Proposed Apartment - : Sankalp Imperial House at Mysuru
Proposed Apartment - : Sankalp Imperial House at Mysuru
Proposed Apartment - : Sankalp Imperial House at Mysuru
Presented by : MOHAMMED
AYAN
(intern at SANKALP BUILDERS, SAMRAJ
CONSTRUCTION)
INTRODUCTION
Material excavated from the earthwork should not be made to deposit nearer to
the excavation that is, lead at least 1m away from the excavated trench .
The sides of the excavation may be cut sloping, or shored or stepped to hold the
face of earth as per site requirements
Chemical is sprayed on surface of excavated ground to prevent the attack of termites as shown in
figure below.
While carrying the excavation, an engineer’s role is to prepare checklist as per the work carried.
If the hard strata is to be found deeper than the specified depth concrete soling should be carried out
under the guidance of senior engineer
CHECKLIST FOR EXCAVATION
LAYING OF PCC
Calculation of required quantity of plain cement concrete to be ordered.
The first observation while conducting the PCC is to maintain level which is marked through Total
station
The PCC should be laid as per the excavated profile which acts as bed concrete ,which is also called as
mud mat.
While laying of PCC the thickness of the bed concrete should be maintained uniformly ,as per
thickness mentioned in drawings.
After PCC bed has hardened the marking for column footing can be done.
The bars crossing each other must be tied together at every intersection with two strands of annealed steel
wire of 0.9 to 1.6 mm thickness twisted tight to make the skeleton of the steelwork rigid so that the
reinforcement does not get displaced during deposition of concrete.
The main bars in footing should be placed along shorter direction and distribution bars along longer
direction.
In the case of column construction, precast cover blocks of cement mortar 1:2 about 4x4 cm section and
of thickness equal to the specified cover shall be placed between the bars and shutters, so as to secure
and maintain the requisite cover of concrete over reinforcement.
In the case of retaining wall raft or footing raft, the vertical distance between the horizontal bars shall be
maintained by introducing chairs or support bars of steel.
Calculation and inspection of number of bars as per the reinforcement details provided in drawing.
Also checking lateral ties (4,5,6 legged stirrups) and number of hooks ,rings in a pedestal column as per
drawings. The number of bars in a column and dia of each bar should be checked before placing of
reinforcement.
The duck leg length should be of minimum of 300mm.
Proper stagging should be maintained by carrying each length of bar accordingly prepared
initially before formation of column.
The lateral ties ring should be laid alternately should also be checked by an engineer.
The lateral ties ring should be bend at 135 degree ,90 degree bend should be rejected.
Shuttering oil should be avoided in contact of reinforcing bars to maintain better bonding between
concrete and steel.
FOOTING AND COLUMN SHUTTERING
LAYING OF CONCRETE
TRANSPORTING OF CONCRETE: The concrete was transported to site through transit mixer with an average capacity
of 5-6 m3 .which was ordered at a cost of 4700 per m 3.
TEST CONDUCTED: Slump cone test and casting of cube
METHOD OF COMPACTION: The needle vibrator of dia 40 and 60mm .
CONDUCTION OF CUBE TEST ON CONCRETE.
CUBE TEST USING CTM
CHECKLIST
DE SHUTTERING AND
CURING
BACK FILLING WITH COMPACTION
PLINTH BEAM
Plinth beam is a beam that rests on the foundation wall. The Plinth
beam carries and transfers the supper structure and external load to the
foundation columns. The plinth beam is the structure which divides the
building into two parts that is superstructure and sub-structure. The
difference of Plinth beam to that of structural beam is that grade beam
does not suspend as structural beam, instead it rests on foundation
masonry wall.
1. Levelling .
3. Oiling.
1. Leveling:
The most important thing is to check the level of centering many times, the slab is very long, so it must be smooth and
leveled on every part.
We check the centering of the slab through following method which were adopted.
a) Set the Main level.
Known as the TBM (Temporary benchmark level) - This level was carried by surveyor.
Ref. of SSL
Measure the plywood level to the marking (in the fig) and repeated it with all the columns and rods.
When plywood is laying in different pieces, tape the joints' opening in the centering.
a) When concrete is pouring into the slab, water will leak out from the holes.
b) Water cement ratio plays a significant role in the slab centering checklist as it is important to maintain
the slurry's water cement ratio. So to save the ratio, voids are to be filled with the tapping.
3. Oiling in slab centring:
BEAM REINFORCEMENT
The following were the observations made while placing of reinforcement of beams:-
Before placing of reinforcement the observation of centering and shuttering, whether the
supports are safe to withstand the load of steel and concrete over it should be checked by the
engineer.
After calculation of BBS of beam the calculated amount of steel should be provided under
the guidance of senior engineer.
In case of cantilever and overhanging beams the necessary prop should be provided at its
end support.
All grade of steel in our site was Fe-500 for beams and grade of concrete M-25 only for
Ground floor roof beam drawings.
Development length for main bars Ld= 50d.
Providing 20mm upward camber at the beam center for the span of
8m and above.
In case of arch shape beams the arch radius should be fixed with a
steel segment which is prepared accordingly with respect to their
beam details(size).
In case of, sunken slab beam the tower beam size shall be
200x600mm unless specified.
The ring portion in the lateral stirrups in the beam section should be
placed alternatively.
The ring portion of the stirrup should be placed in compression zone that
is at the top of beam.
For all one-way slab the main bar of dia 10mm @ 125mm C/C along
shorter direction, distribution reinforcement of dia 8mm @ 175mm
C/C.
For all two-way slab the main reinforcement of dia 10mm @ 150mm
During slab reinforcement, first the bottom bars was placed to their respective spacing..
The U-bars in sunken slab of dia 8mm @100mm C/C should be placed.
The pouring of concrete was lead through pumps and pipes with a horizontal straight and level pipeline for a distance of about 100m at a vertical height up to 9m for first floor roof slab.
FINISHING OF CONCRETE
Finishing of compacted concrete slabs were done with following operations.
1.Screeding: The levelling operations that removes humps and hollows and gives a true uniform concrete
surface is called as screeding or removal of excess quantity of concrete is called as screeding. This is done
with a template known as screed.
2.Floating: The process of removing the irregularities from the surface of concrete lift after screeding is
called floating. The floating is done with the help of wooden float.
3.Trowelling: The final operation of finishing is called troweling. In most cases the troweling is carried
for plastic concrete with the help of trowel.
METHOD OF CURING:
Curing by ponding
DESHUTTERING OF BEAMS AND SLAB
RCC slab centering removal time :
During these past eight weeks of internship, I have been able to see the different
theoretical aspects. methodologies. I have been fulfilling our curiosity in
learning practically building construction well in this internship program.
Generally, the internship program laid sound foundation for me to start my
career.
THANK YOU