Dist TX Failure Analysis and Strategy-Mt Kenya - May 2018
Dist TX Failure Analysis and Strategy-Mt Kenya - May 2018
Dist TX Failure Analysis and Strategy-Mt Kenya - May 2018
TRANSFORMER FAILURE
REDUCTION STRATEGY –
FAILURE TRENDS AND RISK
FACTORS
PRESENTED BY:-
JOHN K. KANAMPIU, Ag. CHIEF
ENGINEER S/STATION MAINTENANCE
CENTRAL OFFICE
CONTENTS
1. INTRODUCTION
2. FAILURE TRENDS
3. RISK FACTORS
4. MITIGATION MEASURES
5. ILLUSTRATIONS
1. INTRODUCTION
REGION ACTUAL
FOR
TOTAL
NUMBER OF
No of failed
txs per 100
Ranking
2017/18 TXS – by July transformers
2017 ()-Last FY
position
1 West Kenya 574 7126 8 (9) 7
% 8.4 5.3 6.8 2.8 10.5 6.0 7.8 22.7 7.4 22.4
GENERAL REMARKS
Most affected regions are West Kenya, North rift
and Nairobi south
The general trend is worsening with only 2 regions
showing signs of improvement
Regions have to carry out immediate field
interventions to reverse the trend.
One of the major causes of tx failures which needs
to be addressed urgently is the transformer
protection (Fuse grading and surge diverters). There
are adequate stock levels of fuses to address this.
Where surge diverters are no available arcing horns
can be properly adjusted to offer necessary
protection.
Central office to support the interventions by
providing the necessary resources
RISK FACTORS
RISK FACTOR PREVALENCE REMARKS
1 Install right size LV fuses 20 txs per weekly Regional Majority of failures are due to shorted/overrated fuses. The right fuse will save the tx and direct the
week O&M maintenance teams on the areas requiring corrective measures
incharge
2 Connect all vandalized surge diverter earths 10 txs per Weekly “ Ensure some protection against surges. Inspect all failed tx structures for priority action.
to earth mat correctly week
3 Ensure all transformers on terminal 5 per week Weekly ‘ Most of the transformers struck by lightning are on terminal structures without surge diverters and/or
structures have surge diverters and without proper earthing or
connected to earth mat correctly
4 Load balancing 10 txs per Monthly A good number of transformers are failing due to single phase imbalance as a result of heightened
connectivity exercise where the tendency to extend one single phase circuit to all customers is very
common. A number of customers in the grain basket regions have connected single phase phosho mills up
to 11HP (8.2KW). The source is mainly a 50KVA tx .
5 Carry out load checks at the peak of each 10 txs per Monthly This is the only way to identify overloaded transformers and those with load imbalance for corrective
transformer month action before they fail
6 Test and improve all the transformer 10 per month Monthly This is a very slow exercise which may require a team well trained and continuously on the program
earthing mats without distraction. Regional manager to facilitate
7 Maintain and reinforce all the LV network 10 per month Monthly Incidences are a guide to the risk factors the tx is exposed to. All the 10 most problematic txs should be
guided by the incidence reports. attended fully
8 Ensure no transformer is commissioned in 100% Report on all Cases of poorly installed s/stations are very common which are commissioned by Hiab drivers without the
the system with defects either on the newly presence of a supervisor.
structure or the LV network commissioned
txs per month
9. No transformer should be issued by the store 100% Stores to Transformers need to be inspected by a competent person before they leave the store and on site before
keeper to any other person other than a compliance enforce and give they are put on the structures. Cases of faulty txs being commissioned or txs being damaged or oil
competent supervisor and action should be a report on non- siphoned on transit have been noted.
taken on any supervisor sending a hiab driver compliance
to collect transformers from store monthly
10 All relevant reports are mandatory. These 100% Weekly reports The company has not been able to claim any compensation for failed transformers under the warranty
are:- compliance on failures and agreement due to failure to comply with the documentation procedures during commissioning and after
1. Failure reports replacements. failure of the transformer.
2. Commissioning reports
Action to be taken on the respective
supervisors for non-compliance.
OTHER LONG TERM MITIGATION MEASURES
Investigate all cases of fuse blowing and rectify
Carry out regular load checks at peak load
Earth the surge diverters properly
Protect the earth leads against vandalism
Inspect s/stations regularly to identify cases of
vandalism
Check and ensure earth values are correct
Ensure loads are balanced on 3-phase
transformers. Raise reinforcement schemes to
balance the loads
Raise reinforcement schemes to correct
overextended lv lines
Ensure no sub-standard construction is accepted
in the network
MITIGATION MEASURES CONTD.
Ensure number of lv circuits as per
construction standards
Replace 3-phase transformers in rural areas
with single phase where applicable
Correct all transformer oil leakages as soon
as identified
Replace all LV leads with burnt insulation
Use the correct termination accessories
Ensure all transformers have fuse carriers
Ensure the wiring is neat and colour coded
ILLUSTRATIONS
END
Presented by :
John K Kanampiu
Ag. Chief engineer, S/Station maintenance,
Network Management