Chapter 2 Day 15.1
Chapter 2 Day 15.1
network design
https://www.youtube.com/watch?v=ZZK3tlVeDC4
PRODUCT DESIGN
Assemble chart
Cap
Fiber Packing
Stem
Bushing
Body
OPERATION PROCESS
CHART
https://www.youtube.com/watch?v=O6rlHOcslTs
PROCESS DESIGN
Determination of how the product is to be produced
◦ Who should do the processing? (Which part of the products should be made?)
◦ How the part will be produced?
◦ Which equipment will be used? (for the parts which will be made in-house)
◦ How long will it take to perform the operation?
Production methods are the most fundamental factor affecting the physical layout
PROCESS DESIGN
Within the process design, we need to consider following issues:
1. Process identification
- Make-or-buy analysis
- Parts identification
2. Process selection
- How the product will be made
(operations, equipment, raw material, etc.)
3. Process sequencing
- Production order.
PROCESS DESIGN
Make-or-buy decisions
The scope of the facility depends on the level of
vertical integration
Production selection is analyzed through a quantitative relationship graph which is Also known as P-Q
(Product-Quantity) analysis
SCHEDULE DESIGN
Volume-variety chart – Pareto law
• For products with n sequential operations, the expected number of units to start into
production at the first operation is shown (On: the required production volume for the final
product):
CALCULATION OF PRODUCTION
REQUIREMENTS
Hệ thống gồm 5 quá trình gia công nối tiếp
Cần 2000 sản phẩm từ hệ thống
Xác định năng suất đầu vào cho từng quá trình?
CALCULATION OF PRODUCTION
REQUIREMENTS
Calculating production requirements for assembled products
The final products are 02 assemblies requiring 03 components). calculating components requirements for assembled
products. The calculations required are also shown in this figure.
2. CALCULATIONS WITH REWORK.
𝐼2
Thus
Since
21
EXERCISE
CAPACITY PLANNING
ANALYSIS
A local manufacturing plant has three work station (as shown in the following figure) with two
machines operating in parallel in station A. In other word before processding station B, the
product can be processed in either one of the two machines in Station A
Station A
12 min/1
unit Station B Station C 6
12 min/1 min/1 unit
Station A unit
12 min/1
unit
a) Which station among the three is the bottleneck workstations
b) If the company operate 8 hours per day, 7 days per week, what is the capacity of this work cell
c) if you could increase the capacity of any one of three workstations, which one could you focus on? By how
much would you increase capacity of this workstation in unit hours
EXERCISES
Capacity planning process
4 ounces of meet per sandwich
25
200 24 loaves 5 min per
sandwich/p customer
ounces/hr in 4 hour
er hour
E[P(Q)]
28
REJECT ALLOWANCE
PROBLEM
REJECT ALLOWANCE
PROBLEMCalculating production quantities that will maximize profit
Probability distributions for the number of good castings (x) out of Q
30
REJECT ALLOWANCE
PROBLEM
Profit from producing Q castings, with exactly x being good
31
OPERATOR MACHINE CHART
0-0.5
0-0.1
1-1.5
1.5-2
1 min load 2-2.5
2.5-3
1 min unload 3-3.5
3.5-4
6 min automatic machince time 4-4.5
0,5 min inspection 4.5-5
5-5.5
0.5 min walking 5.5-6
6-6.5
6.5-7
7-7.5
7.5-8
OPERATOR MACHINE CHART
OPERATOR MACHINE CHART
a: concurrent activity time (e.g: loading and unloading
a machine)
b: independent operator activity time (e.g: walking,
inspecting, packing)
t: independent machine activity time (e.g: automatic
machining time)
n’: ideal number of identical machines to assign an
operator
m: number of identical machines assigned an operator
Tc: repeating cycle time
Io = idle operator time during a repeating cycle
Im = idle time for each machine during a repeating
cycle
34
OPERATOR MACHINE CHART
Machine chart operation
1 min load
𝑇 𝑐=
(( 𝑎 +𝑡 ) 𝑚 ≤𝑛 ′
𝑚 ( 𝑎 +𝑏 ) 𝑚 ≥𝑛 ′ 1 min unload
6 min automatic machince time
0,5 min inspection
0.5 min walking
OPERATOR MACHINE CHART
Machince assigment problem
1 min load
1 min unload
6 min automatic machince time
Let : the ratio of TC(n) to TC(n+1)
0,5 min inspection
0.5 min walking
36
1 min load
If <1: then TC(n) < TC(n+1), and n machines should be assigned; 0.5 min walking
If >1: then TC(n + 1) < TC(n), and n + 1 machines should be assigned;
If =1: then either n or n + 1 machines should be assigned.
E.x:
Suppose C0 = $15/ hour, Cm = $50/ hour.
Therefore, = 0.30 and = 0929.
Since < 1, two machines should be assigned to
an operator (example in fig. 2-18: 3 machines).
37
OPERATOR MACHINE CHART