Chapter Four
Chapter Four
INSTITUTE OF TECHNOLOGY
DEPARTEMENT OF CIVIL ENGINEERING
CHAPTER 4
Quantity surveying
ABADI TIEUMAY
Introduction
In a civil engineering activity, the owner
Promises to pay the contractor an amount
for the work that he does.
2
To estimate how much a civil
engineering project may cost, the actual
quantities of materials, labor &
equipment etc that is needed for the
construction work must be calculated at
the beginning of the work.
4
Measurement of civil works
Measurement of civil works includes;
the billing of each trade of work either from
drawings or the building itself for defining the
extent of works under each trade.
5
Specification Worksheet (BOQ form)
It is the format which is used in a bill of quantity
to list (include) a short description of the
specification along with its measuring unit,
quantity and unit prices to determine the total
cost for each trade of item.
6
There are four clearly defined steps
in preparation of Bill of Quantities:
1. Taking off
2. Squaring
3. Abstracting
4. Writing the final Bill of Quantity
7
Taking off
Is the process of measuring or scaling
dimensions from drawings and recording all
dimensions in an easily understood format.
This is coupled with the descriptions in the
drawings and specifications.
The standard form used for entering the
dimensions taken or scaled from drawings
to determine the accurate quantity in each
trade of work, except reinforcement steel, is
called Take Off Sheet or Dimension Paper.
8
Column 1 is called the timing
column and is used for stating the
number of times an item occurs.
9
Column 3 is called squaring column. The
stated dimensions in column 2 are
multiplied to determine the quantity of the
work either in m, m2, m3 or in Pcs. or No.
Column 4 is called description column
and description of the work item is briefly
stated.
10
11
Squaring:
The process of multiplying, adding, subtracting
or dividing the recorded dimensions for the
purpose of obtaining linear measures, areas,
volumes etc
The dimensions entered in Column 2 are
squared or cubed as the case may be,
multiplied by the timing factor, and the result
entered in Column 3.
All squared dimensions should be carefully
checked by another person before abstracting.
Use two decimal places.
12
Abstracting:
The squared dimensions are transferred to
abstract sheets and all similar dimensions
are collected in the same category to obtain
the total quantity of each item.
Writing the Final Bill
is the process of collecting and entering to an
accepted format all the measured quantities, by
trade and work type, and filling in the total
amount by multiplying with the unit rates.
13
BOQ
14
A typical building project will have the
following work items.
15
A. Substructure
1.Excavation and earth work
1.1. site clearing
to remove the top 20-30cm soil
a working space of 1m is required on each side
Measured in m2
1.2. bulk excavation
for building underground structures
Working space of 25cm is required on each side
Measured in m3 if depth of excavation is more
than 30cm.
16
1.3. Pit excavation
For isolated footing
Expressed in m3
Working space of 25cm is required on
each side
1.4. trench excavation
For foundation wall
Expressed in m3
working space of 25cm is required on
each side
17
1.5. back fill
Net volume to be filled
Working spaces need to be filled
Total excavated= site clearance+ pit
excavation+ bulk excavation+ trench
excavation
Cart away= total excavated – back fill
It is expressed in m3
18
2. Concrete work
2.1. lean concrete
To protect structural concrete from
damage (under footing pads and
foundation wall)
It expressed in area, m2
2.2. concrete for structures
for footing, grade beam, ground floor slab
Overlap should be deducted
Measured in m3
19
2.3. formwork
A temporary structural element, which
supports slabs, beams in casting concrete.
Measured in m2
2.4. reinforcement
measured in kg
Length of the bar is taken from the drawing
and multiplied by weight per unit length to
get the weight of the bar.
e.g. weight per length=(d2 *0.617)/100
for Ф6= 0.222kg/m
20
3. Masonry work/Stone work
For foundation wall (measured in m3)
hard core (measured in m2)
21
B. Superstructure
1. Concrete work
1.1. concrete
For slabs, beams, columns, staircase
Measured in m3
1.2. formwork
Measured in m2
1.3.reinforcement
Expressed in kg.
22
2. Masonry works
Measured in m3
Commonly used for walls of buildings.
3. Roofing
Roof cover is measured by area(m2)
Items like downpipes are measured by
length(m)
23
4. Carpentry and joinery work
Carpentry: -work on timber intended for
structural purposes eg columns, beams,
truss etc
Joinery: - work on timber intended for
finishing purposes eg floor finishes, doors
and windows, ceilings, Cupboard etc
24
5. Steel structural work
for beam, column, slab, truss, connections
etc
Usually measured in weight (kg)
6. Metal works
Includes aluminum and iron works
For door and window frames
Measured in area
25
7. finishing work
Plastering
Measured by area (m2)
Floor and wall finish
Measured by area (m2)
Painting
Shall be measured in area (m2)
Special application to the edges should be
measured in length.
8. Glazing
Glazing shall be measured in area(m2)
26
THANK YOU!
27