ENGINEERING MANAGEMENT
(GE 404)
TUTORIAL # 1
GANTT BAR CHART
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A
B
C
D
E
F
G
H
I
Sa Su Mo Tu We Th Fr S S M T W T F
A
B
C
D
E
F
# Calendar days : 10
# Working days : 9 # Critical tasks; A, B,
F
GE 404 (Engineering Management) December 18, 2023
Example3: The library at KSU has just received authorization to spend up to SR40,000
on new journal subscriptions and book purchases. Accordingly, the librarian has
developed the following small project.
5
a) Draw Gantt bar chart for the library at KSU and use this representation to
determine the expected number of weeks it will take before the new
materials are in the library
b) Draw Gantt bar chart for this project based on the calendar days : (Use
activity duration in days instead of weeks ) Starts on = start date 16/9/2018.
Holidays= Friday and Saturday
GE 404 (Engineering Management) December 18, 2023
a) Draw Gantt bar chart for the library at KSU and use this representation to
determine the expected number of weeks it will take before the new
materials are in the library
6
Time
Task Predecessors
(weeks)
A Solicit Input from employee - 4
Project duration: 12 weeks B Identify obsolete material in library - 3
Critical activities: B, C, E, F C Clear out space for new purchases B 2
D Hold sale/discard obsolete material B 3
Review input from employee given
E A, C 2
budget and space requirements
F Order/receive new material E 5
TASK (Week) 1 2 3 4 5 6 7 8 9 10 11 12
A
B
C
D
E
F
1 2 3 4 5 6
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
A
B
C
D
E
F
7 8 9 10 11 12
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
A
B
C
D
E
F
Questions Please