FURNACE WATER COOLING SYSTEM

DEPARTMENT :- CCP-01 MECH


BUSINESS UNIT:- FABU
LOCATION:- CDR
Clarified water utilisation areas

1.Furnace cover section


2. Furnace electrode cover seal section (Filler section)
3.Contact clamp
4. Pressure ring
5. Cooling shield 8.Raw gas damper
6. Furnace shell 9.GP Compressor
7.Furnace Hydraulic System 10.Dry fog system in RMHS
Furnace water cooling system
FROM
POWER
PLANT

Cold well
(CLEAR)
Cold well
(CONTA)
Flow Diagram of Furnace water cooling system
1.Furnace cover section

4 5
3

18 19 6
2
16
21 20

1 15 17 8
7
25 22
14

13 9
24 23

12 10
11

Furnace cover section assembly in top of the furnace and it is assembly of 13


section and each section water was inlet and outlet from same section. For
cooling purpose water is circulating 100-120LPM in each section.
2. Furnace electrode cover seal section (Filler section)

Furnace electrode cover seal is assembled on furnace cover section.it is


installed in each electrode system. This assembly is divided into 04 filler section
segments,upper part and stuffing box. Here water circuit is assembled in 04
parts.For cooling purpose water is circulating 70-90LPM in each section.
3. Furnace electrode system

Cooling shield
Pressure ring

Contact clamp
Furnace electrode system
In each electrode assembly of 08 no Contact clamp segments,08 no Pressure ring
segments & 08 no cooling shield segments.

For Contact clamp 01 no water circuit is divided for 02 segments. Here for each
electrode, we have 04 circuits for 08 segments from water manifold. It is
nomenclated with X01L,X02L,Y01R,Y02R.(eg:- 101L,102L,201R,202R)

For Pressure ring 01 no water circuit is divided for 02 segments. Here for each
electrode, we have 04 circuits for 08 segments from water manifold. It is
nomenclated with X05,X06,X07,X08.(eg:- 105,106,107,108)

For Cooling shield 01no water circuit is divided for 04 segments. Here for each
electrode, we have 02 circuits for 08 segments from water manifold. It is
nomenclated with X03,X04 (eg:- 103,104).
Tr-B
301R,302R

201L,202L

201R,202R 2 3

303 304

305 306

305 307
301L,302L
308 307

303 304
Tr-C

308 306

A
Tr-
101L,102L
1 101R,102R
S.NO DESCRIPTION INLET OUTLET TRIPPING/RESET

1 PRESSURE RING 6.5 bar 4.5 3.2 / 4.0

2 CONTACT CLAMP 3.2 bar -- 1.2 / 1.8

1.8 bar
3 COOLING SHIELD To - 1.2 / 60
2.2 bar
100 LPM
4 FURNACE COVER To - 60 LPM
120 LPM
70LPM
5 FURNACE FILLER SECTION To - 50 LPM
90LPM
Emergency water tank circuit
FURNACE SHELL COOLING

COLD
WELL
(CONTA.)

Hot well
(Conta.)
Equipment availability
S.NO EQUIPMENT NAME working standby Spares Availability
01 Furnace Main cooling 01W 01S Availble
Pump( GRP 1/1 & GRP 1/2)
02 Pressure ring pump 01W 01S Available
GRP 2/1 &2/2
03 Shell cooling pump 01W 01S To be recieved
04 Hot Contaminator pump 01W 01S Available
05 Main Cooling Tower 01W 01S Available
06 Auxiliary Cooling Tower 01W 01S Plan to repair
07 Back wash pump & tank 01W - Pump spares
available
08 Emergency DG Pump 01W - Pump side
available,DG side
maintained by
Automobile
Issues & planning
1. From Furnace pump house to Furnace building, cooling water header pipeline
is laid under the ground. Identification of leakage & rectification is difficult. So, it
is to be planned for re-routing the pipeline, preferably during Furnace Cover
replacement .
2. In furnace floor, inlet & outlet header pipelines of water manifold & emergency
tank were installed from plant starting and it was never replaced. Header pipelines
are corroded in some areas and hence to be planned for replacement.
3.Auxiliary cooling tower equipment & wooden structure are damaged.
Planned for replacement in FY2023-24.
4. Sealing of all Split Casing Pumps to be changed from Gland Packing type to
Mechanical Seal type, to be prevent leakages.
5. Plan to change GRP 2/2 pump from Imported (ABB STALL( JMW Z-12-125)) to
Indigenous Grundfos(CR 95-5) , to maintain spares availability.