Module 1
Module 1
Module 1
CONSTRUCTION CONTRACTS
METHODS AND EQUIPMENT
PROGRAM ELECTIVE 2
Module 1
Contracts Requirement of Contract, Elements of Contracts based on Indian
Contract Act (1872), Types of Contracts based on Stakeholder responsibilities,
Project Delivery Models – (Turnkey, EPC and PPP Models), Standard forms of
contract - (FIDIC, NHAI and CPWD), General conditions of the contract for
construction.
MODULE 2
Contract Administration Project Documentation, Submission and approval of
documents, Permits and approvals, Construction claims and disputes, Potential
major claim areas, The Bid Proposal Process and the Potential for Disputes,
Modes of resolving disputes, Understanding of Arbitration and Conciliation Act
1996 with latest amendments
MODULE 3
Contract Management Discharge of contract, Breach of contract, Tendering
issues, Risks in construction contract, Regulatory aspects and ethics, Intellectual
property act, Law of Torts, General Construction specifications, Commercial
Construction Specifications, Bonds, Types of Bonds, Insurance, Workers
compensation Insurance, Commercial general liability insurance, Builders risk
insurance.
MODULE 4
Construction Methods Horizontal Systems – Hand - set slab forms, Table forms,
Vertical Systems – Wall forms, Column forms, Combined Horizontal and Vertical
Systems – Tunnel Form Systems, TrenchSafety. Cost effective construction
methods - Prestressed concrete construction - 3D printing. Precast Flat Panel
System-3D Volumetric Construction-Flat Slabs-Hybrid Concrete Construction-
Precast Foundations-Insulating Concrete Formwork-Soil stabilisation methods
Module 5
Acceptance
• When the person to whom
the proposal is made,
signifies his assent there to,
the proposal is said to be
accepted.
Promise A Proposal when accepted becomes a promise.
In simple words, when an offer is accepted it
becomes promise.
Offeror-Accepter
PROMISOR-PROMISEE
Considerati When at the desire of the promisor, the promisee
on or any other person has done or abstained from
doing something such act is called a
consideration for the promise. i.e. something in
return.
Agreement Every promise and set of promises forming the
consideration for each other.
• The contractor is paid for the work actually done at pre-agreed unit
rates.
• Also called as ‘Payment By Quantum Meruit’
• In this type of contract it is important that the items in the Schedule
of rates or Priced Bill of Quantities cover the whole of the work.
• It is used where the nature and extent of the work can accurately
defined but quantity of cannot.
3.By part lump sum , Part schedule of rates
• Part of work under the contract may be covered by a lump sum, Part of
it paid for under schedule of rates.
4. By cost plus
• Also called Cost reimbursement contract
• Contract amount PLUS (+) a fee to cover overhead cost and profit.
• The fee can be done of the following :
• A fixed sum
• A fixed sum with a profit sharing arrangement
• A fixed sum with a bonus arrangement
• A fixed fee with a sliding-scale adjustment
• A percentage of the costs
C. Classification by Technical and administrative responsibility
45
Management contracts
• In effect, management contracting is a
procurement method consisting of 100% sub-
contracting. Every item of building work is sub-
contracted to works contractors.
• The opportunity for the contractor to become part
of the design team arises not from the contract
structure but from early appointment and the
pattern of liability and responsibility outlined in
the contract.
Contractual relationships in management contracting
47
USE OF MANAGEMENT CONTRACTING
1. The employer wishes the design to be carried out by an
independent architect and design team.
2. There is a need for early completion.
3. The project is fairly large.
4. The project requirements are complex.
5. The employer, while requiring early completion, wants
the maximum possible competition in respect of the price
for the building works.
48
Construction management contracts
• A construction management contract is a specific type of agreement
that governs the relationship between a client (often the owner of a
construction project) and a construction management firm or
professional.
• This contract outlines the roles, responsibilities, and terms that will
guide the construction management services for a project.