Flexible and Static Budget
Flexible and Static Budget
Flexible and Static Budget
Hmm! Comparing
static budgets with
Static budgets actual costs is like
are prepared for comparing apples
a single, planned and oranges.
level of activity.
Performance
evaluation is difficult
when actual activity
differs from the
planned level of
activity.
McGraw-Hill/Irwin Copyright © 2006. The McGraw-Hill Companies, Inc.
Flexible Budgets
CheeseCo
CheeseCo
CheeseCo
U = Unfavorable variance
CheeseCo was unable to achieve
the budgeted level of activity.
CheeseCo
CheeseCo
I don’t think I
can answer the Actual activity is below
question using budgeted activity.
a static budget. So, shouldn’t variable costs
be lower if actual activity
is lower?
The
The relevant
relevant question
question is
is .. .. ..
“How
“How much
much of
of the
the favorable
favorable cost
cost variance
variance isis
due
due to
to lower
lower activity,
activity, and
and how
how much
much isis due
due to
to
good
good cost
cost control?”
control?”
To
To answer
answer the
the question,
question,
we
we must
must
the
the budget
budget toto the
the
actual
actual level
level of
of activity.
activity.
Let’s prepare
budgets
for CheeseCo.
CheeseCo
Cost Total Flexible Budgets
Formula Fixed 8,000 10,000 12,000
per Hour Cost Hours Hours Hours
Machine hours 8,000 10,000 12,000
Variable costs Variable costs are expressed as
Indirect labor $ 4.00 a constant amount per hour.
Indirect material 3.00
Power 0.50 $40,000 ÷ 10,000 hours is
Total variable cost $ 7.50 $4.00 per hour.
Fixed costs Fixed costs are
Depreciation $ 12,000
Insurance 2,000
expressed as a
Total fixed cost total amount.
Total overhead costs
McGraw-Hill/Irwin Copyright © 2006. The McGraw-Hill Companies, Inc.
Preparing a Flexible Budget
CheeseCo
Cost Total Flexible Budgets
Formula Fixed 8,000 10,000 12,000
per Hour Cost Hours Hours Hours
Machine hours 8,000 10,000 12,000
Variable costs
Indirect labor $ 4.00 $ 32,000
Indirect material 3.00 24,000
Power 0.50 4,000
Total variable cost $ 7.50 $ 60,000
CheeseCo
Cost Total Flexible Budgets
Formula Fixed 8,000 10,000 12,000
per Hour Cost Hours Hours Hours
Machine hours 8,000 10,000 12,000
Variable costs
Indirect labor $ 4.00 $ 32,000
Indirect material 3.00 24,000
Power 0.50 4,000
Total variable cost $ 7.50 $ 60,000
Fixed costs
Depreciation $ 12,000 $ 12,000
Insurance 2,000 2,000
Total fixed cost $ 14,000
Total overhead costs $ 74,000
McGraw-Hill/Irwin Copyright © 2006. The McGraw-Hill Companies, Inc.
Preparing a Flexible Budget
CheeseCo
Cost Total Flexible Budgets
Formula Fixed 8,000 10,000 12,000
per Hour Cost Hours Hours Hours
Machine hours 8,000 10,000 12,000
Variable costs
Indirect labor $ 4.00 $ 32,000 $ 40,000
Indirect material 3.00 fixed costs
Total 24,000 30,000
Power 0.50
do not change in4,000 5,000
Total variable cost $ 7.50 $ 60,000 $ 75,000
the relevant range.
Fixed costs
Depreciation $ 12,000 $ 12,000 $ 12,000
Insurance 2,000 2,000 2,000
Total fixed cost $ 14,000 $ 14,000
Total overhead costs $ 74,000 $ 89,000 ?
McGraw-Hill/Irwin Copyright © 2006. The McGraw-Hill Companies, Inc.
Quick Check
What
What should
should be
be the
the total
total overhead
overhead costs
costs for
for the
the
Flexible
Flexible Budget
Budget at
at 12,000
12,000 hours?
hours?
a.
a. $92,500.
$92,500.
b.
b. $89,000.
$89,000.
c.
c. $106,800.
$106,800.
d.
d. $104,000.
$104,000.
What
What should
should be
be the
the total
total overhead
overhead costs
costs for
for the
the
Flexible
Flexible Budget
Budget at
at 12,000
12,000 hours?
hours?
a.
a. $92,500.
$92,500.
b.
b. $89,000.
$89,000.
c.
c. $106,800.
$106,800.
d.
d. $104,000.
$104,000.
Fixed costs
Depreciation $ 12,000 $ 12,000 $ 12,000 $ 12,000
Insurance 2,000 2,000 2,000 2,000
Total fixed cost $ 14,000 $ 14,000 $ 14,000
Total overhead costs $ 74,000 $ 89,000 $ 104,000
McGraw-Hill/Irwin Copyright © 2006. The McGraw-Hill Companies, Inc.
Flexible Budget Performance Report
Let’s prepare a
budget performance
report
for CheeseCo.
Fixed costs
Depreciation $ 12,000 $ 12,000
Insurance 2,000 2,050
Total fixed cost $ 14,050
Total overhead costs $ 77,350
McGraw-Hill/Irwin Copyright © 2006. The McGraw-Hill Companies, Inc.
Quick Check
What
What isis the
the variance
variance for
for indirect
indirect labor
labor when
when the
the
flexible
flexible budget
budget forfor 8,000
8,000 hours
hours is
is compared
compared toto the
the
actual
actual results?
results?
a.
a. $2,000
$2,000 U U
b.
b. $2,000
$2,000 FF
c.
c. $6,000
$6,000 U U
d.
d. $6,000
$6,000 FF
What
What isis the
the variance
variance for
for indirect
indirect labor
labor when
when the
the
flexible
flexible budget
budget forfor 8,000
8,000 hours
hours is
is compared
compared toto the
the
actual
actual results?
results?
a.
a. $2,000
$2,000 U U
b.
b. $2,000
$2,000 FF
c.
c. $6,000
$6,000 U U
d.
d. $6,000
$6,000 FF
Fixed costs
Depreciation $ 12,000 $ 12,000
Insurance 2,000 2,050
Total fixed cost $ 14,050
Total overhead costs $ 77,350
McGraw-Hill/Irwin Copyright © 2006. The McGraw-Hill Companies, Inc.
Quick Check
What
What isis the
the variance
variance for
for indirect
indirect material
material when
when the
the
flexible
flexible budget
budget forfor 8,000
8,000 hours
hours is
is compared
compared to
to the
the
actual
actual results?
results?
a.
a. $1,500
$1,500 U U
b.
b. $1,500
$1,500 FF
c.
c. $4,500
$4,500 U U
d.
d. $4,500
$4,500 FF
What
What isis the
the variance
variance for
for indirect
indirect material
material when
when the
the
flexible
flexible budget
budget forfor 8,000
8,000 hours
hours is
is compared
compared to
to the
the
actual
actual results?
results?
a.
a. $1,500
$1,500 U U
b.
b. $1,500
$1,500 FF
c.
c. $4,500
$4,500 U U
d.
d. $4,500
$4,500 FF
Fixed costs
Depreciation $ 12,000 $ 12,000 $ 12,000 $ 0
Insurance 2,000 2,000 2,050 50 U
Total fixed cost $ 14,000 $ 14,050 50 U
Total overhead costs $ 74,000 $ 77,350 $ 3,350 U
McGraw-Hill/Irwin Copyright © 2006. The McGraw-Hill Companies, Inc.
Flexible Budget Performance Report