Project Cost Management
Project Cost Management
Project Cost Management
C o s t
Determine Budget
Control Costs
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Knowledge
Process
Area Monitoring &
Initiating Planning Executing Closing
Control
Plan Cost
Scope Cost Estimating Control Cost
Cost Budgeting
• Cost estimates, budgets, WBSs, and schedules are
interrelated.
• When the cost cannot be estimated because it is
too complex, the task is broken down further
until it can.
Plan Cost Management
Estimate Accuracy
• Most difficult to estimate as very little project info
is available, made during initiating process
Rough Order • Project selection decisions.
--25%
50%
of Magnitude +75% • Very early in the project life cycle, often 3–5 years
+100%
(ROM) before project completion
Contingency
Cost Control reserve
baseline accounts Activity
Work contingency
Package
Activity cost
cost estimate
estimate
Funding Limit Reconciliation
Cost efficiency???
Earn Value Management
NOT ENOUGH
INFORMATION
Earn Value Management
As of today
Original plan
BAC
Original PV
spending
actual AC
spending
ETC EAC
Forecast
Spending
plan
Earn Value Management
Cost efficiency???
The actual cost should be 50.000
Earn Value Management
Plan cost (Plan Value/ PV) or BCWS
Budgeted Cost Work Scheduled
CPI = 1 on BUDGET
Variance
Analysis
C Original estimation
fundamentally flawed
Simple calculation
Based on previous performance
Varians
dianggap
sama sampai
EAC=AC+(BAC-EV)
akhir
Estimate at completion
EAC*= AC + ETC (estimate to complete)
ETC= BAC-EV= 1000-250= 750
EAC*= 310+ 750=1060
EAC*= BAC/CPI = 1000/0.806=1.240,69
TCPI>1 Bad
TCPI<1Good
To-Complete Performance
Index (TCPI)
TODAY
(Reporting day)
Projection of
schedule delay
at completion
Estimate at
Completion
EAC (EAC)
Projection of
cost variance
at completion
BAC (VAC)
AC Budget at
Completion
(BAC)
COST
Cost
Variance
(CV)
PV
Schedule
Variance
(SV)
ACTUAL
EV
PLAN
EARN
VALUE
TIME
Project is over budget & behind schedule
example
activity predecessor resource duration
A - 6 4
B A 2 1
C A 2 3
D B 7 4
E D 3 2
F E,C 1 1
6
Resource
4 imbalance
A D F
B
2 E
C
2 4 6 8 10 12 14
Project Days
Recruitment at the early period
Period levelling
0-4 6 Recruitment cost =
4-5 4
$10/man
5-9 7
7-9 7 Idle cost= $5/man
9-11 5
Wages= $15/man
11-12 1
Recruitment at the early period
Period levelling Cost
0-4 6 1) 7 x $10= $70
2) 6 x $15= $90 Recruitment cost =
3) 1 x $5= 5 $10/man
total= $165
4-5 4 1) 4x $15= $60 Idle cost= $5/man
2) 3 x $5= $5
total= $ 65 Wages= $15/man
5-9 7 7x $15= $90
7-9 7 7x $15= $90
9-11 5 5x $15= $85 Total cost= 510
11-12 1 1x $15= $15
• the United Kingdom’s National Health
Service (NHS) IT modernization program