Lecture 12 Example of CPM

The document provides examples and questions about critical path method (CPM) network analysis. It includes examples of preparing arrow network diagrams based on given activities and durations, calculating earliest and latest start times, and identifying critical paths and activities. It then provides two questions involving performing the same CPM analysis steps on additional sets of project activities and durations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

Lecture 12 Example of CPM

The document provides examples and questions about critical path method (CPM) network analysis. It includes examples of preparing arrow network diagrams based on given activities and durations, calculating earliest and latest start times, and identifying critical paths and activities. It then provides two questions involving performing the same CPM analysis steps on additional sets of project activities and durations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 6

EXAMPLE OF CPM

EXAMPLE 1
 Prepare an arrow network based on the
events given and overall duration to complete
the project.
 Calculate the earliest start event time and

latest start event time.


 Indicate the critical path and critical activity in

the network diagram that has been prepared.


EXAMPLE 2
a) Prepare an arrow network based on the events given in the
Table 1 below and overall duration to complete the project.
b) Calculate the earliest start event time and latest start event
time.
c) Indicate the critical path and critical activity in the network
diagram that has been prepared in (a).

Activity Duration
(days)

1-2 14
2-3 13
2-4 12
3-6 20
4-5 18
4-6 24
5-8 18
6-7 15
QUESTION 1
a) Prepare an arrow network based on the events given in the
Table 1 below and overall duration to complete the project.
(15 marks)
b) Calculate the earliest start event time and latest start event
time. (7 marks)
c) Indicate the critical path and critical activity in the network
diagram that has been prepared in Question 1 (a).
Activity Duration
(days)

1-2 2
2-3 4
2-4 3
3-5 4
4-5 8
4-6 4
5-6 1
5-7 8
QUESTION 2
a) Prepare an arrow network based on the events given in the
Table 1 below and overall duration to complete the project.
(15 marks)
b) Calculate the earliest start event time and latest start event
time. (7 marks)
c) Indicate the critical path and critical activity in the network
diagram that has been prepared in Question 1 (a).
Activity Duration
(days)

1-2 14
2-3 13
3-4 11
2-4 12
2-6 20
4-5 24
5-8 18
6-7 15
QnA