0% found this document useful (0 votes)
61 views

Week 4 Time Chapter 06

The document summarizes key aspects of project time management, including defining activities, sequencing activities, estimating activity resources and durations, and developing the project schedule. It discusses collecting activity information and attributes, using network diagrams to show dependencies, and estimating resources and durations. Common tools for time management include Gantt charts, critical path method, PERT charts and project management software. Managing changes to the schedule and addressing individual work styles are also important to control the project schedule.

Uploaded by

utpalpatel
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views

Week 4 Time Chapter 06

The document summarizes key aspects of project time management, including defining activities, sequencing activities, estimating activity resources and durations, and developing the project schedule. It discusses collecting activity information and attributes, using network diagrams to show dependencies, and estimating resources and durations. Common tools for time management include Gantt charts, critical path method, PERT charts and project management software. Managing changes to the schedule and addressing individual work styles are also important to control the project schedule.

Uploaded by

utpalpatel
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 55

From previous lecture

Project Scope Management Processes

Information Technology Project Management, Sixth Edition

Collecting requirements: defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them Defining scope: reviewing the project charter, requirements documents, and organizational process assets to create a scope statement Creating the WBS: subdividing the major project deliverables into smaller, more manageable components Verifying scope: formalizing acceptance of the project deliverables Controlling scope: controlling changes to project scope throughout the life of the projectTechnology Project Information
Management, Sixth Edition 1

Chapter 6: Project Time Management


Information Technology Project Management, Sixth Edition

Learning Objectives

Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules Describe how project managers use network diagrams and dependencies to assist in activity sequencing Understand the relationship between estimating resources and project schedules Explain how various tools and techniques help project managers perform activity duration estimating

Information Technology Project Management, Sixth Edition

Learning Objectives (continued)


Use a Gantt chart for planning and tracking schedule information, find the critical path for a project, and describe how critical chain scheduling and the Program Evaluation and Review Technique (PERT) affect schedule development Discuss how reality checks and people issues are involved in controlling and managing changes to the project schedule Describe how project management software can assist in project time management and review words of caution Information Technology before using this software Project

Management, Sixth Edition

Importance of Project Schedules


Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes no matter what happens on a project Schedule issues are the main reason for conflicts on projects, especially during the second half of projects

Information Technology Project Management, Sixth Edition

Individual Work Styles and Cultural Differences Cause Schedule Conflicts Some people prefer to follow schedules and meet deadlines while others do not Difference cultures and even entire countries have different attitudes about schedules

Information Technology Project Management, Sixth Edition

Project Time Management Processes


Defining activities: identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables Sequencing activities: identifying and documenting the relationships between project activities Estimating activity resources: estimating how many resources a project team should use to perform project activities Estimating activity durations: estimating the number of work periods that are needed to complete individual activities Developing the schedule: analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule Controlling the schedule: controlling and managing changes to the project schedule

Information Technology Project Management, Sixth Edition

Figure 6-1. Project Time Management Summary

Information Technology Project Management, Sixth Edition

Defining Activities
An activity or task is an element of work normally found on the work breakdown structure (WBS) that has an expected duration, a cost, and resource requirements Activity definition involves developing a more detailed WBS and supporting explanations to understand all the work to be done so you can develop realistic cost and duration estimates

Information Technology Project Management, Sixth Edition


9

Activity Lists and Attributes

An activity list is a tabulation of activities to be included on a project schedule that includes:


The activity name An activity identifier or number A brief description of the activity

Activity attributes provide more information such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity
10

Information Technology Project Management, Sixth Edition

Milestones
A milestone is a significant event that normally has no duration It often takes several activities and a lot of work to complete a milestone Theyre useful tools for setting schedule goals and monitoring progress Examples include obtaining customer sign-off on key documents or completion of specific products

Information Technology Project Management, Sixth Edition


11

What Went Wrong?


At the U.S. Federal Bureau of Investigation (FBI), poor time management was one of the reasons behind the failure of Trilogy, a disastrous, unbelievably expensive piece of vaporware, which was more than four years in the (un)making. The system was supposed to enable FBI agents to integrate intelligence from isolated information silos within the Bureau.* In May 2006, the Government Accounting Agency said that the Trilogy project failed at its core mission of improving the FBIs investigative abilities and was plagued with missed milestones and escalating *Roberts, Paul, Frustrated contractor sentenced for hacking FBI to speed deployment, costs

InfoWorld Tech Watch, (July 6, 2006).


Information Technology Project Management, Sixth Edition
12

Sequencing Activities
Involves reviewing activities and determining dependencies A dependency or relationship is the sequencing of project activities or tasks You must determine dependencies in order to use critical path analysis

Information Technology Project Management, Sixth Edition

13

Three types of Dependencies


Mandatory dependencies: inherent in the nature of the work being performed on a project, sometimes referred to as hard logic Discretionary dependencies: defined by the project team; sometimes referred to as soft logic and should be used with care since they may limit later scheduling options External dependencies: involve relationships between project and nonproject activities Information Technology Project

Management, Sixth Edition

14

Network Diagrams
Network diagrams are the preferred technique for showing activity sequencing A network diagram is a schematic display of the logical relationships among, or sequencing of, project activities Two main formats are the arrow and precedence diagramming methods

Information Technology Project Management, Sixth Edition


15

Figure 6-2. Sample Activity-on-Arrow (AOA) Network Diagram for Project X

Information Technology Project Management, Sixth Edition

16

Arrow Diagramming Method (ADM)


Also called activity-on-arrow (AOA) network diagrams Activities are represented by arrows Nodes or circles are the starting and ending points of activities Can only show finish-to-start dependencies

Information Technology Project Management, Sixth Edition

17

Process for Creating AOA Diagrams


1. Find all of the activities that start at node 1. Draw

their finish nodes and draw arrows between node 1 and those finish nodes. Put the activity letter or name and duration estimate on the associated arrow. 2. Continue drawing the network diagram, working from left to right. Look for bursts and merges. Bursts occur when a single node is followed by two or more activities. A merge occurs when two or more nodes precede a single node. 3. Continue drawing the project network diagram until all activities are included on the diagram that have dependencies. 4. As a rule of thumb, all arrowheads should face toward the right, and no arrows should cross on an AOA network diagram.
Information Technology Project Management, Sixth Edition
18

Precedence Diagramming Method (PDM)


Activities are represented by boxes Arrows show relationships between activities More popular than ADM method and used by project management software Better at showing different types of dependencies

Information Technology Project Management, Sixth Edition

19

Figure 6-3. Task Dependency Types

Information Technology Project Management, Sixth Edition

20

Figure 6-4. Sample PDM Network Diagram

Information Technology Project Management, Sixth Edition

21

Estimating Activity Resources


Before estimating activity durations, you must have a good idea of the quantity and type of resources that will be assigned to each activity; resources are people, equipment, and materials Consider important issues in estimating resources

How difficult will it be to do specific activities on this project? What is the organizations history in doing similar activities? Are the required resources available?

A resource breakdown structure is a hierarchical structure that identifies the projects resources by category and type
22

Information Technology Project Management, Sixth Edition

Activity Duration Estimating


Duration includes the actual amount of time worked on an activity plus elapsed time Effort is the number of workdays or work hours required to complete a task Effort does not normally equal duration People doing the work should help create estimates, and an expert should review them

Information Technology Project Management, Sixth Edition


23

Three-Point Estimates

Instead of providing activity estimates as a discrete number, such as four weeks, its often helpful to create a three-point estimate
An estimate that includes an optimistic, most likely, and pessimistic estimate, such as three weeks for the optimistic, four weeks for the most likely, and five weeks for the pessimistic estimate

Three-point estimates are needed for PERT and Monte Carlo simulations
24

Information Technology Project Management, Sixth Edition

Developing the Schedule


Uses results of the other time management processes to determine the start and end date of the project Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project Important tools and techniques include Gantt charts, critical path analysis, and critical chain scheduling, and PERT analysis

Information Technology Project Management, Sixth Edition


25

Gantt Charts
Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format Symbols include:

Black diamonds: milestones Thick black bars: summary tasks Lighter horizontal bars: durations of tasks Arrows: dependencies between tasks
26

Information Technology Project Management, Sixth Edition

Figure 6-5. Gantt Chart for Project X

Note: Darker bars would be red in Project 2007 to represent critical tasks.

Information Technology Project Management, Sixth Edition

27

Figure 6-6. Gantt Chart for Software Launch Project

Information Technology Project Management, Sixth Edition

28

Adding Milestones to Gantt Charts


Many people like to focus on meeting milestones, especially for large projects Milestones emphasize important events or accomplishments on projects Normally create milestone by entering tasks with a zero duration, or you can mark any task as a milestone

Information Technology Project Management, Sixth Edition


29

SMART Criteria

Milestones should be:


Specific Measurable Assignable Realistic Time-framed

Information Technology Project Management, Sixth Edition

30

Best Practice

Schedule risk is inherent in the development of complex systems. Luc Richard, the founder of www.projectmangler.com, suggests that project managers can reduce schedule risk through project milestones, a best practice that involves identifying and tracking significant points or achievements in the project. The five key points of using project milestones include the following:
1. Define milestones early in the project and include them in the Gantt chart to provide a visual guide. 2. Keep milestones small and frequent. 3. The set of milestones must be all-encompassing. 4. Each milestone must be binary, meaning it is either complete or incomplete. 5. Carefully monitor the critical path.

Information Technology Project Management, Sixth Edition

31

Figure 6-7. Sample Tracking Gantt Chart

Information Technology Project Management, Sixth Edition

32

Critical Path Method (CPM)


CPM is a network diagramming technique used to predict total project duration A critical path for a project is the series of activities that determines the earliest time by which the project can be completed The critical path is the longest path through the network diagram and has the least amount of slack or float Slack or float is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date Information Technology Project

Management, Sixth Edition

33

Calculating the Critical Path


First develop a good network diagram Add the duration estimates for all activities on each path through the network diagram The longest path is the critical path If one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action

34

Information Technology Project Management, Sixth Edition

Figure 6-8. Determining the Critical Path for Project X

Information Technology Project Management, Sixth Edition

35

More on the Critical Path


A project team at Apple computer put a stuffed gorilla on the top of the cubicle of the person currently managing critical task The critical path is not the one with all the critical activities; it only accounts for time

Remember the example of growing grass being on the critical path for Disneys Animal Kingdom

There can be more than one critical path if the lengths of two or more paths are the same The critical path can change as the project progresses

Information Technology Project Management, Sixth Edition

36

Using Critical Path Analysis to Make Schedule Trade-offs

Free slack or free float is the amount of time an activity can be delayed without delaying the early start of any immediately following activities Total slack or total float is the amount of time an activity may be delayed from its early start without delaying the planned project finish date A forward pass through the network diagram determines the early start and finish dates A backward pass determines the late start and finish dates
37

Information Technology Project Management, Sixth Edition

Figure 6-9. Calculating Early and Late Start and Finish Dates

Information Technology Project Management, Sixth Edition

38

Table 6-1. Free and Total Float or Slack for Project X

Information Technology Project Management, Sixth Edition

39

Using the Critical Path to Shorten a Project Schedule

Three main techniques for shortening schedules


Shortening durations of critical activities/tasks by adding more resources or changing their scope Crashing activities by obtaining the greatest amount of schedule compression for the least incremental cost Fast tracking activities by doing them in parallel or overlapping them

Information Technology Project Management, Sixth Edition

40

Importance of Updating Critical Path Data


It is important to update project schedule information to meet time goals for a project The critical path may change as you enter actual start and finish dates If you know the project completion date will slip, negotiate with the project sponsor

Information Technology Project Management, Sixth Edition

41

Critical Chain Scheduling

Critical chain scheduling

A method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date

Uses the Theory of Constraints (TOC)


A management philosophy developed by Eliyahu M. Goldratt and introduced in his book The Goal and Critical Chain

Attempts to minimize multitasking

When a resource works on more than one task at a time


42

Information Technology Project Management, Sixth Edition

Figures 6-10a and 6-10b. Multitasking Example

Information Technology Project Management, Sixth Edition

43

Buffers and Critical Chain


A buffer is additional time to complete a task Murphys Law states that if something can go wrong, it will Parkinsons Law states that work expands to fill the time allowed In traditional estimates, people often add a buffer to each task and use it if its needed or not Critical chain scheduling removes buffers from individual tasks and instead creates:
Project buffers or additional time added before the projects due date Feeding buffers or additional time added before tasks on the critical path

Information Technology Project Management, Sixth Edition

44

Figure 6-11. Example of Critical Chain Scheduling

Information Technology Project Management, Sixth Edition

45

Program Evaluation and Review Technique (PERT)


PERT is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates PERT uses probabilistic time estimates

Duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations, or a threepoint estimate
Information Technology Project Management, Sixth Edition
46

PERT Formula and Example

PERT weighted average =

optimistic time + 4X most likely time + pessimistic time 6

Example: PERT weighted average =

8 workdays + 4 X 10 workdays + 24 workdays = 12 days 6 where optimistic time = 8 days most likely time = 10 days, and pessimistic time = 24 days Therefore, youd use 12 days on the network diagram instead of 10 when using PERT for the above example
Information Technology Project Management, Sixth Edition
47

Schedule Control Suggestions


Perform reality checks on schedules Allow for contingencies Dont plan for everyone to work at 100% capacity all the time Hold progress meetings with stakeholders and be clear and honest in communicating schedule issues

Information Technology Project Management, Sixth Edition

48

Controlling the Schedule

Goals are to know the status of the schedule, influence factors that cause schedule changes, determine that the schedule has changed, and manage changes when they occur Tools and techniques include:

Progress reports A schedule change control system Project management software, including schedule comparison charts like the tracking Gantt chart Variance analysis, such as analyzing float or slack Performance management, such as earned value (Chapter 7)
49

Information Technology Project Management, Sixth Edition

Reality Checks on Scheduling


First review the draft schedule or estimated completion date in the project charter Prepare a more detailed schedule with the project team Make sure the schedule is realistic and followed Alert top management well in advance if there are schedule problems

Information Technology Project Management, Sixth Edition


50

Working with People Issues


Strong leadership helps projects succeed more than good PERT charts Project managers should use:

Empowerment Incentives Discipline Negotiation

Information Technology Project Management, Sixth Edition

51

What Went Right?

Mittal Steel Poland earned Polands Project Excellence Award in 2007 for implementing a SAP system Derek Prior, research director at AMR Research, identified three things the most successful SAP implementation projects do to deliver business benefits: Form a global competence centre Identify super-users for each location Provide ongoing involvement of managers in business processes so they feel they own these processes

Information Technology Project Management, Sixth Edition

52

Using Software to Assist in Time Management


Software for facilitating communications helps people exchange schedule-related information Decision support models help analyze trade-offs that can be made Project management software can help in various time management areas

Information Technology Project Management, Sixth Edition


53

Words of Caution on Using Project Management Software


Many people misuse project management software because they dont understand important concepts and have not had training You must enter dependencies to have dates adjust automatically and to determine the critical path You must enter actual schedule information to compare planned and actual progress

Information Technology Project Management, Sixth Edition


54

Chapter Summary
Project time management is often cited as the main source of conflict on projects, and most IT projects exceed time estimates Main processes include:

Define activities Sequence activities Estimate activity resources Estimate activity durations Develop schedule Control schedule
55

Information Technology Project Management, Sixth Edition

You might also like