Day 4 Esp System Start-Up, Commissioning and Operation - Last
Day 4 Esp System Start-Up, Commissioning and Operation - Last
FRC & Hot Gloves: which should be worn by the Engineer to confirm the
Power Isolation
OAA remove all the tags and then open all x-mass tree valves in order to Run the ESP
Downhole parameter set point (high Pd set, low Pd set, high Pi set, low Pi set, Ti set, Tm set, Vx
Vy,)
Going to calculation sheet to find :
415
6
.
related to calculation sheet:
Find: Secondary volts @ max Hz 2730 + Cable Drop 120 = 2850 +/- 10%
In case we have VSD Filter we should use filter factor=1.067 (in BHI Case)
as know VSD Vout = 415 and transformer in put need V= 480 and this issue can solve
with Input power ratio
8
9
it is important to find Xfmr (transformer ratio)
Overload trip (OLT) is intended to shutdown an electric motor when the operating
current exceeds a nominal current; the aim is to prevent overheating and
breakdown of the stator winding.
10
Setting-up of voltage drop protection should be performed in order to
stabilize ESP system operation.
No-load test
Disconnect cables of Transformer, Downhole and
run the VSD with no-load to ensure there are no
issue with our VSD set up (run at F=30 Hz and
then increase it to 60 Hz).
RTU communication
Confirm RTU communication
with client team.
ES P S ta rt
90
3000
80
Firs t Ind ica tio n Bo th P re s s ure s d e cre a s e
o f Flo w
70
2500
60
Ta ke No te o f S hut-In S uctio n
P re s s ure
50 2000
Co ntro lling P re s s ure
with Cho ke
40
1500
30
20
1000
10
0 500
14 Curre nt We llhe a d Te mp e ra ture We llhe a d P re s s ure Inta ke P re s s ure Dis cha rg e P re s s ure
with first rotation we should monitor value of Pd with Pi, as shown in pervious fig. we
noticed that Pd reduce to the value of Pi, which mean we are in wrong rotation.
after 10 min. we SD the ESP and then;
ESP Start
90
3000
80
First Indication of Flow
70
Check Pressure has Equalised 2500
60
50 2000
Controlling Pressure with Choke
40
1500
30 Min 30 Minute wait
20
1000
10
0 500
15
Send ESP parameters to Application engineer.
Start optimization to ensure that ESP is running inside ROR. Set the VSD
alarms and downloaded the data log
Perform Housekeeping to the Well Site and confirm that work site is safe,
clean and all equipment are arranged properly.
16
17