Unit 3 Final Lecture
Unit 3 Final Lecture
HIGHWAY
AND
RAILROAD
ENGINEERING
Engr. Ralph S. Reyes, CE
Instructor, CSU Carig Campus
College of Engineering and Architecture
Unit 3
HIGHWAY DEVELOPMENT
AND PLANNING
Lesson 1
• MATERIALS TESTING
• QUALITY CONTROL
WHAT IS MATERIALS TESTING ?
It should be emphasized that what are specified are the minimum number
of testing only. Additional number of test can be require to the materials
if the owner/inspector is in doubt of the quality of materials or the
finished structure.
When the Testing of Materials be Conducted
If the test is not conducted at the proper time, there is no quality control
since it will then be too late to correct anything that is defective.
• Surface Courses
Item 300 – Aggregate Surface Course
Item 301 – Bituminous Prime Coat
Item 302 - Bituminous Tack Coat
Item 307 - Bituminous Plant Mix Surface Course-General
Item 310 – Bituminous Concrete Surface Course, Hot Laid
Item 311 – Portland Cement Concrete Pavement
• Bridge Construction
Item 404 – Reinforcing Steel
Item 405 – Structural Concrete
Item 406 – Prestressed Concrete Structures
Item 407 – Concrete Structures
Item 411 – Paints
• Drainage and Slope Protection Works
Item 500 – Pipe Culverts and Storm Drains
Item 505 – Riprap and Grouted Riprap
Item 506 – Stone Masonry
Item 507 - Rubble Concrete
Item 511 – Gabions and Mattresses
* Miscellaneuos Materials
Item 603 – Guardrail
Item 704 – Concrete Masonry Blocks
Main Road Components
Subgrade
Aggregate sub-base course
Aggregate base course
Surface course
Drainage structures
Slope protection/retaining structures
Miscellaneous Works
Main Road Components
Main Road Components
Subgrade- is the upper layer of natural soil which may be the undisturbed
local materials, or soil excavated elsewhere placed as fill. In either case, it is
compacted during construction for road stability.
Aggregate Subbase and Base Courses - are individual stabilizing layers of
selected material and designed thickness placed on top of the subgrade to
distribute the load transmitted from the surface course.
Surface Course - is the uppermost structural component of the roadway,
which provides resistance to wear and shearing stress due to traffic load. It
also provides an even skid resistance surface with comfortable durability and
is appropriately crowned to prevent rain water from penetrating into the
subgrade.
Main Road Components
Shoulders - are located beside the carriage way which is the total width
available for passing vehicles, and is used to receive lateral clearance to
protect major structures on the roadside, to secure safety and comfort of
both motorists and pedestrians and for emergency stopping purposes.
Drainage Structures - are located beneath or alongside the roadway used
in collecting, transporting and disposing of surface water originating in or
near the road right-of-way.
Types of Drainage - can be lateral drainage such as a U-shaped, V-shaped
lined canal (side ditch) or perforated drain canal. It can also be transverse
or cross drainage such as a box culvert or a pipe culvert.
Main Road Components
Y
MASONR
P
RA
- STONE
ITEM 311 - PCCP
RIP
ED
6
GR
ITEM 50
05
M5
• Prior to excavation, all necessary clearing and grubbing in that area shall have
been performed in accordance with Item 100, Clearing and Grubbing
• All excess material, including rock and boulders that cannot be used in the
embankments shall be disposed off as directed.
ITEM 104 - EMBANKMENT
ITEM 104 - EMBANKMENT
• an earth material placed on top of subgrade in order to distribute the wheel
load transmitted to the subgrade. It is commonly used as fill materials to a
roadway construction where it needs to upgrade the existing grade elevation
to suit to actual field conditions when required in the plans.
MATERIALS REQUIREMENT :
Embankments shall be constructed of suitable materials, in consonance
with the following definitions:
Selected Borrow , for Topping – soil of such gradation that all particles
will pass sieve with 75 mm ( 3 inches ) and not more than 15 mass
percent will pass the 0.075 mm ( N0. 200 ) sieve. The materials shall have
a plasticity index of not more than 6 and a liquid limit of not more than
30
2. Unsuitable Material - material other than suitable materials such as:
a. Materials containing detrimental quantities of organic materials,
such as grass, roots and sewerage.
b. Organic soils such as peat and muck.
Compaction Trials
Before commencing the formation of embankments, compaction trials
on areas not less than 10 m wide and 50 m long shall be carry-out to
determine the relationship between types of compaction equipment and
the number of passes required and the method of adjusting moisture
content.
The embankment material shall be compacted in layers until a uniform
density of not less than 95 mass percent of the maximum dry density is
attained as determined by AASTHO T 99 Method C
At least one group of three in-situ density tests shall be carried out
for each 500 m2 of each layer of compacted fill.
ITEM 105 - SUBGRADE PREPARATION
This item shall consist of the preparation of the subgrade for the support of
overlying structural layers and should extend to full width of the roadway.
MATERIALS REQUIREMENT :
Unless otherwise stated in the Contract and except when the subgrade is
in rock cut, all materials below subgrade level to a depth of 150 mm or to
such greater depth shall meet the requirements of Item 104 - Embankment
The target density shall be the mean density of the control strip by
averaging the results of ten in-place density tests taken at randomly
selected sites within the control strips
If the mean density of the control strips is less than 98 percent of the
density of laboratory compacted specimens as determined by testing
procedures appropriate for the material being placed, another control
strip shall be constructed.
ITEM 200 – AGGREGATE SUBBASE COURSE
ITEM 200 – AGGREGATE SUBBASE COURSE
• The subbase is a structural layer which accepts greater compressive stress
than the subgrade and thus reduces the deformation of the pavement under
traffic loading.
Materials Requirements:
- The fraction passing 0.425 mm (No. 40) sieve shall have a Liquid
Limit of not greater than 35
- where the required thickness is more than 150 mm, the aggregate
subbase shall be spread and compacted into two (2) or more layers
of approximately equal thickness and the maximum compacted
thickness of any one (1) layer shall not exceed 150 mm
- one trial section of about 500 m2 shall be made for every type of
material and/or construction equipment/procedure propose for use.
Allowable Tolerances to the Designed Level and
Transverse Slopes for a Compacted Aggregate Subbase
Made of high quality material with a high load bearing capacity and lies
close under the surfacing course material. It provides a relatively non-
frost material on which to provide support for surface course and
sometimes to carry traffic temporarily.
Materials Requirements:
The fraction passing the 0.075 mm (No. 200 sieve shall not be
greater than 0.66 (two thirds) of the fraction passing the 0.425 mm
(No. 40 sieve)
Materials Requirements
This material requires a soil binder to have plasticity for proper bonding of
aggregates and use to provide support for surface course of a roadway.
Material Requirements
Crushed Aggregates
Materials Requirement :
Shall consist of hard, durable particles or fragments of stone or gravel and
sand or other fine mineral particles free from vegetable matter and lumps
or balls of clay and it can be compacted readily to form a firm, stable layer.
Grading Requirements
Materials Requirement :
Prime coat shall be applied only to surfaces which are dry or slightly
moist. No prime coat shall be applied when the weather is foggy or
rainy.
Materials Requirement :
Tack coat shall be applied only to surfaces which are dry or slightly
moist. No tack coat shall be applied when the weather is foggy or
rainy.
Before applying the tack coat , the full width of the surface to be
treated shall be cleaned of loose and foreign materials by means of
power broom or blower and supplemented as necessary by hand
sweeping.
Materials Requirements :
Composition and Quality of Bituminous Mixture
( Job Mix Formula )
The mixture shall have a mass percent air voids with the range of 3 to 5
The mixture shall also have an index of Retain Strength of not less than
70 when tested by AASTHO T 165
Hydrated lime shall be added to the mixture during the mixing operation
in the amount of one-half to one ( 0.5 to 1.0 ) mass percent by dry
aggregate basis.
Construction / Quality Control Requirements :
The mixture shall be placed at a temperature not less than 107 deg.
Centigrade as measured in the truck just prior to dumping into the
spreader.
Samples shall be cut at full depth of the finished pavement for testing
by sawing or core drilling. Sawed and cored samples shall be squared
at least 150 mm x 150 mm or 100 mm diameter, respectively.
At least one, but not more than three (3) samples shall be taken for each
full day’s operation.
If no core samples were taken during the day’s operation, core samples
shall be taken from the completed pavement for every 100 lm. per lane.
no acceptance and final payment shall be made on completed asphalt
pavement unless core test for thickness determination is conducted.
The compacted pavement shall have a density equal to, or greater than 97
mass percent of the density of a laboratory specimen. The asphalt
pavement represented by the cores shall not accepted if the deficiency in
density is more than 2 %.
If the deficiency in the core thickness is more than 5 mm, additional layer
may be permitted in order to meet the designed thickness, however, the
minimum additional asphalt overlay thickness should be dependent on the
minimum capacity of asphalt paver but it should not be less than 50 mm
( 2 inches ).
ITEM 311 - PORTLAND CEMENT C0NCRETE PAVEMENT
1. Portland Cement
Only Type I Portland Cement shall be used unless otherwise provided for
in the Special Provisions.
Different brands or the same brands from different mills shall not be mixed
nor shall they be used alternately unless the mix is approved by the
Engineer.
The use of Portland Pozzolan Cement Type IP meeting the requirements
of AASTHO M 240 / ASTM C 695 shall be allowed, provided that the trial
mixes shall be done and that the mixes meet the concrete strength
requirements.
2. Fine Aggregate
• material passing the 0.075 mm ( No. 200 sieve ) shall not contain
more than (3) mass percent by washing nor more than (1) mass
percent each of clay lumps or shale.
2.36 mm ( No. 8 ) -
1.18 mm ( No. 16 ) 45 - 80
0.600 mm ( No. 30 ) -
0.300 mm ( No. 50 ) 5 - 30
• contain not more than one (1) mass percent of material passing the 0.074
mm ( No. 200 sieve ) by washing nor more than 0.25 mass percent of clay
lumps, nor more than 3.5 mass percent of soft fragments.
• if subjected to five (5) cycles of the sodium sulfate soundness test, the
weighted loss shall not exceed 12 mass percent.
• shall have a mass percent of wear not exceeding 40 when tested to Los
Abrasion machine.
Grading Requirement For Coarse Aggregate
75 3 in. 100 - -
37. 5 1 – ½ in. 25 – 60 35 – 70 -
25 1 in. - 0 – 15 35 – 70
19 ¾ in. 0 – 10 - -
• tie bars shall be deformed bars that are to bent and re-straightened
during construction and shall conform to the requirements of AASTHO M 31 or
M42
• dowel bars shall be plain round bars where one-half of the length shall
be painted with one coat of approved lead or tar paint and shall conform to
the requirements of AASTHO M 31 or M42.
Slump Requirements :
- if vibrated, a slump between 37.5 – 75 mm ( 1-1/2 – 3 inches )
- compressive strength @ 14 days of 24.1 Mpa ( 3500 psi ) for cores taken
Setting of Forms
• forms shall be of steel and of equal depth equal to the thickness of the
pavement at the edge and provided with adequate devices for secure
setting.
• any roadbed, which at the form line is found below established grade,
shall be filled with approved granular materials to grade in lifts of 3 cm.
or less, and thoroughly re-rolled or tamped.
Mixing of Concrete
• the time elapsed from the time the water is added to the mix until the
concrete is deposited in place at the site, shall not exceed 45 minutes
when concrete is hauled in non agitating trucks, nor 90 minutes when hauled in
truck mixers.
• concrete not in place within 90 minutes from the time the ingre-
dients were charged into the mixing drum or that has developed
initial set shall not be used.
Placing of Concrete
• if only finishing equipment is carried on the newly paved lane,
paving in adjoining lanes may be permitted after 3 days.
• concrete shall be thoroughly consolidated by means of a vibrator
inserted in the concrete in a vertical position and should not be
operated longer than 15 seconds in any one location.
• vibrators shall be used for consolidation only, and not be used for
moving concrete horizontally along the forms.
• concrete not in-place within 90 minutes from the time the ingredients
were charged into the mixing drum or that has develop initial set shall
not be used.
Test Specimens
• as work progresses, at least one (1) set consisting of three (3) concrete
beam test specimens, 150 mm x 150 mm x 525 mm or 900 mm shall be
taken from each 330 m2 of pavement, 230 mm depth, or fraction thereof
placed each day.
Joints in Portland Cement Concrete Pavement
Longitudinal Joints
• when shown on the plans and when the adjacent lanes of pavement are
constructed separately, joint steel side forms shall be used which will
form a keyway along the construction.
Transverse Contraction Joint/ Weakened Joint
• the depth of the weakened plane joint should at all times not less
than 50 mm and width should not be more than 6 mm.
Longitudinal joints
width = 6mm, min.
- sawing of any joint shall be omitted if cracks occurs at or near the joint
location prior to the time of sawing.
Transverse Construction Joint
• the portion of each dowel shall be painted with one coat of lead
or tar and be thorouhly coated of an approved lubricant to
prevent the concrete from binding to that portion of the dowel.
Materials Requirements
Stones – consist of rock as nearly rectangular in section as is
practical,except that riprap of Class A may consist of round
natural stones. The stones shall be sound, tough, durable,
dense, resistant to the action of air and water, and suitable
in all respects for the purpose intended.
2.36 mm ( No. 8 ) -
1.18 mm ( No.16 ) 45 - 80
0.600 mm ( No. 30 ) -
0.300 mm ( No. 50 ) 5 - 30
0.150 mm ( No. 100 ) 0 - 10
Mortar
• the horizontal and vertical contact surface between stones shall be
embedded by cement mortar having a minimum thickness of 20 mm.
• sufficient mortar shall be used to completely fill all voids leaving the
face of the stones exposed.
Filter Materials
• when required, the riprap shall be placed on a filter layer to prevent fine
embankment materials to be washed out through the voids of the faces of
stones.
• the grading of the filter material shall be specified on the Plans or in the
Special Provisions.
Class A - 300 mm
Class B - 500 mm
Class C - 600 mm
Class D - 800 mm
• Weepholes shall be placed horizontally at the lowest points
where free outlets for water can be obtained and shall spaced
at not more than 2 meter center to center in a staggered
manner.
Materials Requirements
Stone - unless otherwise shown on the Plans, stones shall have a thickness
of not less than 150 mm, and widths of not less than one and one-half
times their respective thickness, and lengths of not less than one and
one-half times their respective widths. Stones shall be clean, hard,
durable and of good shape and free of depressions and projections
that might weaken or prevent it from being properly bedded. Adobe
stones shall not be used unless otherwise specified.
Mortar
- shall consists of sand, cement and water conforming to there
requirements under Item 405 – Structural Concrete except as to
the of fine aggregate which shall all pass the 2.36 mm (No.8)
sieve, not less than 15 nor more than 40 percent shall pass the 0.3
mm (No. 50) sieve, and not more than 10 percent shall pass the 0.15
mm (No. 100) sieve.
• shall be mixed in the proportion of one part cement to three parts sand by
volume and sufficient water to obtain the required consistency that can be
handled easily and spread with the trowel.
• Mortar that is not used within 90 minutes after the water has been added shall be
discarded. Retempering of mortar will not be permitted.
• Stones shall be laid with their longest faces horizontal in full beds of mortar and
joints shall be flushed with mortar. Large stones shall be used in the corners.
• The exposed faces of individual stones shall be parallel to the faces of the walls
in which the stones are set.
• Weepholes shall be placed horizontally at the lowest points where free outlets
for water can be obtained and shall spaced at not more than 2 meter center to
center in a staggered manner. Other provision of weepholes shall conform to the
requirements of Item 405, Riprap and Grouted Riprap.
• All faces of stones shall be thoroughly cleaned of mortar stains immediately after
stones are laid and while the mortar is fresh.
• The stone masonry shall be protected from the hot or dry weather and
shall be cured by keeping wet for a period of at least three (3) days after
completion.
• The length of the weepholes shall not be less than the thickness of the
walls of the abutment and shall be at least 50 mm diameter PVC or other
pipe material accepted by the Engineer.
Materials Requirements
Stone - the stone shall be cleaned, hard, and durable and shall be
subject to the Engineer’s approval. Adobe stone shall not be used
unless otherwise specified. Stones to be used shall be more than
0.015 cubic meter in volume and not less than 75 percent of the
total volume of rock embankment and shall consist of stones 0.03
cubic meter in volume.
Placing of Concrete:
- One layer of concrete Class “B” shall be placed at the prepared
base prior to placing of stones. Clearance between stones shall
not be less than 2-1/2 inches or the maximum size of concrete
aggregates for Class “B”.
- Concrete Class “B” shall be placed after each layer of stone and shall
be thoroughly consolidated by means of a vibrator inserted in each
in each layer of concrete. In no case shall the vibrator be operated
longer than 10 seconds in any location.
Weepholes
• Weepholes shall be placed horizontally at the lowest points where
free outlets for water can be obtained and shall spaced at not more
than 2 meter center to center in a staggered manner. Other provision
of weepholes shall conform to the requirements of Item 405, Riprap
and Grouted Riprap.
Item 511 – Gabions and Mattresses
M
a
t
t
r
Gabions e
s Gabions
s
GABIONS
- it is made of zinc-coated steel wire and range in size from 1.0 x 1.0 x 1.0
m to 1.0 x 1.0 x 3.0 m. Each basket is secured to an adjacent basket
with a tie wire and is loaded in place with selected rocks ranging from
200 mm to 400 mm in size.
Gabion structures can be subject to various stresses and they must be able to
settle, twist and conform to channel and foundation shifts and changes. At the
same time, gabions must have sufficient strength to contain the weight of the
rocks with which they are filled and of additional filled gabions that may be
placed upon them, as well as to resist the impact force of high velocity
currents and soil pressure.
Applications:
• Slope reinforcement
• Shore Protection
• Bridge abutments
• Erosion Control
Gabions shall be constructed of wire mesh and shall be supplied in
various lengths and heights. A double twisted wire mesh
container of various sizes, uniformly partitioned into internal
cells , interconnected with other units and filled with stones to
form flexible, permeable, monolithic structures such as retaining
walls, spur dikes, sea walls, revetments and channel linings for
erosion control.
The lengths shall be multiples of 2,3 or 4 times the width of the gabion
and height shall be 0.50 m to 1.00 m and the horizontal width shall
not be less than one-meter.
Mattresses are double twisted wire mesh container uniformly partitioned into
internal cells with relatively small height in relation to other
dimensions, having smaller mesh openings than the mesh used for
gabions. It is generally used for river bank protection and channel
linings.
• The nominal and the minimum thickness of PVC coating shall be 0.50 mm and
0.38 mm, respectively
• The PVC coating shall not show cracks or breaks after the wires are twisted in the
fabrication of the mesh.
Lacing Wire and Stiffener - shall be made of wire having the same
coating material as the double-twisted wire mesh
conforming to Specification requirements of ASTM 641, A
856/A 856 M or A 809
Gabion Mattresses
Metallic PVC Metallic PVC
Coated Coated Coated Coated
• Rock used in the gabions and mattresses shall consist of hard, durable
rock pieces that will not deteriorate when submerge to water or exposed
to severe weather conditions.
• No rock size shall exceed 2/3 the mattress depth and at least 85% by
weight of the stone shall have a size greater than 80 mm. No stones
shall be able to pass through the mesh.
• Rock shall have a sodium sulfate soundness loss of not more than 9%
after five (5) cycles.
Construction / Quality Control Requirements
Strength Requirements
Strength Requirements