Chapter 5 Present Worth Analysis
Chapter 5 Present Worth Analysis
Present-Worth Analysis
Nature of Project:
Federal Express
Ultimate Questions
Is it worth investing $150 million to save $20 million per year, say over 10 years?
Interest + Repayment
Investment Project (project cash flow)
Investment
Company Project
Return
Loan versus project cash flows
• Fixed assets – similar to an investment made by a bank, when its lends money
• Fixed assets - future return takes the form of cash generated by productive use of the asset
• Future earnings along with the capital expenditure and annual expenses is the project cash flow
• Annual expenses : such as raw materials, operating costs, maintenance costs, income taxes.
Payback period - screens projects on the basis of how long it takes for net receipts to equal investment outlays
The payback period is calculated by adding the expected cash flows for each year until the sum is equal to or greater than
zero.
The cumulative cash flows equal zero at a point where cash inflows exactly match or payback, the cash outflows; thus the
project has reached the payback point.
once the cumulative cash flows exceed zero, the project has begun to generate a profit.
This calculation can take one of two forms by either ignoring time value of money consideration or including
them.
The former(ignoring time value of money) case is usually designated – conventional pay back method
High-tech firm : such as computer chip manufacture would set a short time limit for any new investment,
because high-tech products rapidly become absolute.
Initial Project Screening Methods
When the money invested in a project can be
recovered ??
Principle:
How fast can I recover my initial investment?(Once the cumulative cash flows exceed zero, the project has
begun to generate a profit)
Method:
Based on cumulative cash flow (or accounting profit)
Screening Guideline:
If the payback period is less than or equal to some specified payback period, the project would be
considered for further analysis.
Weakness:
Does not consider the time value of money
Example 5.1 Conventional Payback Period with Salvage Value
0 -$105,000+$20,000 -$85,000
1 $35,000 -$50,000
2 $45,000 -$5,000
3 $50,000 $45,000
4 $50,000 $95,000
5 $45,000 $140,000
6 $35,000 $175,000
$85,000
150,000
Cumulative cash flow ($)
0
-50,000
-100,000
0 1 2 3 4 5 6
Years (n)
Example :
Machining and turning centre - Mazak multi tasking machine centre
0 -$1800000 $1800000
1 $454,000 -$1,346,000
2 $681,000 $665,000
3 $908,000 $243,000
4 $908,000 $1,151,000
5 $908,000 $2,059,000
6 $908,000 $2,967,000
7 $1,268,000 $4,235,000
0 -$1800000 0 -$1800000
Net-Present-Worth Criterion
A0 A1 A2 AN
PW (i ) ...
1 i 1 i 1 i 1 i
0 1 2 N
N
An N
An P F , i, n
1 i
n
n 0 n 0
Present Worth Analysis
Step 7: Positive NPW means that the equivalent worth of the inflows is more than the
equivalent worth of the outflows, so project makes a profit. It means,
PW is positive Project is accepted
PW is negative Project is rejected
Decision Rule:
If PW(i) > 0, accept the investment
If PW(i) = 0, remain indifferent
If PW(i) < 0, reject the investment
Example 5.3 - Tiger Machine Tool Company
Net Present Worth – Uneven Flows
inflow
$55,760
$24,400 $27,340
0
1 2 3
outflow
$75,000
Consider the multi-tasking machine center investment project. Recall that the required initial investment of $1,800,000 and the projected cash
savings over a seven year project life are as follows. You have been asked by the president of the company to evaluate the economic merit of
the acquisition. The firms MARR is known to be 15% per year.
End of Cash flow
year Given: MARR = 15% per year
0 -$1800000
Find NPW?
1 $454,000
PW(15%) = -$1800000 +
2 $681,000
$454,000 (P/F, 15%, 1) +
3 $908,000
$681,000 (P/F, 15%, 2) +
4 $908,000
$908,000 (P/A, 15%, 4) (P/F, 15%, 2) +
5 $908,000
$1,268,000 (P/F, 15%, 7)
6 $908,000
= $1,546,571
7 $1,268,000
$1,268,000
$908,000
$681,000
$454,000
0 1 2 3 4 5 6 7
= $3,346,571
0
1 2 3
$75,000
Project life
Future Worth Criterion
PW (i) ($ thousands)
10
$3553 17.45%
0
-10
-20
-30
0 5 10 15 20 25 30 35 40
i = MARR (%)
Investment Pool Concept
• Suppose the company has $75,000. It has two options.
(1)Take the money out and invest it in the project or
(2) leave the money in the company.
Mutual funds are among the best-known of pooled funds. Actively managed by professionals, unless they are index funds, they spread their
holdings across various investment vehicles, reducing the effect that any single or class of securities has on the overall portfolio.
Because mutual funds contain hundreds or thousands of securities, investors are less affected if one security underperforms.
Another type of pooled fund is the unit investment trust. These pooled funds take money from smaller investors to invest in stocks, bonds, and
other securities. However, unlike a mutual fund, the unit investment trust does not change its portfolio over the life of the fund and invests for
a fixed length of time.
Project
Balance -$75,000 -$61,850 -$43,788 +$5,404
Net future worth, FW(15%)
PW(15%) = $5,404 (P/F, 15%, 3) = $3,553
Project Balance Diagram
60,000
Terminal project balance
40,000 (net future worth, or
project surplus)
20,000
Project balance ($) $5,404
0
Discounted
-20,000 payback period
-$43,788
-40,000
-60,000 -$61,850
-$75,000
-80,000
-100,000
-120,000
0 1 2 3
Year (n)
Guidelines for selecting a MARR :
Conceptually, the rate of return that we realistically expect to earn on any investment is a function of three components.
Investment pool :
investments that yield a return equal to MARR, We may view these funds as an investment pool.
Alternatively, if no funds are available for investment, we assume that the firms can borrowed them at MARR from the capital markets.
An investment pool is equivalent to firms treasury. Its where all fund transaction are administered and managed by the firms controller or comptroller.
Example:
Option 1:
If the firm did not invest in the project and instead left the $1,800,000 in the investment pool for seven years, these funds would have grown as follows.
$1,800,000(F/P, 15%, 7) = 4,788,000
Suppose the company did decide to invest $1,800,000 in the project.
since, the funds that return to the investment pool earn interest at a rate of 15%, it
End of year (n) Cash flow()
would be helpful to see how much the would benefit from this investment.
1 $454,000
for this alternative, return after reinvestment are as follows:
2 $681,000
$454,000 (F/P, 15%, 6) + = $1,050,130 +
3 $908,000
$681,000 (F/P, 15%, 5) + = $1,369,734 +
4 $908,000
$908,000 (F/A, 15%, 4) (F/P, 15%, 1) + = $5,214,082 +
5 $908,000
$1,268,000 (F/P, 15%, 0) = $1,268,000
6 $908,000
this $4,113,910 surplus is also known as net future worth of the project at the project termination.
If we compute the equivalent present worth of this net cash surplus at time “0”
End of year(n) 0 1 2 3 4 5 6 7
Beginning Project balance 1800000 1616000 1177400 446010 -395089 -1362352 -2474705
payment received 1800000 454000 681000 908000 908000 908000 908000 1268000
project balance 1800000 1616000 1177400 446010 -395089 -1362352 -2474705 -4113910
Do-Nothing Alternative
When considering an investment, we are in one of two situations: Either the project is aimed at replacing an existing
asset or system, or it is a new attempt. If a process or system already in place to accomplish our business objectives is
adequate, then we must determine which, if any, new proposals are economical replacement. If none are feasible, then
we do nothing. If the existing system has failed, then the choice among proposed alternatives is mandatory (i.e., do
nothing is not an option).
Revenue Projects
are projects that generate revenues that depend on the choice of alternative that we want to select the alternative with the
largest net gains
Service Projects
are projects that generate revenues that do not depend on the choice of project, but must produce the same amount of
output (revenue) with lower production cost.
Analysis Period is the time span over which the economic effects of an investment will be evaluated.
The study (analysis) period, sometimes called the planning horizon, is the selected time period over which Mutually
Exclusive alternatives are compared.
Factors influence the decision are; the required service period, the useful life of the shorter lived alternative, the useful lived
of the longer lived alternative, company policy and so on.
One convenient choice of analysis is the period of the useful life of the investment project.
Comparing Mutually Exclusive Projects
= -362,007
= -364,131
Case 2: Project lives shorter than the
analysis period (Example 5.7)
$2,000
0 1 2
3 4 5
Model A
$5,000 $5,500
$6,000 Required Service
$1,500 Period = 5 years
$12,500
1 2 3
0 4 5
$15,000
PW(15%)A = -$35.929
PW(15%)B = -$33,173
= -$12,500 - $5,000(F/P, 15%, 4) …….F=P(1+i)^N = 1.749
- $5,000(F/P, 15%, 3) …………………….= 1.521
- $6,000(F/P, 15%, 2) ……………….. = 1.322
+$2,000 (F/P, 15%, 2) …………………= 1.322
= - 34,898
Ansell , Inc., a medical device manufacturer, uses compressed air in solenoids and pressure switches in its machines to control various
mechanical movements. Over the years, the manufacturing floor layout has changed numerous times. With each new layout, more piping was
added to the compressed air delivery system in order to accommodate new locations of manufacturing machines. None of the extra unused old
piping was capped or removed; thus the current compressed air delivery system is inefficient and fraught with leaks. Because of the leaks in the
current system, the compressor is expected to run 70% of the time that the plant will be in operation during the upcoming year. The compressor
will require 260kw of electricity at a rate of $0.05/kwh. The plant runs 250 days a year, 24 hours per day. Ansell may address this issue in one of
two ways.
Option 1: Continue current operation. If Ansell continues to operate the current air delivery system, the compressors run time will increase by
7% per year for the next five years because of ever-worsening leaks.(After five years, the current system will not be able to meet the plants
compressed air requirement so it will have to be replaced)
Option 2: Replace old piping now. If Ansell decides to replace all of the old piping now, new piping will cost $28,570. The compressor will still run
for the same number of days; however, it will run 23% less(or will incur 70%(1-.23)=53.9% usage per day) because of the reduced air-pressure
loss.
If Ansell's interest rate is 12% compounded annually, is it worth fixing the air delivery system now?
Cost of power consumption = % of day operating * days operating per year * hours per day * kw * $/kwh.,
Each year, if the current piping system is left in place, the annual power cost will increase at the rate of 7% over the previous cost.
= $54600 [
= $222,937
Option 2:
If Ansell replaces the current compressed air delivery system with the new one(23% less during the first year, will remain at that level over
the next five year)
= $151,553
After eight years the converted building will be too small for efficient production of either product line. At that time, Monroe's plans to use it as a warehouse
for storing raw materials as before. Monroe's required return on investment is 15%. Which product should be manufactured?
= $42,544
= $50,407.
Project lives longer than the Analysis period:
Allen company got permission to harvest southern pines from one of its timber land tracts. Its considering purchasing a feller buncher, which has the ability to
hold saw, and place trees in bunches to be skidded to the log landing. The logging operation on this timberland track must be completed in three years. Allen
could speed up the logging operation but doing so is not desirable because the market demand of the timber does not warrant such haste. Because the logging
operation is to be done in wet conditions, this task requires a specially made feller-buncher with high-flotation tires and other devices designed to reduce site
impact. There are two possible models of feller-buncher that Allen could purchase for this job. Model A is a two year old used piece of equipment where as
Model B is a brand-new machine.
Model A costs $205,000 and has a life of 10,000 hours before it will require any major overhaul. The operating cost will run $50000 per year for 2000 hours of
operation. At this operational rate, the unit will be operable for five years, and at the end of that time, its estimated that the salvage value will be $75000.
The more efficient model B costs $275000 has a life of 14000 hours before requiring any major overhaul and costs $32500 to operate for 2000 hours per year in
order to complete the job within three years. The estimated salvage value of model B at the end of seven years is $95000.
Since, the life time of either model exceeds the required service period of three years, Allan company has to assume some things about the used equipment at the
end of that time. Therefore, the engineers at Allen estimate that after three years, the model A unit could be sold for $130000 and the model B unit for $180,000.
After considering all tax effects, Allan summarized the resulting cash flows for the projects as follows.
Period Model A Model B
0 -$205,000 -$275,000
1 -50,000 -32,500
2 50,000- -32,500
3 130,000 50,000- 180,000 -32,500
4 50,000- -32,500
5 75000 50,000- -32,500
6 -32,500
7 95,000 -32,500
Here, the figures in the boxes represent the estimated salvage values at the end of the analysis period(end of year 3). Assuming that the firms MARR is 15%,
which option is more acceptable?
With this scenario, which option should the firm select at MARR = 12%?
Since each option has a shorter life than the required service period (10Years), we need to make an explicit assumption of how the service requirement is to be met.
If the company goes with the conveyor system, it will spend $18,000 to overhaul system to extend its service life beyond eight years. The expected salvage
value of the system at the end of the required service period (10 years) will be $6000. The annual operating and maintenance cost will be $15,000.
If the company goes with the Lift truck option, the company will consider leasing a comparable lift truck that has an annual lease payment of $8000, payable at the
beginning of each year, with an annual operating cost of $13,000 for the remaining required service period.
= -$205,000 -$15,000 (P/A, 12%, 10) -$18,000 (P/F, 12%, 8) + $6,000 (P/F, 12%, 10)
= -$205,000 -$15,000 [ - 1)/ -$18,000 + $6,000
= -$295,088
= -$275,000 -$13,000 (P/A, 12%, 10) -$8,000 (P/A, 12%, 4) (P/F, 12%, 5) + $4,000 (P/F, 12%, 6)
= -$275,000 -$13,000 [ - 1)/
-$8,000 + $6,000
= -$347,800.710
Since, these projects are service projects, the conveyor option is the better choice.
5:14: You have been asked to evaluate the profitability of building a new distribution center under the following conditions:
# The proposal is for a distribution center costing $1,500,000. The facility has an expected useful life of 35 years and a net salvage value(net proceeds from its
sale after tax adjustments) of $225,000.
# Annual savings(due to a better strategic location) of $227,000 are expected, annual maintenance and administrative costs will be $114, 000 and annual income
taxes are $43,000.
Suppose that firms MARR is 12%. Determine the net present worth of the investment.
Given:
Center costing = $1500,000
Life 35 years
Salvage value = $225,000
Maintenance and operating cost = $114,000
Annual savings = $227,000
Income tax = $43,000
MARR = 12%
NPW ==?
PW(12%) = -$1,500,000 + $70,000(P/A, 12%, 34) + $295,000(P/F, 12%, 35)
= -$1,500,000 +
$70,000[
= -923,443.2434
5:15: You are considering the purchase of a parking deck close to your office building. The parking deck is a 15 year old structure with an estimated remaining
service life of 25 years. The tenants have recently signed long term leases, which leads you to believe that the current rental income of $250,000 per year will
remain constant for the first five years. Then the rental income will increase by 10% for every five year interval over the remaining asset life. Thus the annual
rental income would be $275,000 for years 6 through 10, $302,500 for years 11 through 15, $332,750 for years 16 through 20, and $336,025 for years 21 through
25. You estimate that operating expenses, including income taxes, will be $65000 for the first year and that they will increase by $6000 each year thereafter. You
estimate that razing the building and selling the lot on which it stands will realize a net amount of $200,000 at the end of the 25 year period. If you had the
opportunity to invest your money elsewhere and thereby earn interest at the rate of 15% per annum, what would be the maximum amount you would be willing
to pay for the parking deck and lot at the present time?
Given :
Estimated remaining service life = 25 years,
Current rental income = $250,000 per year,
Operating and maintenance costs = $65,000 for the first year increasing by $6000 thereafter,
Salvage value = $200,000
MARR = 15%
PW(15%) = $250,000(P/A, 15%, 5) +
$275,000(P/A, 15%, 5) (P/F, 15%, 5) +
$302,500(P/A, 15%, 5) (P/F, 15%, 10) +
$332,750(P/A, 15%, 5) (P/F, 15%, 15) +
$366,025(P/A, 15%, 5) (P/F, 15%, 20) +
$65,000(P/A, 15%, 25) - $6000(P/G, 15%, 25) + $200,000(P/F, 15%,25) = $1,116,775
5: 20: Consider the following sets of investment projects, each of which has a three year investment life:
4 -$2000 -$2000
Assuming a common service period of 15 years 5 -$2000 -$2000
Project A:
$34,151
Project B with 4 replacement cycles where the 4 th replacement cycle ends at the end of first operating year:
n Model A Model B
0 -$150,000 -$230,000
Given :
1 -$55,000 -$30,000
Cash flow for Model A, Model B
2 -$55,000 -$30,000
i=15% compounded annually
3 -$55,000 +$15,000 -$30,000 Find AE cost and which model is the preferred alternative.
4 -$30,000
5 -$30,000 +$35,000
Model A: for a three year period (first cycle)
PW(15%) = -$150,000 - $55,000 (P/A, 15%, 3) + $15,000 (P/F, 15%, 3)
= -$265,715
AEC(15%) first cycle = -$265,715 (A/P, 15%, 3) = $116,377
for 15 year period (five replacement cycle)
PW(15%) = -$265,715 [1 + (P/F, 15%, 3) + (P/F, 15%, 6) + (P/F, 15%, 9) + (P/F, 15%, 12)]
=-$680,499
Model B:
0 1 2 3 4
$2,500
$4,000 $4,000 $4,000
$15,000
Model A:
0 1 2 3
$3,000
$5,000 $5,000
$12,500
• First Cycle:
PW(15%) = -$12,500 - $5,000 (P/A, 15%, 2) - $3,000 (P/F, 15%, 3)
= -$22,601
AE(15%) = -$22,601(A/P, 15%, 3) = -$9,899
• With 4 replacement cycles:
PW(15%) = -$22,601 [1 + (P/F, 15%, 3) + (P/F, 15%, 6) + (P/F, 15%, 9)]
= -$53,657
AE(15%) = -$53,657(A/P, 15%, 12) = -$9,899
Model B:
0 1 2 3 4
$2,500
• First Cycle:
PW(15%) = - $15,000 - $4,000 (P/A, 15%, 3) - $2,500 (P/F, 15%, 4)
= -$25,562
AE(15%) = -$25,562(A/P, 15%, 4) = -$8,954
• With 3 replacement cycles:
PW(15%) = -$25,562 [1 + (P/F, 15%, 4) + (P/F, 15%, 8)]
= -$48,534
AE(15%) = -$48,534(A/P, 15%, 12) = -$8,954
0 1 2 3
$4,000
4 5 6
$5,000
$5,500
$12,500
$4,000 7 8 9
$5,000
$5,500
$12,500
Model A $4,000
10 11 12
$5,000
$5,500
$12,500
$4,000
$5,000
$5,500
0 1 2 3 4
$12,500
$4,000
5 6 7 8
$4,000
$4,500
$5,000
$4,000
$15,000
9 10 11 12
$4,000
$4,500
$5,000
$15,000 $4,000
Model B $4,000
$4,500
$5,000
$15,000
5:51: An electric utility company is taking bids on the purchase, installation, Cost per Tower
and operation of microwave towers:
Bid A Bid B
Which is the most economical bid if the interest rate is 11%? Both towers will have no salvage Equipment cost $65000 $58,000
value after 20 years of use. Installation cost $15,000 $20,000
Annual maintenance and inspection fee $1,000 $1,250
Since either tower will have no salvage value after 20 years, we may select the analysis Annual extra income taxes $500
period of 35 years: Life 40 years 35 years
Salvage value $0 $0
PW(11%) Bid A $80, 000 $1, 000( P / A,11%,35)
$88,855
PW(11%) Bid B $78, 000 $1, 750( P / A,11%,35)
$93, 497
Bid A is a better choice.
If we assume an infinite analysis period, the present worth of each bid will be
[$80,000 $1,000( P / A,11%, 40)]( A / P,11%, 40)
PW(11%)Bid A
0.11
$90,341
$93, 497( A / P,11%,35)
PW(11%)Bid B
0.11
What is a Bid. $95,985
Bid A is still preferred.
The term bid refers to an offer made by an individual or corporation to purchase an asset. Buyers commonly make bids at auctions and in various markets, such as the stock
market. Bids may also be made by companies that compete for project contracts. When a buyer makes a bid, they stipulate how much they're willing to pay for the asset along with
how much they are willing to purchase. 1
A bid also refers to the price at which a market maker is willing to buy a security. But unlike retail buyers, market makers must also display an ask price.
Multiple Alternatives. The approach we discussed earlier to compare between two alternatives can be extended to more than two alternatives. Just compute the
NPW of each alternative, and then pick the one with the best NPW. Comparing Alternatives
Example. A contractor must build a six-miles-long tunnel. During the five-year construction period, the contractor will need water from a nearby stream. He
will construct a pipeline to carry the water to the main construction yard. Various pipe diameters are being considered.
Pipe diameter
The salvage value of the pipe and the cost to remove them may be ignored.
The pump will operate 2,000 hours per year.
The lowest interest rate at which the contractor is willing to invest money is 7%.
(This is called the minimum attractive rate of return, abbreviated as MARR.)
We compute the present worth of the cost for each alternative.
This cost is equal to the installed cost of the pipeline and pump, plus the present worth of five years of pumping costs.
Pumping costs:
2” pipe: 1.2 (2000) (P/A,7%,5) = 1.2 (2000) (4.100) = $9,840.
3” pipe: 0.65 (2000) (4.100) = $5,330
4” pipe: 0.50 (2000) (4.100) = $4,100.
6” pipe: 0.40 (2000) (4.100) = $3,280.
PW of all costs:
2” pipe: $22,000 + $9,840 = $31,840 30
3” pipe: $23,000 + $5,330 = $28,330
4” pipe: $25,000 + $4,100 = $29,100
6” pipe: $30,000 + $3,280 = $33,280.
Select the 3 in. pipe size since it the alternative with the least present worth of cost.
Example
An investor paid $8,000 to a consulting firm to analyze what to do with a parcel of land on the edge of town that can be bought for $30,0000. The consultants
suggest four alternatives (shown in the following table) An investor always has the alternative to do nothing. It is not too exciting, but may be better than other
choices.
A Do nothing $0 $0 $0
B Vegetable market $50,000 $5,100 $30,000
The problem is one of neither fixed input nor fixed output. So, our criterion will be to maximize the present worth of benefits minus the present worth of cost; i.e.
maximize the net present worth (NPW)
Alternative A: do nothing, NPW = 0
Alternative B: Vegetable market
NPW = -50,000 + 5,100 (P/A,10%,20) + 30000 (P/F,10%,20)
= -50,000 + 5,100 (8.514) + 30000(0.1486) = - 50,000 + 43,420 + 4,460 = - $2,120.
Alternative C: Gas station
NPW = -95000 + 10500 (P/A,10%,20) + 30000 (P/F,10%,20)
= -95,000 + 10500 (8.514) + 30000(0.1486) = - 95,000 + 9,400 + 4,460 = - $1,140.
Alternative D: Small motel
NPW = -350,000 + 36000 (P/A,10%,20) + 150000 (P/F,10%,20)
= -350,000 + 36000 (8.514) + 150000(0.1486) = - 350,000 + 306,500 + 23,290 = - $21,210
Important note. The $8,000 the investor spent for consulting services is a past cost, and is called a sunk cost. The only relevant costs in the economic analysis are
present and future costs. Past events and past costs are gone and cannot be allowed to affect future planning.
The authors do not mention it, but the sort of analysis the consultants did to provide the table was probably very approximate. Predicting the future is always
very tricky