Estimations
Estimations
Estimations
IT-425
Prof. Dr. Ali Raza
Time Estimation
• Activity duration estimating is the process of taking information on
project scope and resources and then developing durations for input
to schedules.
• Activity duration estimates are approximations of how much time a
project task will take.
• Accurate estimates help in developing realistic project schedules
and managing resources effectively.
Duration Vs Effort
• Duration includes the actual amount of time spent working on an activity
plus elapsed time
• For example, even though it might take one workweek or five workdays to do
the actual work, the duration estimate might be two weeks to allow extra time
needed to obtain outside information or to allow for resource availability
• Effort is the number of workdays or work hours required to complete a task
• A duration estimate of one day could be based on eight hours of work or
eighty hours of work
• Duration is used to determine the schedule; effort is used to determine labor
costs
Estimation: Key
Considerations
• Complexity: The complexity of an
activity directly impacts its duration.
More complex activities typically require
more time to complete.
• Resource Availability: The availability
and allocation of resources, such as
manpower, equipment, and materials, can
significantly influence activity duration.
Estimation: Key
Considerations
• Dependencies: Activities that are dependent on other tasks or
milestones may have their durations affected by delays or dependencies
in the project schedule.
• Risks and Uncertainties: Project risks and uncertainties can impact
activity duration. It is important to consider potential delays or
disruptions when estimating activity durations.
Causes of Time Variation
• Varying skill levels—You may get a higher- or lower-skilled person
assigned to the task, causing the actual duration to vary from planned
duration.
• Unexpected events—Random acts of nature, vendor delays, incorrect
shipments of materials, traffic jams, power failures, etc.
• incomplete work.
Causes of Time Variation
• Efficiency of worker’s time—Every time a worker is interrupted, it
takes additional time to get back to the level of productivity attained
prior to the interruption.
• Mistakes and misunderstandings—Despite all of your efforts to
clearly and concisely describe each task that is to be performed, you
will most likely miss a few. This will take its toll in rework or scrapping
incomplete work.
Estimation Methods
1. Extrapolating Based on Similarity to Other Tasks
•If some tasks in your project are similar to tasks completed in other
projects, you can use recollections or historical data from those tasks to
estimate the duration of the present task.
•Project methodologies often include a project notebook that records
estimated and actual task durations. This historical data can be used as a
knowledge base for estimating task duration.
2. Seeking Expert Advice:
•When dealing with breakthrough technologies or new technologies within
the organization, outside authorities such as vendors or non-competitors
who have experience with the technology can provide valuable expert
advice.
Estimation Methods
3. Applying the Delphi Technique
• The Delphi technique involves a group estimation process. After
briefing the group on the project and task, each individual provides
their best guess for the task duration.
• The guesses are tabulated, and the results are presented to the group.
Participants with estimates in the outer quartiles explain their
reasoning, and the group members make subsequent guesses.
• This iterative process continues until a consensus is reached, and the
average of the final guesses is used as the group's estimate.
• The Delphi technique is effective when expert advice is unavailable.
Estimation Methods
4. Applying the Three-Point Technique
• Task duration is considered a random
variable. The three-point technique takes
into account the variability of task
duration.
• Each task is estimated using three values:
optimistic (best-case), pessimistic (worst-
case), and most likely. These estimates
provide a probabilistic view of the task's
duration.
• The three estimates are used to calculate a
weighted average, considering the
Estimation Methods
5. Applying the Wide-Band Delphi Technique
• The wide-band Delphi technique combines the Delphi method and
the three-point technique.
• A panel of experts provides optimistic, pessimistic, and most likely
estimates for the duration of a chosen task in each iteration.
• Extreme estimates are removed, and averages are computed for each
estimate. The resulting averages serve as the optimistic, pessimistic,
and most likely estimates of the task duration.
Elapsed Vs Productive Time
• Duration is the elapsed time in
business working days.
• Work effort is the labor required to
complete an activity. It is typically the
amount of focused and uninterrupted
labor time required to complete an
activity.
• Productive time is the percentage
of work day that can devoted to
project activity work.
Project Networks Diagram
• A project network diagram is a pictorial representation of the
sequence in which the project work can be done.
• We have identified the known set of tasks and their duration
• The planning team needs to determine the order in which
these tasks are to be performed.
• The graphic picture provides project schedule information :
1. The earliest time at which work can begin on every task
2. The earliest expected completion date of the project
Build Project Network
Diagram
• A project schedule can be built using either of the following:
1. Gantt chart
2. Network diagram
• The Network diagram can be build using:
1. Network Analysis with Activity on Arrow (AOA)
2. Network Analysis with Activity on Node (AON)
Build Project Network
Diagram
Network Analysis with Activity on Arrow (AOA)
• The node at the left edge of the arrow is the event that begins the task,
and the node at the right edge is the event that ends the task.
• Nodes are numbered sequentially, and their order has to be preserved.