Pe 511
Pe 511
What is a Project?
• A project is “a unique aim to produce a set of deliverables within clearly specified time, cost and quality constraints”.
▪ Are unique in nature. They do not involve repetitive processes. Every project undertaken is different from the last, whereas operational activities
▪ Have a defined timescale. Projects have a clearly specified start and end date within which the deliverables must be produced to meet a specified
customer requirement.
▪ Have an approved budget. Projects are allocated a level of financial expenditure within which the deliverables must be produced to meet a
▪ Have limited resources. At the start of a project an agreed amount of labor, equipment and materials is allocated to the project.
▪ Involve an element of risk. Projects entail a level of uncertainty and therefore carry business risk
▪ Achieve beneficial change. The purpose of a project, typically, is to improve an organization through the implementation of business change.
• PMI (Project Management Institute) defines a project as “a temporary aim undertaken
to produce a unique product, service, or result” (PMBOK ® Guide, Project Management
Institute, 2008, p. 5).
• This means that a project is done only one time. If it is repetitive, it’s not a project. A
project should have definite starting and ending points (time), a budget (cost), a clearly
defined scope—or magnitude—of work to be done, and specific performance
requirements that must be met. “Should” because seldom does a project conform to
the desired definition. These constraints on a project, are referred to as the PCTS
targets.
The relationship among the PCTS constraints can be written as follows:
C = f(P, T, S)
In words, this says, “Cost is a function of Performance, Time, and
Scope.” Graphically, it can be represented as a triangle, in which P, C,
and T are the sides and S is the area.
P
P C
C
S S
T
T
• Dr. J. M. Juran, the quality guru, also defines a project as a problem scheduled
for solution. This definition reminds us that every project is conducted to solve
some kind of problem for a company.
However, It must be caution that the word “problem” typically has a negative
meaning, and projects deal with both positive and negative kinds of problems.
For example, developing a new product is a problem, but a positive one, while
an environmental cleanup project deals with a negative kind of problem.
What is Project Management?
• Planning is the systematic process of establishing a need and then working out the best
way to meet the need, within a strategic framework that enables you to identify
priorities and determines your operational principles.
• Planning means thinking about the future so that you can do something about it now.
This doesn’t necessarily mean that everything will go according to plan. It probably
won’t. But if you have planned properly, your ability to adjust, without compromising
your overall purpose, will be that much greater.
DIFFERENT KINDS OF PLANNING
• “Planning” is a big term that includes a number of different kinds of activities. It is possible to plan at the
strategic level, at the activity or operation level, to plan for an organisation, or for a programme or for a
project. The two main kinds of planning are:
• Strategic planning and business/action/operational planning
Strategic planning/strategic framework
• Strategic planning, or developing a strategic framework, is about the bigger picture.
• Organisations often get so caught up in everyday problems that they do not think about the big picture. They
are too busy planning “to do things”, something that falls under business/action/operational planning.
• It is through strategic planning that an organisation develops a strategic framework. This framework helps the
organisation determine its priorities and the strategies that are likely to help it achieve its vision of the future.
• A strategy is an overall approach, based on an understanding of the broader context in which you function,
your own strengths and weaknesses, and the problem you are attempting to address.
• A strategy gives you a framework within which to work, it clarifies what you are trying to achieve and the
approach you intend to use. It does not spell out specific activities.
Where do you go with strategic planning?
• Strategic planning enables a development organisation to:
• Analyze the situation or context in which it is operating (social, political and economic) so
that it understands the context and is able to formulate a vision.
• Identify the problem or problems within the situation that the organisation believes it is well-
placed to address.
• Reflect on its value system in order to create parameters (a frame) for its activities. To set
goals for itself.
• Formulate a vision and mission statement based on its problem analysis and identification.
• Analyze its strengths and weaknesses in addressing the identified problem (a SWOT analysis
for a method).
• Identify opportunities and threats in the environment that may affect its work (both a SWOT
Analysis and a PEST Analysis)
• Priorities what it needs to do.
• Review strategic options for achieving its goals and select the most appropriate.
Project Execution
• This phase involves the execution of each activity and task listed in
the Project Plan. While the activities and tasks are being executed, a
series of management processes are undertaken to monitor and
control the deliverables being output by the project.
• This includes the identification of changes, risks and issues, there
view of deliverable quality and the measurement of each deliverable
being produced against the acceptance criteria.
• Once all of the deliverables have been produced and the customer
has accepted the final solution, the project is ready for closure.
Project Closure
• Project Closure involves releasing the final deliverables to the
customer, handing over project documentation, terminating supplier
contracts, releasing project resources and communicating the closure
of the project to all stakeholders. The last remaining step is to
undertake a Post Implementation Review to quantify the overall
success of the project and list any lessons learnt for future projects.
Chapter 2 #
Project Leadership
• Vance Packard, in his book The Pyramid Climbers. He define
leadership as, “the art of getting others to want to do something that
you believe should be done”.
• Leading a project is not the same as leading a department. A project
by definition is unique; it has never been done before. As a result, the
end product and the process for producing it are never fully specified
in advance. Therefore, the project leader lives in an environment of
constant uncertainty.
Planning
• Planning is quite simply answering questions shown in the Figure.
They may be called the “who, what, when, why, how much, how
long?”.
Centralization
• Who makes the decisions in an organization? If decision-making
power is concentrated at a single point, the organizational structure is
centralized. If decision-making power is spread out, the structure is
decentralized.
Specialization
• Also known as division of labor, specialization is the degree to which
activities or tasks in an organization are broken down and divided into
individual jobs. High specialization can be beneficial for an
organization, as it allows employees to become “masters” in specific
areas, increasing their productivity as a result. However, low
specialization allows for more flexibility, as employees can more easily
tackle a broader array of tasks (as opposed to being specialized for a
single task).
Formalization
• Similar to specialization, formalization deals with how jobs are structured
within an organization. The key differentiator here is that formalization
also takes into account the degree to which an employee’s tasks and
activities are governed by rules, procedures, and other mechanisms.
• A formal organizational structure seeks to separate the individual from
the role or position, as the role or position stays the same regardless of
who’s holding it.
• An informal organization, on the other hand, places more value on the
individual. It allows for the evolution of a role or position based on an
individual’s preferences, skill set, etc., and places less importance on what
team or department that individual is part of.
Chapter 5 #
Organisational chart
• Is a diagram showing the organisational structure of the organisation.
• An Organisational Chart is a diagram which sets out the job titles of
the various people that work in the company and who they are
responsible to.
• This usually involves the CEO (Chief Executive Officer) or Directors
sitting at the top of the diagram, the most junior staff at the bottom
and the other staff in between depending on their seniority.
Organizational structure – Line
• The traditional line structure is organized in
such a way that a president or CEO (Chief
Executive Officer) is at the top. Then there are
the directors or VPs (Vice-Presidents) of specific
areas, followed by managers, and so on, until
the operational personnel.
• It’s a very rigid structure, with little information
exchange, typical of bureaucratic companies in
which there is little collaboration.
• Nowadays it’s unusual, but in the past it was
practiced in military, religious, and even
academic organizations. In this way, one area
doesn’t interfere with the work of another, and
the staff only obeys the ‘orders’ of the
immediate superior.
Organizational structure – Functional
• The functional organizational structure derives from the
line structure; the difference is that employees in an area
need to report to all the directors.
• For instance, an employee from the finance department
may be called upon by the HR (Human Resource)
manager to handle a matter related to this area. The IT
(Information Technology) manager may do the same, and
so forth.
• It’s a way to avoid centralization and excessive
specialization in tasks in your area.
• Today this is the most used structure in many companies
and organizations, but this doesn’t mean it’s the best one.
• Everything will depend on the relationship between
managers and, especially, on the appropriate use of IT to
aid in internal communication.
• This organizational structure example is suitable for small
companies, such as manufacturing, hotels, medium-sized
car repair shops, medical clinics, or other types of
business where informal structures allow functional
control over employees without generating conflicts
between managers.
Organizational structure – Line-and-staff
• It’s similar to the line structure,
except that in this case the staff
advises, gives opinion, makes reports,
authorizes and supports the
organization.
• Organizational structure of this type
include insurance companies,
engineering firms, law firms,
regulatory agencies, etc.
• In other words, organizations that
need isolated technical advice to
assist employees who handle or
manage the day-to-day operations on
the front line.
Project-based structure
• Highly dynamic and creative
companies – such as software
developers, architecture firms, special
industrial equipment installation
projects and event organization
companies – typically use this
structure. It’s characterized by a series
of specialized employees, ready to
compose a work team as needed.
• In each project, these collaborators
report to a different leader. Once they
complete the project, a manager
assigns them a new project and leader.
Matrix structures
• This structure is widely used both by
companies that are constantly launching
new products and marketing campaigns,
for example, and by companies that have
project-based structures, but also believe
that functional supervision is necessary
and important.
• Each project must occur independently.
However, it’s important to have a senior
manager of each department (finance,
operations, HR, marketing, etc.) to check
if everything is in accordance with the
company’s policies and level of services.
Chapter 6 #
Creating the Project Risk Plan
knowledge, or understanding.
Risk is actually a measure of the amount of uncertainty that exists. It’s directly tied
to information.
In the world of project management, risk relates primarily to the extent of your
ability to predict a particular outcome with certainty.
No information
Some information
Total certainty
Relative uncertainty
Total uncertainty
• Threat The effects of risk can be positive or negative. Positive effects
of risk are often referred to as opportunities.
• Threats are the negative—or “downside”— effects of risk. Threats are
specific events that drive your project in the direction of outcomes
viewed as unfavorable (e.g., schedule delays, cost overruns, and
inferior product performance).
Managing Risk
• Project risk management is “the process of conducting risk
management planning, identification, analysis, response planning,
and monitoring and control on a project.”
The Six-Step Process
• Step 1: Make a List
Brainstorm. Making a list of potential risks to the project should not be an analysis
but a formal brainstorming session, when all ideas are captured.
• Steps 2 & 3: Determine the Probability of Risk Occurrence and Negative
Impact.
These two steps allow to prioritize all identified threats to the project and helps
determine how much time, effort, staff, and money should be devoted to preventing
or qualifying each.
How probable is it that each risk will become a reality?
Use a High-Medium-Low (HML) scale and apply it to the list of risks.
If the risk becomes a reality, how badly will it damage the project.
Risk Probability Impact
A M L
B M M
C L L
D H H
• Step 4: Prevent or Mitigate the Risk
Some risks can be prevented; others can only be mitigated.
• Step 5: Consider Contingencies
Contingencies represent the specifications that will be taken if the risk occurs.
Here, the question “If the risk becomes reality, what will we do”?
• Step 6: Establish the Trigger Point
The trigger point is often the most important element of the project risk plan.
There is a direct relationship between the trigger point and the contingencies.
It is a judgment call meant to maximize the value of the predetermined
contingency by implementing it at the optimal time.
Establishing Reserves
activity start).
probabilistic).
• The primary reason for scheduling a project is to ensure that the deadline
can be met.
• Each activity is defined by its duration (time to complete the activity) and
its predecessors (activities that must be completed before the activity can
start).
• Analyze and break down the project in terms of specific activities and/ or
events.
• Determine the interdependence and sequence of specific activities and
prepare a network.
• Assign estimates of time, cost or both to all the activities of the network.
• Identify the longest or critical path through the network.
• Monitor, evaluate and control the progress of the project by re-planning,
rescheduling and reassignment of resources.
• The central task in the control aspect of these models is to identify
the longest path through the network. The longest path is the critical
path because it equals to the minimum time required to complete the
project.
• All other paths other than the critical path (i.e. non-critical or slack
paths) offer flexibility in scheduling and transferring resources,
because they take less time to complete than the critical path.
ADVANTAGES OF CRITICAL PATH ANALYSIS
There are a number of advantages in using critical path analysis.
• It allows for a comprehensive view of the entire project. Because of the sequential and
concurrent relationships, time scheduling becomes very effective.
• Identifying the critical activities keeps the executive alert and in a state of awareness, with
alternative plans ready in case these are needed.
• Breaking down the project into smaller components permits better and closer control.
• Critical path analysis offers economical and effective system of control based on the
principle of management by exclusion i.e. need for corrective action arises only in
exceptional situations and in most of other cases, performance is in conformity with the
plans.
• It is a dynamic tool of management which calls for constant review, a reformulation of the
network, and finding the current path of relevance and optimum resources allocation.
Definitions of Network Terms
• ACTIVITY An activity always consumes time and may also consume resources.
Examples include paperwork, labor, negotiations, machinery operations, and lead
times for purchased parts or equipment.
• CRITICAL A critical activity or event is one that must be achieved by a certain
time, having no latitude (slack or float) whatsoever.
• CRITICAL PATH The critical path is the longest path through a network and
determines the earliest completion of project work.
• EVENTS Beginning and ending points of activities are known as events. An event
is a specific point in time. Events are commonly denoted graphically by a circle
and may carry identity nomenclature (e.g., words, numbers, alphanumeric codes).
• MILESTONE Milestones are events that represent a point in a project of special
significance. Usually, it is the completion of a major phase of the work. Project
reviews are often conducted at milestones.
• NETWORK Networks are called “arrow diagrams.” They provide a graphical
representation of a project plan showing the relationships of the activities.
• Network Diagrams is a sequence in which work is performed, task A is
done before B, while Task C is done in parallel with them.
A B C
D
The first step in CPM/PERT is to construct a project
network.
C
The first node represents the start of the activity and the
second node represents the end of it.
In the project network each activity is represented by an arc connected by two nodes.
The first node represents the start of the activity and the second node represents the end of it.
E
Consider the activity in the table, drew the network and find the critical
path.
Activity Immediate
predecessor
s
A -
B -
E 5 J
C - 5 8
2 5
D B N
A K
E A F
1 L
F A B 3 G 66 9
G B D
H
C
H C,D 4 7 M
I C,D 44 I
J E
K F,G,H
L F,G,H
M I
N J,K
Consider the activity in the table, drew the network and find the
critical path and the completion time .
E (7) 5 J (5)
5 8
Activity Immediate Duration(da 2 5
predecessor ys) A (2) N (8)
s F(3)
K (4)
A - 2 ES
1 B(5) L(3)
B - 5 3 G(3) 66 9
C - 4 C(4) D(5) H (6)
D B 5 4 7 M (12)
E A 7 44 I (2)
F A 3
G B 3
H C,D 6 1-2, 2-5, 5-8, 8-9 =2+7+5+8 = 22
1-2, 2-6, 6-9, = 2+3+3 = 8 Determine earliest
I C,D 2
1-2,2-6,6-8,8-9 = 2+3+4+8 = 17 start time Es of all
J E 5 1-3, 3-6, 6-9 = 5+3+3 = 11 the nodes forward
K F,G,H 4 1-3, 3-6, 6-8, 8-9 =5+3+4+8 = 20 pass v
L F,G,H 3 1-3, 3-4, 4-6, 6-9 = 5+5+6+3 = 19 Determine latest
M I 12 1-3, 3-4, 4-6, 6-8,8-9 = 5+5+6+4+8 =28 completion time Ec
N J,K 8 1-4, 4-6, 6-9 = 4+6+3 = 13 backward pass
1-4, 4-7, 7-9 = 4+2+12 = 18
8 Esj = Maxi(Esi + Dij)
15
Lc 2 J (5) 20 I for starting activity
E (7) 9
55 8 J for ending activity
2 20
Es 2 5 N (8)
0 A (2) F(3) For node 1 Esj =0
0 28 For node 2 Esj = 0 + 2 = 2
K (4)
28 For node 3 Esj= 0+5=5
1 B(5)
5 33 L(3) For node 4 we have 2
G(3) 6 16 9
5 6 options
16
C(4) Esj= 0+4=4 or 5+5 =10
D(5) H (6)
We chose Max. 10 ….
4 7 M (12)
4
4 I (2)
10
16 Lci = Minj(Lcj-Dij)
10
12 For node 8 Lci=28-8=20
For critical path we need this conditions
1- Esi = Eci
2- Esj=Ecj
3- Esj – Esi = Ecj – Eci = Dij
• Calculate the total float time and the free float time for the non critical path.
• Total float is the amount of time that a completion time of an activity can be delayed with out affecting
the project completion time.
• Tfij = Lcj - Esi – Dij
• Free float is the amount of time that the activity completion can be delayed with out affecting the
earliest start time of immediate successor activity in the network
• Ffij = Esj – Esi -Dij
• Any critical activity will have zero total float and zero free float
E
SWOT analysis
• SWOT analysis is a framework used to evaluate a company's
competitive position by identifying its strengths, weaknesses,
opportunities and threats.
• It is a foundational assessment model that measures what an
organization can and cannot do, and its potential opportunities and
threats.
• SWOT analysis is a basic, analytical framework that assesses what an
entity — usually a business, although it can be a place, industry or
product — can and cannot do, for factors both internal and external.
• Using environmental data to evaluate the position of a company, a
SWOT analysis determines what assists the firm in accomplishing its
objectives, and what obstacles it must overcome or minimize to
achieve desired results:
where the organization is today, and where it may go
• For example, back in 2015, The Coca-Cola Company noted strengths
like its well-known brand name, vast distribution network and
opportunities like emerging markets, but it also noted weaknesses
and threats such as foreign currency fluctuations, a growing taste for
"healthy" beverages and the subsequent competition from providers
of such beverages. Coca-Cola took steps to address these concerns,
ramping up its marketing, advertising and promotional activities, and
expanding into other beverage categories. As a result, within a year,
its dividend-per-share rose from 33 to 35 cents, and its stock, which
was hovering around $39 per share, climbed to $46. It's fallen since,
but remains up about 13 percent over the past three-year period.
• Strengths describe what an organization
bests at and separates it from the
competition: a strong brand, loyal customer
base, a strong balance sheet, unique
technology and so on. For example, a privet
fund may have developed a exclusive trading
strategy that returns market-beating results.
It must then decide how to use those results
to attract new investors.
• Weaknesses stop an organization from Strength Weaknesses
performing at its optimum level. They are Internal
areas where the business needs to improve
to remain competitive: higher-than-industry-
average turnover, high levels of debt, an
inadequate supply chain or lack of capital.
• Opportunities refer to favorable external
factors that an organization can use to give it External
a competitive advantage. For example, a car Opportunity Threats
manufacturer can export its cars into a new
market, increasing sales and market share, if
a country cuts tariffs.
• Threats refer to factors that have the
potential to harm an organization. For
Al’s Ice Cream: The Case for Expansion
• Al’s Ice Cream is a exclusively owned ice cream shop that its founder
Al’s creates handcrafted ice cream with local ingredients. Al’s
company is profitable with strong margins on its premium-priced
cones, but Al is wondering if the single store approach isn’t limiting
his growth.
Strengths Weaknesses
Superior product with unique flavors difficult to
duplicate Limited market penetration due to a single location
Strong sales and generous profit margin Limited capital for expansion