Project Risk Management and Resource Scheduling
Project Risk Management and Resource Scheduling
Management and
Resource Scheduling
Project Management and Basics of Research
BTHM32013G
1
Risk
• A risk may be defined as a potential problem.
2
Risk and Uncertainty
“Risk is the situation, where there is enough information to justify
assignment of probabilities to different outcomes, thus enabling us
to calculate the expected value of outcomes”.
• Risk can be insured against investment for them.
• Positive risks are called opportunities.
• Negative risks are called threats.
Accordingly,
Risk = f (Likelihood, Impact, Risk Exposure)
4
Systematic Risk Vs Unsystematic Risk
• Systematic Risk
This risk that affects the overall market. Occurs due to change in the
country’s economic position, tax reforms, or a change in the world energy
situation etc.
• Unsystematic risk
This risk that is independent of economic and political and all other such
factors. It is associated with factors related to a particular company or industry.
5
Project Risk Management
• The objective of project risk management is to
- understand project and programme level risks
- minimize the likelihood of negative events
- maximize the likelihood of positive events on projects and
programme outcomes.
6
Project Risk Management
• Risk management is a process of the identification, analysis, assessment,
control, and avoidance, minimization, or elimination of unacceptable
risks.
8
Project Risk Identification
• Risk identification is the identification of all possible risks that
could either negatively or positively affect the project.
9
Sources of Project Risk Identification
• What you need to identify a Project Risk
• Product description
• Planning documents
• Project Scope Statement
• Cost Management Plan
• Schedule Management Plan
• Communications Management Plan
• Enterprise Environmental Factors
• Stakeholder Register
• Quality Management Plan
• Historical Information (Previous Project Data)
• Expert Knowledge
10
Risk analysis
• The analysis phase determines the likelihood and impact of each
identified risk and prioritizes risks for management attention.
11
Response Planning
• Response planning is the phase where the project team
develops response actions and alternative options to reduce
project risks.
12
Risk Response strategies - I
• Risk response strategies will target to reduce the Probability or Impact
of the risk
• A risk response strategy should be
• Realistic
• Cost effective
• Agreeable to key stakeholders
• Responsible
• Main Risk Response Strategies are as follows
i. Avoiding the Risk
ii. Transference the Risk
iii. Mitigating the Risk
iv. Accepting the Risk
13
Risk Response strategies - II
• Avoidance of Risk usually involves changing the project plan
including
a) Expanding the Schedule of the Project
b) Reducing the Scope of the Project
c) Increasing the Cost of the Project to eliminate the risk
14
Risk Response strategies - III
• Mitigation of Risk involves carrying out work now to reduce the
Probability and / Or Impact of a risk to be within the acceptable
threshold limits
• It may include preventive, detective or testing possible ways to
reduce the risk
16
Expected Return and Risk
• Assume that there is an equal probability (P = 0.25) associated
with the four states of economic conditions
• Hence, the Expected Value / Expected Net Present Value
[E(NPVi )] is the sum of product of each outcome (NPV) and its
associated probability as summarized in the table.
Economic conditions NPV (Rs. Mn) Probability Expected Value
(1) (2) (NPV) (Rs.Mn)
(3) – (1) x (2)
High Growth 18.5 0.25 4.63
Expansion 10.5 0.25 2.62
Stagnation 1.0 0.25 0.25
Decline (6.0) 0.25 (1.50)
Expected Rate of Return - 1.0 6.00
17
Expected Return and Risk
• Expected Value of the Project is the average rate of return / NPV.
• It is only 6% in the above example.
• It is noted that the possible outcomes or NPV varies from - 06% to
+18.5%.
• Hence, the returns are expected to fluctuate widely due to its standard
deviation of 9.29% is comparatively high . The lower NPV would be -
06% and highest NPV would be 18%.
• Investors tend to prefer with higher NPV and lower standard deviation
• Maxim: High Risk leads to High Return
19
Active Learning
NPV Probability
200 0.3
600 0.5
900 0.2
20
Active Learning - Answer
NPV Probability
200 0.3
600 0.5
900 0.2
21
Monitoring and Controlling
• The final step of risk management is monitoring and control.
22
Resource Scheduling
23
Resource Scheduling
• Resource scheduling is the process of identifying when project
resources are needed and allocating them based on factors such
as capacity planning or resource availability.
• This leads to not only getting projects done on time and within
budget, but also builds morale, fosters better relationships, helps
with profitability and boosts stakeholder satisfaction.
24
Scheduling Techniques
• Work Breakdown Structure - The project is scheduled in
various phases following a bottom-up or top-down approach.
25
26