Project Risk Management
Project Risk Management
-
Threat
RISK
CAN NEVER BE TOTALLY
ELIMINATED.
SHOULD BE ADDRESSED
PROACTIVELY AND CONSISTENTLY
THROUGHOUT THE PROJECT
3
PROJECT RISK MANAGEMENT
4- Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project 4.5 Monitor and Control Project 4.7 Close Project
Work Work or phase
4.4 Manage Project Knowledge 4.6 Perform Integrated Change
Control
5- Project Scope Management 5.1 Plan Scope Management 5.5 Validate Scope
5.2 Collect Requirements 5.6 Control Scope
5.3 Define Scope
5.4 Create WBS
6- Project Schedule Management 6.1 Plan Schedule Management 6.6 Control Schedule
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
7- Project Cost Management 7.1 Plan Cost Management 7.4 Control Costs
7.2 Estimate Costs
7.3 Determine Budget
8- Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9- Project Resource Management 9.1 Plan Resource Management 9.3 Acquire Resources 9.6 Control Resources
9.2 Estimate Activity Resources 9.4 Develop Team
9.5 Manage Team
10- Project Communications 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications
Management
11- Project Risk Management 11.1 Plan Risk Management 11.6 Implement Risk 11.7 Monitor Risks
11.2 Identify Risks Responses
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12- Project Procurement 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 6
Management
13- Project Stakeholder 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder 13.4 Monitor Stakeholder
Management Engagement Engagement
PLAN RISK MANAGEMENT
4. (EEF)
5. (OPA)
Timing Probability
Tracking Impact
Matrix
Funding Reporting
Format
Roles &
Responsibility Categories
Risk Stakeholders’
Strategy Risk appetite
Methodolog Definitions of
y RM Plan P&I
Implement risk response Risk response At the right time Agreed upon responses Contingency
owners reserves
11
Very High
High
Moderate
Low
Very Low
Probability Impact
Very Low Low Moderate High Very High
0.05 0.10 0.20 0.40 0.80
Strength
Weakness
Opportunity
Threats
Risks register
Summary identification Analysis Response
ID O/T Description of Risk Category Potential Owner Prob. Schedule Cost Quality Score Strategy Tactic Fallback
response
R1 T the probability of tech. call Site
worker xxxxx falls ambulance Engineer
and injured
19
PERFORM QUALITATIVE RISK
ANALYSIS
22
Probability Impact
Very Low Low Moderate High Very High
Very Low
Hierarchical charts
Bubble charts
ASSESSMENT OF OTHER RISK PARAMETERS
A short period indicates high Urgency Proximity A short period indicates high
urgency proximity.
Where a risk is
perceived as very
significant, propinquity is
high
Risks register
Summary identification Analysis Response
ID O/T Description of Risk Category Potential Owner Prob. Schedule Cost Quality score Strategy Tactic Fallback
response
R1 T the probability of tech. call Site M VL H L MH
worker xxxxx falls ambulance Engineer
and injured
Watch list 26
Perform Risk Quantitative Analysis
18k
ad
e
ex 10
40,000 , 60%
isti K
a l i ty
ng
qu
= 24 k
d
M
Go o
ac
0 %
0* 6
hi
4 00 0
ne
,
1 00 0 0 *
28k 40%=4
B ad Q k
uality
29
10,000 , 40%
REPRESENTATIONS OF UNCERTAINTY
33
Examines uncertainty of each project element affects the objective being examined WHEN all other elements are fixed.
INFLUENCE DIAGRAM
• INFLUENCE DIAGRAMS ARE GRAPHICAL
AIDS TO DECISION MAKING UNDER
UNCERTAINTY
PLAN RISK RESPONSE
• ESCALATE
• AVOID
• TRANSFER
• MITIGATE
• ACCEPT
RESPONSE STRATEGIES FOR OPPORTUNITIES
Escalate
Exploit
Share
Enhance
Accept
Risks register
Summary identification Analysis Response
ID O/T Description of Risk Category Potential Owner Prob. Schedule Cost Quality score Strategy Tactic Fallback
response
R1 T the probability of tech. call Site M VL H L MH Mitigate Safety Take him
worker xxxxx falls ambulance Engineer procedure to
and injured s hospital
pt e
Watch list
ce
ce ssiv
an
Ac Pa
42
SECONDARY RISK:
RISKS THAT ARISE AS A DIRECT
RESULT OF IMPLEMENTING A RISK
RESPONSE.
RESIDUAL RISK:
RISKS THAT REMAIN AFTER
AVOIDANCE, TRANSFER OR
MITIGATION RESPONSES HAVE BEEN
TAKEN. THIS ALSO INCLUDES MINOR
RISKS THAT HAVE BEEN ACCEPTED.
Implement Risk Responses
Inputs Tools & Techniques Outputs
1. Project manage. Plan 1. Expert judgment 1. Change request
•Risk management Plan
2. Interpersonal & teams skills 2. Project documents
2. Project documents •Influencing updates
•Lessons learned register • Issue log
•Risk register 3. Project management • Lessons learned
•Risk report information system register
• Project team
3. (OPA) assignments
• Risk register
• Risk report
MONITOR RISKS
AN EXAMINATION OF THE EFFECTIVENESS OF RISK RESPONSE PLANS AND THE PERFORMANCE OF THE
RISK OWNER.
WORKAROUND PLANS
UNPLANNED RESPONSES TO EMERGING RISKS THAT WERE PREVIOUSLY UNIDENTIFIED OR
UNEXPECTED.
QUESTIONS
48
1- ALL OF THE FOLLOWING ARE FACTORS IN THE ASSESSMENT OF
PROJECT RISK EXCEPT:
A. RISK EVENT
B. RISK PROBABILITY
C. AMOUNT AT STAKE
D. INSURANCE PREMIUMS
2- RISK TOLERANCES ARE DETERMINED IN ORDER TO HELP:
D ) CONTROL RISKS.
52
5- WHAT SHOULD BE DONE WITH RISKS ON THE WATCH LIST?
C. DOCUMENT THEM AND SET THEM ASIDE BECAUSE THEY ARE ALREADY
COVERED IN YOUR CONTINGENCY PLANS
54
7- IF A PROJECT HAS A 60% CHANCE OF A U.S. $100,000 PROFIT AND A 40% CHANCE
OF A U.S. $100,000 LOSS, THE EXPECTED MONETARY VALUE FOR THE PROJECT
IS:
A. $ 100,000 PROFIT
B. $ 60,000 LOSS
C. $ 20,000 PROFIT
D. $ 40,000 LOSS
8- IF A RISK EVENT HAS A 90% CHANCE OF OCCURRING, AND THE CONSEQUENCES
WILL BE U.S. $100,000, WHAT DOES U.S. $90,000 REPRESENT?
A. RISK VALUE
B. PRESENT VALUE
D. CONTINGENCY BUDGET
9- A PROJECT MANAGER HAS JUST FINISHED THE RISK RESPONSE PLAN FOR A U.S. $387,000
ENGINEERING PROJECT. WHICH OF THE FOLLOWING SHOULD BE PROBABLY DONE NEXT?
A. MITIGATION
B. TRANSFER
C. ACCEPTANCE
D. AVOIDANCE