Utcl Nathdwara - 03.02.2024
Utcl Nathdwara - 03.02.2024
Utcl Nathdwara - 03.02.2024
UTCL, NATHDWARA
Key Highlights– Till 03rd FEB 2024
Infinite -Uptime has generated total 49 reports so far with
total savings up to 160hrs
www.infinite-uptime.com
Open Report Details
Created Recommendation
Machine Name Fault Fault Progression Trend Spectrum Remarks
Date
www.infinite-uptime.com
Open Report Details
Created Recommendation
Machine Name Fault Fault Progression Trend Spectrum Remarks
Date
1.In the next opportunity Check the
gears for high backlash & increased
tooth clearances, if found above limits
fluctuation in all three then adjust / repair.
Vibration characteristics Indicates velocity trend are incresed 11 Jan 2. To confirm the defect, rpm of each
Coal Mill-1 Main Drive L41 MD1-GB I/P
improper Gear meshing in the shaft in gearbox and no. of teeth of
DE from 5-10mm/s to 5- 2024
Gearbox. each gear is required, provide the
20mm/s same.
3. Conduct the WDA of gearbox oil on
immediate basis and share the report
with Infinite Uptime.
Crusher Main drive- CRUSHER Velocity trend is increasing and
(Crusher main drive-Crusher DE) vibration characteristics 1. Check & correct the alignment
Indicates minor misalignment Only fluctuation in axial 30 Jan between Motor & Rotor Pulleys.
between Motor & Crusher velocity, Overall trend of 2024 2. Inspect the condition of belts
pulleys. velocity (RMS) shows
and check them for proper tension.
progression 8 (mm/s to
3. Ensure that Rotor NDE bearing is
13mm/s) in last 15days
properly lubricated.
www.infinite-uptime.com
Thank you!