Chapter 13 PPSJ Lecture 1
Chapter 13 PPSJ Lecture 1
Material Requirements
Planning (MRP)
Business 3401
Introduction
• MRP (Material Requirements Planning)
o determines the plans for purchasing and
production of dependent-demand components.
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Independent and Dependent
Independent Demand
Demand
finished goods A Dependent Demand
raw materials,
B(4) C(2) parts,
subassemblies
D(2) E(1) D(3) F(2)
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Material Requirements Planning
(MRP)
• Computer-based information system that handle
ordering and scheduling of dependent demand
items.
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Description of MRP
MRP converts the production plan for final
products into requirements for component items
and raw materials:
What is needed
When is needed
How much is needed
When should procurement, fabrication assembly
start for completing end items on time
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Overview of MRP
MRP Inputs MRP Processing MRP Outputs
Changes
Master Immediate
Production order releases
Schedule Planned-order
releases
Primary
reports
Demand history
reports
Bill of MRP computer Secondary
Performance-
materials programs reports control
reports
Inventory
records Inventory
transaction
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
MRP Inputs
1. Master Production Schedule
• States which items are to be produced, when these are
needed, and in what quantities
2. Bills of Material (BOM)
• BOM - A listing of all raw materials, subassemblies and parts
needed to produce one unit of a product
• Assembly diagram and product structure tree – Visual and
nominal depiction of the requirements in a bill of material,
where components are shown by levels
3. Inventory levels, Lead times, and Open Orders
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Input: Master Production
Schedule
Master Production Schedule: Which end items are to be
produced, when these are needed, and in what
quantities.
The planning horizon is divided into time periods called time-
buckets (typically weeks)
WEEK NUMBER
Item: A 1 2 3 4
Quantity 100
Level
Chair (C)
0
1 Leg Back
Assembly (LA) Seat (S) Assembly (BA)
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Example: Product Structure Tree
Level
Determine the quantities of
0 A each item needed for 50 As.
1 B(2) C(3)
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Question 3, a)
Draw the product structure tree for the End item
End Item
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Question 3, b)
If 40 units of the end item are to be assembled, how many
additional units of B are needed?
B on hand: 30
Required for 40 items: Less on hand: B’s Needed:
L: 2 x 40 = 80 10 70 x 2 = 140
C: 1 x 40 = 40 15 25 x 2 = 50
K: 3 x 40 = 120 20 100 x 2 = 200
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Question 3 c)
An order of 40 units of the end item is scheduled to be
shipped at the start of week 8. What is the latest week that
the components of the order can be started and the order still
be ready to ship on time?
End Item-1
7 weeks in the longest lead time so, 8 – 7 = 1. Must begin by start of week 1
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
MRP Processing & Assembly Time Chart
MRP processing takes end item requirements specified by
MPS and explodes them into time-phased requirements for
fabrication or assembly of subassemblies
Procurement of
raw material D Fabrication
of part E
Subassembly A
Procurement of Final assembly
raw material F and inspection
Procurement of
part C
Procurement of
part H Subassembly B
Planned- Planned-
Net
order order
requirements
receipts releases
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
Inventory Requirements
Net requirements =
Gross Requirements
– Available Inventory
Available Inventory =
Projected on hand
– Safety stock
– Inventory allocated to other items
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
MRP Processing
• Gross requirements
o Total expected demand during a time period
• Scheduled receipts
o Open orders scheduled to arrive
• Projected on hand
o Expected inventory on hand at the beginning of each time
period
• Net requirements
o The actual amount needed in each time period
Chapter 13 – Material
Business 3401
Requirements Planning (MRP)
MRP Processing
• Planned-order receipts
o Quantity planned to be received at the beginning of a
time period
• Planned-order releases
o Quantity planned to be ordered in the beginning of a
time period
o = planned-order receipts offset by lead time
Chapter 13 – Material
Business 3401
Requirements Planning (MRP) 22
Example (Chair Assembly)
Suppose that a 100-unit delivery of chairs is
scheduled at the start of week 6. Determine the
size and the timing of back-support parts to meet
this delivery.
LEADTIME
Final Chair Assembly 1 week
Back Assembly 1 week
Back Support Procur. 2 weeks
Week Number 1 2 3 4 5 6
Part: Back Gross Requirements 100
Assembly Scheduled Receipts
LT: 1 Projected On-hand
Net Requirements 100
Planned-order Receipts 100
Planned Order Releases 100
Chapter 13 – Material
Requirements Planning (MRP)
Example (Chair Assembly)
Week Number 1 2 3 4 5 6
Part: Back Gross Requirements 300
Support Scheduled Receipts 60
LT: 2 Projected On-hand 20 20 20 80
Net Requirements 220
Planned-order Receipts 220
Planned Order Releases 220
Chapter 13 – Material
Requirements Planning (MRP)
Lot Sizing Rules
Week Number 1 2 3 4 5 6
Part: Back Gross Requirements 300
Support Scheduled Receipts 60
LT: 2 Projected On-hand 20 20 20 80
Net Requirements 220
Planned-order Receipts 220
Planned Order Releases 220