Work Method Statement For Live 33kv Distribution Line Crossing

The document provides work methods and safety requirements for stringing activities to cross an existing live 33kV distribution line, including pre-stringing checks, stringing methodology using cranes, safety precautions like permitting and PPE, risk assessment of hazards like electrocution, and a rescue plan for any falls from height.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views12 pages

Work Method Statement For Live 33kv Distribution Line Crossing

The document provides work methods and safety requirements for stringing activities to cross an existing live 33kV distribution line, including pre-stringing checks, stringing methodology using cranes, safety precautions like permitting and PPE, risk assessment of hazards like electrocution, and a rescue plan for any falls from height.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 12

WORK METHOD STATEMENT FOR LIVE 33KV DISTRIBUTION

LINE CROSSING

Introduction
Work Scope
Required Tools & Equipment
Manpower
Pre-Stringing Activity For Crossing
Stringing Methodology
Job Safety Procedure/Safety Precautions
Risk Assessment
Work At Height Rescue Plan
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING

INTRODUCTION/PURPOSE
• To provides the requirements for stringing activity on
live 33kv line crossing.
• To includes the requirement for safety and quality
control.
• Layout all necessary requirements to achieve safety
and standard quality of said OHTL project.
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING

 WORK SCOPE
 Crossing of Live Existing 33KV OHTL
Distribution Line
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING
 REQUIRED TOOLS & EQUIPMENT
 Tensioner
 Puller
 Cable Drum Trailer
 Boom Truck
 Full body harness safety belts
 5 No. Hydraulic Cranes of Different Capacity
 Bull Wire
 Pilot Wire
 4 No. Nylon Ropes(350m each)
 Stand for conductor reel
 Work Bridge
 Traveler/Pulley
 Tool Box
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING

 Manpower
 Construction Manager 1 No.
 Site Engineer 1 No.
 HSE Engineer 1 No.
 Gang Leader 1 No.
 Forman 1 No.
 Lineman 4 No.
 Fitter 6 No.
 Labor Person 4 No.
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING

PRE-STRINGING ACTIVITY FOR CROSSING


 To check complete details of Tensioner and Puller capacity
 To check approved certificates of operators
 Coordination to the proponent organization
 To check all proper tools and PPEs.
 To request for work permit
 To check all manpower and equipment for competence efficiency and
effectiveness
 To implement the proper use of PPEs
 Conduct tool box meeting before commencing with the activity
 To Ensure safety of 33kv live line to be crossed with proper installation
of its protection
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING

STRINGING METHODOLOGY
 Conductor pulling will be done by utilizing 4 cranes and wooden spreader
 Positioning of cranes on both sides of 33kv live line two at each side with wooden
spreader beem
 Both cranes will hold the wooden spreader beem at the required level and
position
 5th crane will hold the conductor traveler for nylon rope/pilot wire passing
 Fiber wire rope shall be passed from conductor traveler
 Conductor shall be pulled under controlled tension method
 Above same method is repeated for stringing of all phases of circuit I&II.
 After completion of pulling conductor shall be removed from traveler while doing
rough sag.
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING

 JOB SAFETY PROCEDURE/SAFETY PRECAUTIONS


 To acquire proper PTW from SEC
 Safe work procedure for the specific activity
 To follow all safety precautions indicated within the issued work
permit
 To notify proper and concerned authorities regarding the
activity to be done
 To check all manpower and equipment for competence and
effectiveness
 To implement the proper use of PPEs
 Conduct tool box meeting before commencing with the activity
WORK METHOD STATEMENT FOR LIVE 33KV
DISTRIBUTION LINE CROSSING
RISK ASSESMENT WHILE WORKING
ON LIVE OHTL LINE CROSSING
WORK PLACE HAZARD RISK CONTROL

Positioning of cranes Existing Electrocautions 1-Competent crane operators with


at both sides of live 33kv live live line, valid license.
line 33kv for crossing line Damage to 2-Crane itself should be valid fitness
of conductors. material, certificates and load charts.
Tripping of live 3-No liffting operation should be
line done with out the clearance from
SEC.
4-Distance of cranes boom should be
4.5m.
5-Grounding must be provided to
cranes.
WORK METHOD STATEMENT FOR LIVE
33KV DISTRIBUTION LINE CROSSING
RISK ASSESMENT WHILE WORKING
ON LIVE OHTL LINE CROSSING
WORK PLACE HAZARD RISK CONTROL

Payout/Crossing of Existing Electrocautions 1-Continuous monitoring of


Pilot and Bull Wire 33kv live live line, superviser is required in this activity.
line Damage to 2-All equipment Tensioner,Puller
material, should be grounded.
Tripping of live 3-All lineman should know the
line hazards of activity.
WORK METHOD STATEMENT FOR LIVE
33KV DISTRIBUTION LINE CROSSING
RISK ASSESMENT WHILE WORKING
ON LIVE OHTL LINE CROSSING
WORK PLACE HAZARD RISK CONTROL

Pulling of Not properly Damage to 1-Wire socks should be proper and in


Conductors and secure wire material, good condition.
OPGW Connection, Tripping of 2-First ad kit must be available.
Existing live live line 3-All lineman should know the
line hazards of activity.
WORK METHOD STATEMENT FOR LIVE
33KV DISTRIBUTION LINE CROSSING
WORK AT HEIGHT RESCUE PLAN
 Pre-planned procedure is designed to be used in the event of a fall from
height
 To inform the HSE manager and get contacted with the nearest emergency
assistance,rescue centers and hospitals.
 To ensure the rescue is carried out in a steady and controlled manner
 To ensure effective communication is maintained at all times
 Carefully monitor the condition of the worker and administer first aid
where necessary
 Contacting the emergency services so that victim person can begin
receiving medical treatment as quickly as possible