Margareta Hotel Presentation
Margareta Hotel Presentation
Margareta Hotel Presentation
North Facade /
Superstructure / (10) Days - Lag [ Densglass Sheathing
Project Byout / Foundation / Piles Area A – [ 1st Floor through Scaffolding
Subcontractor through Roof Floor] Removal]
award - Project Start
Start : Dec,03-2018
Finish : Dec,31-2018
Duration : 18 days
Start : May,19-2018
Start : Jul,07-2020 Finish : Jul,06-2018
Finish : Sep,16-2018 Finish : Aug,12-2020 Duration : 30 days
Project Finish
Duration : 25 days
1st LVL – Verticals Only
Structural Work (Sequence) – Margaritaville Beach Hotel 2nd LVL
3rd LVL
4th LVL
5th LVL
6th LVL
7th LVL
8th LVL
Roof Slab
Start : Jan,25-2019
Finish : May,08-2019
Duration : 66 days
S.O.G Will start after
Completion of 5th LVL
Structural work
Start : Jan,25-2019
Finish : May,08-2019
Duration : 66 days
Facade Work (Sequence) – Margaritaville Beach Hotel
Once we finish
structural work till
roof then we go
Once we finish with West Façade
W
S
structural work till after 30 days :
roof then we go
with South Façade
after 20 days : Start : Jan,17-2020
Finish : Jun,18-2020
Duration : 97 days
Start : Jan,02-2020
Finish : Jun,03-2020
Duration : 97 days
Once we finish
structural work till
Oncethen
roof we finish
we go
Once we finish
structural
with Northwork till
Façade
structural work till
roof then
after we :go
10 days
roof then we go
with North Façade
with East Façade :
after 10 days :
Start : Dec,16-2019
Finish : May,18-2020
Start : Nov,27-2019
Start : Dec,16-2019
Duration : 97 days
Finish : May,01-2020 E Finish : May,18-2020
Duration : 97 days
N
Duration : 97 days
***Critical***
Landscape (Sequence) – Margaritaville Beach Hotel
W Once we Remove
Scaffolding of West
Façade then we go
Once we Remove through Landscape
Scaffolding of South (West Side)
Façade then we go Start : Jun,19-2020
through Landscape Finish : Jul,29-2020
(South Side) Duration : 25 days
Start : Jun,04-2020 S
Finish : Jul,13-2020
Duration : 25 days
Once we Remove
Once we Remove
Scaffolding of North
Scaffolding
Façade we goofwithNorth
Once we Remove Scaffolding Façade
Storm Techwe (Start
go with
:
of East Façade we go with Storm Tech (Start :
May,19-2018
tower crane removal & N May,19-2018
Finish : Jul,06-2018
Scaffolding Removal (Start : Finish
Duration: Jul,06-2018
: 30 days)
April,30-2020 Duration
then we go: 30 days)
through
Finish : May,01-2020 Landscape (North
then we go through
Duration : 02 days) then we Side) starting
Landscape with
(North
go through Landscape (East Storm Tech. with
Side) starting with Lag
20 days
Side) Storm Tech. with
Start : Jul,07-2020
Start : May,04-2020 Lag 20 days
Finish : Aug,12-2020
Finish : Jul,29-2020 Start : Jul,07-2020
Duration : 25 days
Duration : 55 days Finish : Aug,12-2020
E Duration : 25 days
***Critical***