Lecture 3 - Introduction To Management
Lecture 3 - Introduction To Management
Introduction to
Management Science
Chapter 1 in the textbook
2. Problem solving
process identifying a difference between actual and the
desired state of affair
Takes action to resolve the difference
Evaluate the
alternatives
Single-criterion Multicriterion
decision problems decision problems
Analog models
- physical in form, but do not physically resemble the
object being modeled
Mathematical models
- represent real world problems through a system of
mathematical formulas and expressions based on key
assumptions, estimates, or statistical analyses
DR. NOR KHAIRUSSHIMA 10
ADVANTAGES OF MODELS
1. Generally, experimenting with models (compared
to experimenting with the real situation):
requires less time
is less expensive
involves less risk
2. Constraints
a set of restrictions or limitations, such as production capacities
Example :
5x ≤ 40
x≥0
DR. NOR KHAIRUSSHIMA 12
MATHEMATICAL MODELS
3. Uncontrollable Inputs
environmental factors that are not under the control of
the decision maker
4. Decision Variables
controllable inputs; decision alternatives specified by the
decision maker, such as the number of units of Product X
to produce
Uncontrollable Inputs
(Environmental Factors)
Controllable
Mathematical Output
Inputs
Model (Projected Results)
(Decision Variables)
Answer:
Management science can provide a structured,
quantitative approach for determining the minimum
project completion time based on the activities' normal
times and then based on the activities' expedited
(reduced) times.
DR. NOR KHAIRUSSHIMA 18
EXAMPLE: PROJECT
SCHEDULING
Question:
What would be the uncontrollable inputs?
Answer:
Normal and expedited activity completion times
Activity expediting costs
Funds available for expediting
Precedence relationships of the activities
Objective function:
- minimize project completion time
Constraints
- do not violate any activity precedence relationships and do
not expedite in excess of the funds available. 20
DR. NOR KHAIRUSSHIMA
EXAMPLE: PROJECT
SCHEDULING
Question:
Is the model deterministic or stochastic?
Answer:
Stochastic. Activity completion times, both normal
and expedited, are uncertain and subject to variation.
Activity expediting costs are uncertain. The number of
activities and their precedence relationships might change
before the project is completed due to a project design
change.
Question:
Suggest assumptions that could be made to simplify
the model.
Answer:
Make the model deterministic by assuming normal and
expedited activity times are known with certainty and are
constant. The same assumption might be made about the
other stochastic, uncontrollable inputs.
P - 800(A) - 0.025(M )
Answer:
B = 0.7(12,500) - 560(4) - 0.0175(60,000) = $5,460
“Subject to”
Answer:
Substituting, the model is: