0% found this document useful (0 votes)
15 views3 pages

Project Status Update

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views3 pages

Project Status Update

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Project

Status
Update
Project Name
Date
Instructions for Use
 File Name:
o AA - Country or client
o Project Name
o Date
o Version (if needed)
 Project the title slide while waiting for team members to join the meeting
 Work on the second slide during the meeting
o Adjust the timeline for your project. Don't show the entire year if the project is of shorter
duration. You can tailor it by adding more months or deleting the ones that you don't
need.
o Add important milestones by copying and pasting the existing ones
o Move the red line each week to show where you are
o Adjust colors to the appropriate level:
 Green - On track; Yellow - At risk; Red – Delayed; Black - Not started
o Complete the key results achieved, plan for upcoming activities, track your open action
and add notes.
Project Status Update
January February March April May June July August September October November December

Milestone WK: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52
Timeline Project Integration Go Live
Kick-off Build

Overall Schedule
Budget Status Issues Risks
 Add the results achieved during the weeks using bullet points
Project Status Status
Status Results Achieved
Weeks 1 & 2

Activity Status Overview


Activity Status Notes • Add the task(s) planned for the upcoming weeks
Project Kick-Off Complete
Planned Activities
Current State Discovery Complete
Weeks 3 & 4
Current State Validation Complete
Future State Discovery Complete
Future State Validation Complete o Add the results achieved during the weeks using bullet points
Design Validation Complete
System Configuration Complete Open Actions
Integration Design Complete
Integration Build In Progress
System Integration Testing (SIT) Complete o Use this space for notes
Training – Wave 1 In Progress
User Acceptance Testing (UAT) In Progress
Cutover Not Started Notes
Training – Wave 2 In Progress
Go-Live Not Started
Hyper Care Not Started

You might also like