & ID’s/Instrument Index/
Design Basis/ Plot plan / Piping GAD’s
These are prepared after the receipt of Piping GAD’s
Location layout shows location of all Transmitter/
Switches /Gauges etc..
Instrument cable routing layout shows location & routing of
main trays (ie) Trays from junction boxes to Control room
Pneumatic tubing layout shows locations of all Pneumatic
instruments like I/P converter, Control calves etc. and shows
Tubing trays and Purging connections for control panel, if
applicable.
12-08-04 35
OTHER DEPARTMENTS INTERACTION
12-08-04 37