Final Design Presentation
Final Design Presentation
Final Design Presentation
• Surface Water
• Groundwater
SURFACE
• River Obinna
• 106.57sq
• 2.6cumecs
• Baseflow fro the ajali sandstone acquifer
• Unit Hydrograph
• Flood hydrograph for 100 year return period using satellite rainfall
data
GROUNDWATER
• Hydrogeology
• Scarpland and outcrop of ajali sandstone
• Recharge area at high elevation
• Dips in westerly direction and drives flows from east to west accordingly
• Imo shale and Nkporo shale confining the prolific ajali sandstone
• Artisan conditions exist because the elevation around the Adani irrigation
scheme is bellow the pizometric height of the confined groundwater. The
recharge area around the eastern scarpland is much higher.
Geophysical investigation
• Water Source:
• We have assumed that the source of water will be in the middle of the plot or on the top portion of an inclined plot.
Artesian wells in this project area are found to present on the average; flow conditions of 100m3/hr capacity at 20m Head.
• Pipe Network:
• Consists of Mainline, Sub-mainlines and Laterals.
• Medium to large sprinkler irrigation systems serviced by a single source of water function efficiently by looping part of the
pipe line system. Loops allow for even pressure distribution within the looped system, it is budget friendly and makes
maintenance and operation of system easier. The mainline usually comes from the water source as a single line. At each
looped service point; it splits into two pipes (often smaller in size than the mainline). The two pipes will rejoin each other
to form a loop. Isolation valves maybe added to loops to aid operation and maintenance requirement. Shutting of any part
does preclude other sections from functioning.
•
Design Proper cont.
• Pipe Sizing
• We have a peculiarity in sizing and choosing conduits down the line
from source to exit through sprinklers. The luxury of mechanical
assistance is absent and events are solely controlled on the basis of
the well piezo metric head. In other words, pressure compensation
cannot be made. We are constrained to design within a narrow range
of pressure of 1.5 bar to 2.0 bar. Therefore, conduits must be sized for
near zero pressure drop for the system. As mentioned earlier, looping
will be employed as much as possible to achieve to the barest
minimum dynamic pressure losses
Design Proper cont.
• Pipe sizing
• This design will be constrained to keep the total pressure loss to less than or 0.5 bar
from source to sprinkler theoretically flow through;
• Mainline loss ≤ 0.166 bar
• Sub-Mainline ≤ 0.166 bar
• Laterals ≤ 0.166 bar
• Total 0.166 x 3 = 0.498 bar
• Tables developed for Laminar water flow in pipe will be consulted
extensively in determining conduit sizes for the mainline, sub-mainlines and
the laterals
• The Hazen Williams formula in conjunction with the general laminar flow
velocity equation in pipes were used empirically to compile such tables.
Design Proper cont.
• Mainline
• 6” pipe, head loss .03bar < 0.166 bar (150mm x 7mm Upvc pipe)
• Sub-Mainline
• The Mainline delivers flow to 2 loops at a time, the loops been equal geometrically we can
safely assume that each loop receives half of the total flow
• Use 90mm x 5mm Upvc pipe as sub-mainline
• Laterals lines
• The design loop must feed the lateral lines within the 2 symmetrical segments so that pressure
at all hydrant points will be same generally speaking. The hydrants are set at 25meter centers
for each segment i.e. 24 hydrants on each loop. This allows for convenient deployment of
movable sprinkler units on a stand with 50 meters of non-kink flexible hose in any direction.
Design Proper cont.
• Sprinkler Selection and Matching
• NAANDANJAIN 5022SD is in reference. It performs between 1.5bar to
4.0bar. The performance related to our desired values are highlighted
below:
• Nozzle Pressure(bar) Qm3/hr/gpm
R(M)
• 2.5 1.5 0.320/1.4 9.5
• 2.0 0.375/1.6 10
• 2.8 1.5 0.415/1.8 10.75
• 2.0 0.475/2.06 11.0
Design Proper cont.
• Sprinkler Run-time
• In general using irrigation as the only source of water the average amount
of time required to put the daily crop water need using the adopted
sprinkler (nozzle) at 10m spacing either singly or in group can be estimated
• For Upland Rice: 5.3mm is the daily water need
Run-time = 5.3mm per day/4.15mm/hr
= 1.28hr/day = 1hr 20min (nearest 5min)
Design Proper cont.
• The Surface Scheme
• Detailed Topographic Survey
• Main canal
• Invokes the Manning’s equation for expression of open channel flows in channels.
• V= (1/n)R3/2S1/2
• Q=VA
• 4.3m3/sec delivering 36MCM
• Existing scheme can take 14MCM leaving a balance of 22MCM
• Secondary Canals
• 18 sectors feed by Secondary canals see table
• Two sets of canals sized (using Manning’s equation) for constructional ease
Design Proper cont.
• Tertiary/field canals canals
• Maximum discharge on field canal is .026m3/sec
• Inflow time
• The time for which water flows into the basin. This is selected to allow the desired dept of
infiltration taking place at the far end of the basin. In General this is the summation of the
advance time and the time required to deliver the volume of water needed for adequate
irrigation. 4-hours inflow time with a flow rate of about 27liters/sec is worked out thus:
• Ta = FnL/60QnE
• Ta =inflow time
• L= length of basin 100m
• Qn= application efficiency 65%
• E= Unit inflow rate Q/50mm
• Bunds/ ridges
• These are marked out to be approximately in 100m x 50m giving a plot size of
0.5ha
Layout drawings
• Carlson civil Suite software was used in the drafting.
BEME
• Spread sheets show the BEME as well as the supporting calculations.
calculations