Introduction PPT
Introduction PPT
Introduction PPT
Engg
• Briefing : Already discussed last class: Review again
High-side and low-side switching:
• In Figure 1.2, the high-voltage switching is done with a simple switch.
More extensive substations may use high-voltage circuit breakers in a
variety of high-voltage bus designs. The low-voltage switching in
Figure 1.2 is accomplished with relay-controlled circuit breakers. In
many cases, reclosure will be used in place of the relay/circuit
breaker combination. Some substation designs will include a low-
voltage bus circuit breaker in addition to the circuit breakers for each
feeder. As is the case with the high-voltage bus, the low-voltage bus
can take on a variety of designs.
Voltage transformation
• : The primary function of a distribution substation is to reduce the
voltage down to the distribution voltage level. In Figure 1.2, only one
transformer is shown. Other substation designs will call for two or
more three-phase transformers. The substation transformers can be
three-phase units or three single-phase units connected in a standard
connection. There are many “standard” distribution voltage
transformers.
Voltage regulation
• As the load on the feeders vary, the voltage drop between the substation and the user will
vary. In order to maintain the user’s voltages within an acceptable range, the voltage at the
sub-station needs to vary as the load varies. In Figure 1.2, the voltage is regulated by a “step-
type” regulator that will vary the voltage plus or minus 10% on the low-side bus. Sometimes
this function is accom-plished with a “load tap changing” (LTC) transformer. The LTC changes
the taps on the low-voltage windings of the transformer as the load varies.
• Many substation transformers will have “fixed taps” on the high-voltage winding for Off load
• These are used when the source voltage is always either above or below the nominal
voltage.
• The fixed tap settings can vary the voltage plus or minus 5%. Many times instead of a bus
regulator, each feeder will have its own regulator. This can be in the form of a three-phase
gang-operated regulator or individual phase regulators that operate independently.
Protection:
• The substation must be protected against the occurrence of short
circuits. In the simple design of Figure 1.2, the only auto-matic
protection against short circuits inside the substation is by way of the
high-side fuses on the transformer. As the substation designs become
more complex, more extensive protective schemes will be employed
to protect the transformer, the high- and low-voltage buses, and any
other piece of equipment. Individual feeder circuit breakers or
reclosers are used to provide interruption of short circuits that occur
outside the substation.
Metering
• : Every substation has some form of metering. This may be as simple as
an analog ammeter displaying the present value of sub-station current as
well as the minimum and maximum currents that have occurred over a
specific time period.
• Digital recording meters are becoming very common. These meters
record the minimum, average, and maximum values of current, voltage,
power, power fac-tor, etc., over a specified time range. Typical time
ranges are 15 min, 30 min, and 1 h.
• The digital meters may monitor the output of each substation
transformer and/or the output of each feeder.
•
The substation of Figure has two LTC transformers, serves four dis-tribution feeders, and is fed
from two sub transmission lines. Under normal conditions, the circuit breakers (CB) are in the
following positions:
• So, load flow analysis is required for taking various decisions during the operational stages of
the distribution system as well as the design stage of the distribution system.
• So, during the operational stage like load balancing or reconfiguration of the distribution
system, we need a load flow analysis.
• During the design stage while we are selecting conductor size of the distribution conductors
or transformer sizes we need to know the load flow solution.
• Voltage regulation and tap operation during the operational stage we need result from load
flow analysis,
• Power loss reduction we need load flow analysis;
• then nowadays capacitor placement as well as DG placement, we need results from load flow
analysis.
• Then short circuit analysis is required while during the settings for protective relays or
• During the relay coordination in a distribution system also to calculate short-circuit current in
the upstream network.
• So, we need actually result from short circuit analysis during these design stages.