Unit 2
Unit 2
Prepared By:
Jay Prakash Maurya
Syllabus of Unit 3
• Resource allocation –
– Most effective ways of allocating resources
– Investigate the relationship between timescales and
resource availability
– Efficacy of additional spending on resource
procurement.
• Detailed costing –
– How much will the project cost
Activity planning Objectives
– what expenditure likely to take place?
– More detailed estimates of costs and their timing.
• Motivation –
– Providing targets and being seen to monitor
achievement against targets is an effective way
• Co-ordination –
– Staff in different departments need to be available
– When do staff need to be transferred between projects?
– Effective vehicle for communication and co-ordination
among teams
• Activity planning –
– Activity risk analysis - aimed at identifying
potential problems.
– Resource allocation - The expected availability of
resources might place constraints on when certain
activities can be carried out
– Schedule production - Once resources have been
allocated to each activity, we will be in a position
to draw up and publish a project schedule.
Project Schedule
– Project schedule simply means a mechanism that is used
to communicate and know about that tasks are needed
and has to be done or performed and which organizational
resources will be given or allocated to these tasks and in
what time duration or time frame work is needed to be
performed.
– A schedule in your project’s time table
– Consists of sequenced activities and milestones that are
needed to be delivered under a given period of time.
– Identify
• list the category of activities involved from the
start to the completion of the project.
• The activities are grouped in categories which are
different from each other.
– Arrange
• The list of activities, as in above, in sequential
order of their performance.
• There may be activity which can be started only
after the completion of some other activity,
whereas there may also be some other independent
activity which can be started simultaneously.
Network Planning Models
– With the details of A and B above, draw the diagram of
the network of the activities so that the operational
planning of the execution of the entire project can be
visualized.
• This whole procedure is the network planning of the
project schedule which makes the monitoring and
controlling of the project.
• Terms Frequently used in Network Diagram:
1. Events
1. An ‘event’ is an occurrence, representing a happening of
an incident.
2. It represents a static point of time denoting completion
of all preceding activities.
3. The earliest event occurrence (EET) is the longest of
this early finish time of all activities merging to the event.
4. Head Event, Tail Event, Burst Event and Merge Event.
Network Planning Models
2. ‘Activity’
1. Indicates an operation carrying out a defined work.
2. It is a continuity till the work is completed
3. The time element required to complete the work is called
the ‘duration’ of the activity.
4. When activities are carried out from one event to another,
the preceding event is called ‘tail event’ and the
succeeding one is ‘head event’.
3. Slack
1. Associated with an event and represents the difference
between the EET and LET of that particular event.
2. This is the breathing time of an event
4. Arrow
1. Indicates continuous flow of the projected activity.
2. Every activity is represented by one arrow with its tail as
the start and the ‘head’ as the completion of the
activity.
Network Planning Models
1. Conventionally the arrow is from left to right showing the
direction towards the completion of the activity.
3. Dummy Activity
1. Occasion when the connecting of some activities is by
dotted line arrow, which is called dummy activity.
2. Does not consume any resources
3. Indicate the logic/logistic part.
• The activity starts from an event, that is, the ‘tail event’.
• The activity on completion of the defined work lands up
to another event, the head event.
• Therefore, no activity can start unless the tail event
with the exception of the very first activity starting from
the number one event.
• The event is also called ‘NODE’. When- more than one
activity emanates from one event, such event is called
‘burst event’.
Network Planning Models
• When a number of activities terminate in one event,
such event is called ‘merge event’.
• The burst event and the merge event diagrams shown
below:
– The length of the arrow does not have any relation with
the duration of time.
– The events and activities follow the dependency rule
• Overlapping Activities
– In network construction we assume that a succeeding
activity can start only after the completion of the preceding
activity.
– In reality, may not be necessary as such in some cases,
particularly when a series of items are to pass through a
sequence of activities
Network Planning Models
• In such cases, selecting one activity and instead of
completing the entire series, the work can be
economically carried out.
• SWOT Analysis
– Strengths-Weaknesses-Opportunities-Threat (SWOT) is
very technique and helpful for identifying risks within
greater organization context.
– Used as planning tool for analyzing business & its
resources.
– Technique often used in formulation of strategy simply
by looking at internal strengths and weaknesses and
opportunities and threats in external environment.
– The appropriate time and effort should be spent
– SWOT analysis is more effective and successful in risk
identification.
Managing Risk
• Flowchart Method –
– Dynamic process to be diagrammatically represented in
paper.
– Used to represent activities of process graphically and
sequentially to simply identify the risk.
Managing Risk
• Risk Assessment
– Risk assessment is a step in a risk management
procedure. Risk assessment is the determination of
quantitative or qualitative value.
– Risk assessment involves measuring the probability
that a risk will become a reality.
– Risk assessment is not a project manager's
responsibility its ideas of the entire team.
• Project Manager: acts as the chairperson
• Project Team: project manager assign any project team
member the roles of recorder and timekeeper
• Key Stakeholders: those identified that may bring
value in the identification of project risks.
• Subject Matter Experts: those identified that may
specialize in a certain project activity
Managing Risk
– Project Sponsor: may participate depending on the size
and scope of the project
Risk Identification
Compiled a list of risks from previous project experiences.
Reviewed at the beginning of the project
Give an insight to the members to predict possible risks.
Use methods for identifying risks like Crawford Slip method
Managing Risk
Managing Risk
2. Categorize and Group Duplicates
Categorizing risks is a way to systematically identify the
risks.
Provide a foundation for awareness, understanding and
action.
The most common, easy and the most effective method
for this is to post the sticky notes
3. Qualify Risks
Assign Probability and Impact to Each Risk
The key questions to assess any risk in projects are:
• What is the risk – how will I recognize it if it becomes a
reality?
• What is the probability of it happening – high, medium
or low?
• How serious a threat does it pose to the project – high,
medium or low?
Managing Risk
• What are the signals or triggers that we should be looking
out for?
5. Documentation of Risks
– Enter all the risks, probability-impact scores, and
responses and maintain a document to explain all risks.
Managing Risk
– The high scoring risks will be added to the Project
Management Plan.
– As a method to track the risk at the correct time.
– Provide awareness and visibility to the participants
• Risk Monitoring -
– where you keep track of about how your risk
responses are performing against the plan as well as
the place where new risks to the project are managed.
– Risks can have negative and positive impacts.
– Positive risk - potential benefits outweigh the
traditional approach
– Negative risk - negatively influence the cost of
– Following primary objectives as follows.
• To check if predicted risks occur or not.
• To ensure proper application of risk aversion steps
defined for risk.
Managing Risk
• To collect data for future risk analysis.
• To allocate what problems are caused by which
risks throughout the project.
• As the project proceeds, risk monitoring activities
commence. The project manager monitors factors
• In the case of high staff turnover, the following factors
can be monitored: