Internship Presentation
Internship Presentation
Internship Presentation
Presentation/Progress
Report
Company Name:
KALYAN TOLL INFRASTRUCTURE LTD.
Intern/Trainee:
Sanket Agrawal-85
Company Background
• Kalyan Toll Infrastructure Limited was incorporated in the year 2002
• Kalyan Toll Infrastructure Limited is one of the leading Four construction company in Madhya Pradesh. The company has been registered for
construction works with Public Works Department of Maharashtra and Madhya Pradesh as "A" category contractor. The Company is registered for VAT &
TIN, EPF, Service Tax, Professional Tax, Income Tax, and Importer Exporter Code.
• Apart from latest methods and techniques, the company has introduced computerization in its working. Kalyan Toll Infrastructure Limited is always on
the move to improve its productivity further by introduction of latest technology and tools of management.
Our construction activities comprise of :
• Road Projects
• Railway Projects
• Bridges, ROB and Flyover Projects
• Water Supply Projects
• Commercial and Residential Complexes
• Sewerage Projects
• Construction of Dams
Kalyan Toll Infrastructure Limited is one of the few construction companies in M.P., which has successfully executed TEN BOT projects and THREE are
under execution.
The company has a historical growth because it has carried out Constructions of projects worth more than Rs 15000 millions in different states like Madhya
Pradesh, Uttar Pradesh, Maharashtra. Rajasthan & Gujarat. Thus the company has contributed its might in nation building.
https://kalyangroup.in/About_Us.html
Internship Details
Internship Details
This project comes under PWD Nanded and Kalyan Toll is executing the Project.
• The day when I joined the internship, Excavation around the toe of the existing road was going on.
• Also cutting of the existing flexible pavement using cold Milling Machine Wirtgen W-100 was ongoing.
• I got the opportunity to be on the Milling machine to understand its usage and working principle.
• I have been Embankment construction , on the excavation work also to understand type of working practices
used in excavation of the road construction.
• As a Jr. Site Engineer I have been trained to operate very important and useful surveying Instrument viz. Auto
Level Machine.
• Level Machine is used in conjunction with a levelling staff to establish the relative height or levels (the vertical
separation) of objects or marks and to measure height differences and to transfer, measure, and set heights of
known objects and marks.
• After the excavation part, Murum filling part and Subgrade preparation part was also done.
• I have also got to know type of safety measure to be taken while working on the site.
• Understood about the different types of Machinery such as Grader, Roller, Pokhlan, JCB machine its uses,
working principle.
• Built up new connections and network of people.
Actual Site Details
• Wherever excavation, cutting work is going on we have installed the Warning boards in order to
maintain smooth flow of the traffic.
• Gunny bags are kept along the side of the ongoing cutting area and radium is applied on each of the
bag.
• Safety ribbons (Danger illuminated radium) were also applied.
• For smooth traffic flow , cutting/ excavation work is started 20 m away from any intersection, small
bridges, junctions etc.
• On working on the Road construction site safety is the top preference.
• Speed limit boards were also installed.
• After the work for the day is done, proper safety measures are taken.
Some glimpse of the site