INDUSTRIAL TRAINING

ON
“CONSTRUCTION OF C.C ROADS”
(Under Municipality Department, Punganur)

Presented
by
A.MEGHANA
20018-C-004

Internal Guide Training Incharge


Smt.C. Gowri Sri.P.S MAHESH garu.
Lecturer Deputy Executive Engineer
Muncipality Department
The following works are comes under municipal
Department;
Municipal roads and water drainage.
Urban planning including town planning.
Water supply for commercial purpose.
Public health, sanitation.
Street lighting.
Under municipality, I worked on construction of
CC roads and CC drains.
CC ROAD
SITE DETAILS
S NO PLACE NAME LENGTH BREADTH
1 BHAGATH SINGH 92.00 m 4.5 m
COLONY

2 MELUPATLA 97.00 m 4.5 m


3 NEAR INDIAN BANK 45.00 m 4.5 m
4 NEAR MARKET YARD 60.00 m 3.5 m
5 KONETIPALEM 75.00 m 4.00 m
6 SUBEDARA STREET 55.00 m 3.5 m
7 THATIMAKULAPALEM 45.00 m 3.00 m
8 MANGALAM COLONY 80.00 m 4.5 m
9 KONETIPALEM 60.00 m 3.00 m
10 KOTHAPET 210.00 m 4.5 m
11 POLICE LINE STREET 60.00 m 3.5 m
CONTENTS
INTRODUCTION
MATERIALS
MACHINERY
CONSTRUCTION PROCEDURE
CONCLUSION
INTRODUCTION
ROADS
The routes or path being at one destination and lead to
another.
Road is an open, generally public way for the passage
of vehicles, people, and animals.(village Road)
MATERIALS
 Cement:
• A cement is a binder used in construction.
• At site OPC 43 Grade used.
Sand:
• The aggregates which pass through IS sieve 4.75 mm is called Fine
aggregate .
• Source : Cheyeru river, Rajampeta to site .
Coarse aggregate :
• The aggregates which retain on mm IS sieve 4.75 mm is called coarse
aggregate .At Some sites 40mm & 20 mm Size HBG metal used
• CC(1:4:8) & CC(1:2:4)
 Water: Potable water is used for mixing and curing of concrete.
MACHINERY
Weigh batching plant : To weigh the ingredients of concrete.
Concrete Mixer: To Mix the ingredients of concrete.
Needle Vibrator: To vibrate and proper compaction. 40mm or
60mm needle vibrator used.
Trowels : It is used for adjusting and spreading the concrete.
Wooden/ metal : To spread concrete and removing excess
height of concrete.
Surface vibrator : To vibrate and remove voids.
Machineries
AJAX FERARI: Which
mixes and transports the
concrete

Concrete mixer
MELUPATLA SITE:

 I am presenting on melupatla site.

 The length of the road is 97.00 m.

 The width of the road is 4.5 m.

 The thickness of the road is 0.2m.

 The Estimated cost of the road is Rs.7.60 lakhs.


CONSTRUCTION PROCEDURE
 SITE CLEARENCE
 PREPARATION OF SUBGRADE
 PREPARATION OF SUB BASE
 PLACING OF FORMS
 BATCHING OF MATERIALS & MIXING
 TRANSPORTING & PLACING OF CONCRETE
 COMPACTION
 CURING
 OPENING TO TRAFFIC
SITE CLEARENCE

•Removal of Unwanted
plants .
• Disposing of all
unsuitable materials
such as trees,bushes,
shrubs, and top Organic
soils up to a minimum
depth of 4”.
PREPARATION OF SUBGRADE.

•The subgrade course is


typically the natural soil.
• After cleaning ,it is
prepared to the required
grade and profile,
that is 4 inches.
PREPARATION OF SUB BASE
When natural sub-
grade is not very firm,
a sub-base over the
subgrade .
The thickness of the
Sub-base is 0.1 m.
PLACING OF FORMS
The forms are made
up of Steel or
timber.
The depth of the
steel sections is
equal to thickness of
the road that is 4
inches.
BATCHING OF MATERIALS & MIXING
The materials used
Cement ,Fine & Coarse
aggregates, and water
with weigh batch
CC(1:1 1/2:3)-M25 Grade
Mixing is Done for
Two minutes until
Homogeneous mixture.
TRANSPORTING AND PLACING OF CONCRETE
Transferring of concrete from mixing plant to
construction site by chute and placed it ,spread on
subsurface with required thickness that is 4 inches
.
COMPACTION

Packs the aggregate


particles
together so as to increase the
density of concrete.
• The Surface is finished with
Wooden tamper.
• It increases the strength of
Concrete.
CURING
• For hardening of concrete ,and to achieve strength
oit is cured by ponding method regularly for about
28 days.
OPENING TO TRAFFIC
 After completion of curing the road is open to
traffic.
CONCLUSION
I learnt How the Construction of CC Roads Undergoes.
I can conclude that there is difference between theoretical
and practical work. The scope of understanding will be more
when practical work is done.
I got more knowledge and experience by doing
practical work.
I have successfully completed the Industrial
Training by the guidance of Internal & External guides.
Thank
you